|
|
Line 2: |
Line 2: |
| | number = ML17201A101 | | | number = ML17201A101 |
| | issue date = 08/04/2017 | | | issue date = 08/04/2017 |
| | title = 07/13/2017 Summary of Meeting with PSEG Nuclear LLC to Discuss Potential License Amendment Request Technical Specification Task Force Traveler-542 for Hope Creek Generating Station | | | title = Summary of Meeting with PSEG Nuclear LLC to Discuss Potential License Amendment Request Technical Specification Task Force Traveler-542 for Hope Creek Generating Station |
| | author name = Regner L | | | author name = Regner L |
| | author affiliation = NRC/NRR/DORL/LPLIV | | | author affiliation = NRC/NRR/DORL/LPLIV |
Letter Sequence Meeting |
---|
CAC:MF9877, Reactor Pressure Vessel Water Inventory Control (Open) |
|
MONTHYEARML17191A3442017-07-10010 July 2017 PSEG Handouts for July 13, 2017 Public Meeting on TSTF-542 Proposed License Amendment Request Project stage: Meeting ML17194A6912017-07-12012 July 2017 Revised PSEG Handouts for July 13, 2017 Public Meeting on TSTF-542 Proposed License Amendment Request Project stage: Meeting ML17194A6922017-07-12012 July 2017 Insert Page for PSEG Handouts for July 13, 2017 Public Meeting on TSTF-542 Proposed License Amendment Request Project stage: Meeting ML17201A1012017-08-0404 August 2017 Summary of Meeting with PSEG Nuclear LLC to Discuss Potential License Amendment Request Technical Specification Task Force Traveler-542 for Hope Creek Generating Station Project stage: Meeting 2017-07-12
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24155A1992024-06-0303 June 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Meeting Summary ML24068A0742024-03-13013 March 2024 Summary of February 27, 2024, Pre Submittal Public Meeting with Pseg Nuclear Llc to Discuss Future Amendment Regarding Improved Technical Specification Conversion ML24068A0862024-03-13013 March 2024 February 27, 2024, Summary of Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Future Amendment Regarding 24 Month Fuel Cycle and Surveillance Interval Extension ML23300A0382023-11-0101 November 2023 Summary of Hope Creek Oct 24, 2023, Pre Submittal Public Meeting with PSEG Nuclear LLC to Discuss Future Amendments Regarding Improved TS Conversion 24 Month Fuel Cycle & Surveillance Interval Extension & Safety Relief Valve Lift Setpoint C ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23146A1012023-05-31031 May 2023 Summary of May 25, 2023, Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Reduction of the Sites Exclusion Area Boundary ML22325A3052022-11-22022 November 2022 Summary of November 17, 2022, Pre Submittal Public Meeting with PSEG Nuclear LLC to Discuss Threshold Determination on Transferring Ownership of Portions of the Site ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML21092A1502021-04-15015 April 2021 Summary of Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss License Amendment Regarding Ultimate Heat Sink Technical Specification Changes ML21064A0962021-03-0909 March 2021 Summary of 3/4/2021 Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Adoption of ASME Section XI Code Cases N-878, N-879, and N-880 at Hope Creek Generating Station and Salem Nuclear Generating Station ML20308A3692020-11-19019 November 2020 Summary of Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Replacement of Source and Intermediate Range Neutron Monitors with Numac Wide Range Neutron Monitoring System ML19317E6762019-11-26026 November 2019 Summary of November 12, 2019, Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Proposed License Amendment to Adopt 10 CFR 50.69 ML19109A1282019-04-16016 April 2019 and Hope Creek Generating Station: Summary of Public Webinar Meeting on April 10, 2019 ML19045A4702019-02-15015 February 2019 Summary of Closed Teleconference Meeting with PSEG Nuclear LLC and General Electric-Hitachi Nuclear Energy to Discuss a General Electric Part 21 Issue ML18156A4242018-06-0505 June 2018 Annual Assessment Meeting, 5/30/18 Meeting Summary ML18044A9942018-02-26026 February 2018 Summary of Meeting with PSEG Nuclear LLC Regarding Planned Submittal of License Amendment Request to Revise Technical Specifications Regarding Extending the Allowed Outage Time for the Inverters ML18036A6142018-02-21021 February 2018 Generation Station-Summary of January 24, 2018, Meeting with PSEG Nuclear LLC on Planned Submittal of License Amendment Request to Revise Technical Specifications Regarding Diesel Generator Extended Allowed Outage Time ML17201A1012017-08-0404 August 2017 Summary of Meeting with PSEG Nuclear LLC to Discuss Potential License Amendment Request Technical Specification Task Force Traveler-542 for Hope Creek Generating Station ML17164A1742017-06-20020 June 2017 Summary of May 31, 2017, Meeting with PSEG Nuclear LLC to Discuss a Potential Measurement Uncertainty Recapture Power Uprate for Hope Creek Generating Station ML17102A7772017-04-10010 April 2017 Summary of Annual Assessment Meeting with PSEG ML16362A2022017-01-24024 January 2017 Summary of Meeting with PSEG Nuclear LLC Regarding Potential Measurement Uncertainty Recapture Power Uprate ML17023A1452017-01-23023 January 2017 Summary of Teleconference with PSEG Regarding Hope Creek HPCI ML16347A3932017-01-0505 January 2017 Summary of Teleconference with PSEG Nuclear LLC Regarding Planned License Amendment Request Regarding Change to the Salem Nuclear Generating Station-Hope Creek Generating Station Emergency Action Levels (MF8875, MF8876, and MF8877) ML16201A0292016-08-15015 August 2016 Summary of June 21, 2016, Teleconference with PSEG Nuclear LLC on the Upgrade of the Hope Creek Generating Station Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring System ML16217A4552016-08-15015 August 2016 Summary of July 19, 2016, Teleconference with PSEG Nuclear LLC on the Upgrade of Hope Creek Generating Station'S Power Range Neutron Monitoring System ML16141A2402016-06-16016 June 2016 Summary of April 19, 2016, Teleconference with PSEG Nuclear LLC on the Upgrade of Hope Creek Generating Stations'S Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring System ML16113A3962016-04-29029 April 2016 Summary of Teleconference with PSEG Nuclear LLC on the Upgrade of Hope Creek Generating Station'S Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring System ML16096A2222016-04-0505 April 2016 March 30, 2016, Summary of Annual Assessment Meeting with PSEG - Salem Nuclear Generating Station & Hope Creek Generating Station ML16064A0052016-03-22022 March 2016 Summary of Teleconference with PSEG Nuclear LLC on the Upgrade of Hope Creek Generating Station'S Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring System ML16116A2352016-03-15015 March 2016 Meeting Summary for Public Teleconference Between PSEG LLC and the Nuclear Regulatory Commission, Hope Creek Generating Station - Power Range Neutron Monitoring System Digital Upgrade LAR HCGS Numac Upgrade - Open Item DOC-0006-2118 Ri ML15104A1492015-04-14014 April 2015 Hope, Summary of Annual Assessment Meeting with PSEG ML15043A2392015-03-24024 March 2015 January 29, 2015, Summary of Pre-licensing Meeting with PSEG Regarding Digital Upgrade of Power Range Neutron Monitor (Prnm) ML14224A1332014-08-26026 August 2014 Summary of August 12, 2014, Pre-Licensing Meeting with PSEG Regarding Digital Upgrade of Power Range Neutron Monitor ML14100A0242014-04-10010 April 2014 Salem and Hope Creek - Summary of Annual Assessment Meeting with PSEG ML13364A2422014-02-0404 February 2014 9/11/2013 - Summary of Pre-Licensing Meeting with PSEG Regarding Digital Upgrade of Power Range Neutron Monitor ML13099A3242013-04-0909 April 2013 Salem & Hope Creek - Summary of Annual Assessment Meeting with PSEG ML12144A3312012-05-23023 May 2012 Summary of Meeting at the PSEG to Discuss the Nrc'S Assessment of Pseg'S Safety Performance at Salem & Hope Creek for 2011 ML1129700652011-10-21021 October 2011 Summary of PSEG Drop-in Visit, 9-28-2011 and Slides ML11292A1612011-10-20020 October 2011 Summary of Meeting with Beyond Nuclear Regarding Their 10 CFR 2.206 Petition to Suspend Operating Licenses of General Electric Mark I Boiling Water Reactors ML11181A1772011-06-30030 June 2011 June 29, 2011 Summary of Public Meeting to Discuss Observations and Lessons Learned During the Hope Creek Nuclear Generating Station Application of the Nuclear Energy Institute'S Nuclear Safety Culture Assessment Process ML11166A1342011-06-22022 June 2011 Meeting Summary with the Beyond Nuclear Petitioners Regarding Their 2.206 Petition to Suspend Operating Licenses (Ols) of General Electric (GE) Boiling Water Reactors (Bwrs) Mark I (Bwrs) ML11138A3212011-06-0808 June 2011 May 9, 2011, Summary of Telephone Conference Call Held Between NRC and PSEG Nuclear, LLC, Concerning Status of Hope Creek Drywell Air Gap Drains ML11137A0762011-06-0202 June 2011 Summary of Telephone Conference Call Held on May 11, 2011, Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning the Hope Creek License Condition for the Drywell ML1114002132011-05-20020 May 2011 Summary of Annual Assessment Meeting for Salem and Hope Creek ML11105A0372011-05-0404 May 2011 Summary of Telephone Conference Call Held on March 25, 2011, Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning Findings on the Hope Creek Generating Station Gas Turbine ML1100700302011-03-25025 March 2011 Summary of Telephone Conference Call Held on August 30, 2010, Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning Questions Pertaining to the Hope Creek Generating Station License Renewal Application ML1034909292011-02-0909 February 2011 Summary of Telephone Conference Call Held on November 18, 2010, Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning Findings on the Hope Creek Generating Station Recent Outage ML1100501592011-02-0909 February 2011 September 15, 2010 Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning Questions Pertaining to the Hope Creek Generating Station License Renewal Application ML1031907452010-11-19019 November 2010 Summary of Telephone Conference Call Held on 10/21/10 Btw the USNRC and PSEG Nuclear, LLC, Concerning Hope Creek Generating Station, License Renewal Application, Environmentally Assisted Fatigue Analysis ML1025903832010-11-0202 November 2010 September 09, 2010, Summary of Telephone Conference Call Held Between NRC & PSEG Concerning a LRA Supplement Pertaining to the Hope Creek Generating Station, License Renewal Application 2024-06-03
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 4, 2017 Mr. Peter P. Sena, Ill President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P.O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SUMMARY
OF JULY 13, 2017, MEETING WITH PSEG NUCLEAR LLC TO DISCUSS POTENTIAL LICENSE AMENDMENT REQUEST RE: TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER-542 FOR HOPE CREEK GENERATING STATION (CAC NO. MF9877)
Dear Mr. Sena:
On July 13, 2017, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of PSEG Nuclear LLC (PSEG or the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, MD. The purpose of the meeting was to discuss a proposed license amendment request (LAR) to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-542, "Reactor Pressure Vessel Water Inventory Control," Revision 2, for Hope Creek Generating Stations (Hope Creek). The meeting notice and agenda, dated June 29, 2017, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML17194A699. A list of attendees is enclosed.
The licensee presented information in draft documents available in ADAMS at Accession Nos. ML17191A344, ML17194A691, and ML17194A692. The licensee discussed its proposed variations from the TSTF-542 recommended changes to the technical specifications (TSs). The PSEG staff stated that these variations would not affect the applicability of the Traveler or the NRC staff's safety evaluation. However, because Hope Creek TSs are based on an older version of the Standard Technical Specifications, NUREG-0123, "Standard Technical Specifications for General Electric Boiling Water Reactors," the Traveler is not directly applicable. TSTF-542 is based on the improved Standard Technical Specifications in NUREG-1433, "Standard Technical Specifications - General Electric Plants (BWR/4)." The variations provided by PSEG account for differences between the Hope Creek TSs and the TSTF-542 recommended TS changes. The PSEG staff stated its intent to submit a LAR to adopt TSTF-542 by the end of August 2017, with an issuance date requested to allow implementation prior to the fall 2019 refueling outage.
PSEG staff stated that the 15 proposed variations listed in the handout at ADAMS Accession No. ML17194A691 would be categorized into four types: (1) administrative, (2) v13riations that describe proposed changes to requirements currently in Hope Creek TSs that are outside the scope of the evaluation that supports TSTF-542, but PSEG proposes to make the final product as much like TSTF-542 as possible, 3) variations that describe proposed changes to the Hope Creek TSs that are consistent with STS bases or are encompassed in the TSTF justification, and 4) variations that describe TSTF-542 changes where no corresponding Hope Creek TS changes are being proposed.
P. Sena, Ill The NRC staff recommended that PSEG conduct a detailed review to ensure a high quality submittal of the TS changes, since many of the questions the NRC staff has generated during reviews of this TSTF for other plants are related to quality control. The NRC staff also requested PSEG to consider breaking up the variations listed in number 11, since this variation included several subparts. PSEG responded that the handout was a draft and that the final submittal would be more organized, categorized as stated above, and likely include additional variations and modifications.
NRC staff notified PSEG that since it does not have improved Standard Technical Specifications, the review would be more complex, and thus, could require more hours to complete.
Members of the public did not attend and no public meeting feedback forms were received.
Please direct any inquiries to me at (301) 415-1906 or Lisa.Regner@nrc.gov.
Lisa M. Regner, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-354
Enclosure:
List of Attendees cc w/enclosure: Distribution via Listserv
LIST OF ATTENDEES JULY 13, 2017, MEETING WITH PSEG NUCLEAR LLC TO DISCUSS POTENTIAL LICENSE AMENDMENT REQUEST RE: TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER-542 FOR HOPE CREEK GENERATING STATION Name Organization Lisa Reqner NRC Larry Wheeler NRC James Danna NRC Khadijah West NRC Muhammad Razzaque NRC Eric Oesterle NRC Jennifer Whitman (by phone) NRC Russell Haskell NRC Paul Duke PSEG Licensing Lee Marabella PSEG Licensing James Priest PSEG Operations David Bartlett PSEG Engineering Johnathan Getty PSEG Engineering Enclosure
P. Sena, Ill
SUBJECT:
SUMMARY
OF JULY 13, 2017, MEETING WITH PSEG NUCLEAR LLC TO DISCUSS POTENTIAL LICENSE AMENDMENT REQUEST RE: TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER-542 FOR HOPE CREEK GENERATING STATION (CAC NO. MF9877) DATED AUGUST 4, 2017 DISTRIBUTION:
Public RidsRgn1 MailCenter Resource RidsNrrDorlLpl1 Resource RidsNrrLALRonewicz Resource RidsNrrPMHopeCreek Resource RidsACRS_MailCTR Resource LWheeler, NRR KWest, NRR MRazzaque, NRR EOesterle, NRR JWhitman, NRR RHaskell, NRR TWertz, NRR JBowen, OEDO RidsNrrDeEvib Resource ADAMS A ccess1on No.: ML17201A101
- b>yema1 OFFICE DORL/LPL4/PM DORL/LPL 1/LA DSS/SRXB/BC*
NAME LRegner LRonewicz EOesterle DATE 07/21/2017 07/21/2017 7/21/2017 OFFICE DSS/STSB/BC* DE/El CB/BC* DORL/LPL 1/BC DORL/LPL4/PM NAME JWhitman MWaters JDanna LRegner DATE 7/26/2017 7/27/2017 08/01/2017 08/04/2017 OFFICIAL RECORD COPY