ML18044A994
| ML18044A994 | |
| Person / Time | |
|---|---|
| Site: | Salem, Hope Creek |
| Issue date: | 02/26/2018 |
| From: | Carleen Parker Plant Licensing Branch 1 |
| To: | Public Service Enterprise Group |
| Parker C, NRR/DORL/LPLI, 415-1603 | |
| Shared Package | |
| ML18044B0007 | List: |
| References | |
| EPID L-2018--LRM-0002 | |
| Download: ML18044A994 (4) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 26, 2018 LICENSEE:
PSEG Nuclear LLC FACILITIES: Salem Nuclear Generating Station, Unit Nos. 1 and 2, and Hope Creek Generating Station
SUBJECT:
SUMMARY
OF FEBRUARY 1, 2018, MEETING WITH PSEG NUCLEAR LLC ON PLANNED SUBMITTAL OF LICENSE AMENDMENT REQUESTS TO EXTEND THE ALLOWED OUTAGE TIME FOR THE INVERTERS (EPID L-2018-LRM-0002)
On February 1, 2018, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of PSEG Nuclear LLC (PSEG or the licensee) by teleconference. The purpose of the meeting was to discuss PSEG's planned submittal of license amendment requests (LARs) for Salem Nuclear Generating Station (Salem),
Unit Nos. 1 and 2, and Hope Creek Generating Station (Hope Creek) to revise the Technical Specifications (TSs). Specifically, the proposed amendments would extend the allowed outage time for the inverters from 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to 7 days.
The meeting notice and agenda, dated January 22, 2018, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML18022A695. A list of attendees is enclosed.
The licensee presented an overview of its plans to submit the LARs. The presentation closely followed PSEG's slides provided for the meeting (ADAMS Accession No. ML18032A331 ).
The licensee explained that the Salem D inverter does not supply control or indication of the emergency diesel generators (EDGs); therefore, it is has a longer allowed outage time (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> versus 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />) in the current TSs.
PSEG provided a specific example of a recent inverter failure that could have resulted in the unit being shut down if the failure mechanism had not been evident. The licensee stated that the current allowed outage time puts a large amount of stress on the staff to identify and correct any failures. Also, PSEG stated that inverter failures will be filtered into the next risk update.
The licensee stated that the worst case scenario, with one inverter out of service, is a loss of offsite power with one EOG failing to auto load; however, PSEG has procedures on how to manually start the EOG. Once the EOG is started, the inverter would be energized. While the EOG was unavailable, two vital buses would still be available via the other EDGs.
The licensee stated that it will perform a full defense-in-depth review as required per the NRC guidance. Also, PSEG stated that the fire probabilistic risk assessment for Salem is only partially done and will not be finished in time for this proposed amendment. However, PSEG will use insights gained from the partially finished fire probabilistic risk assessment in the application. If PSEG identifies any requirements during the NRC Regulatory Guide 1.177, Revision 1, "An Approach for Plant-Specific, Risk-Informed Decision Making: Technical Specifications," (ADAMS Accession No. ML100910008) Tier 2 and Tier 3 review, PSEG will discuss the procedure changes that will be made to address the requirements in the LARs.
The NRC staff provided the following feedback:
The LARs should discuss the impact of one EOG failing to auto load (i.e., discuss any impact from the additional time without the inverter).
Since the change will be permanent, the LARs need to consider the permanent risk increase.
The LARs need to provide up-to-date information for fire hazards (Salem) and external events (Hope Creek and Salem).
For previous Salem LARs, the NRC staff has requested bounding analysis for fire hazards and external events. The NRC staff also clarified to the licensee that applicable external hazards to the proposed change must be justified as having an insignificant risk impact. The NRC staff has also considered a gap analysis to address the differences between the Individual Plant Examination of External Events Fire-Induced Vulnerability Evaluation methodology and methodology provided in American Society of Mechanical Engineers (ASME)/American Nuclear Society (ANS) RA-Sa-2009, "Addenda to ASME/ANS RA-S2008 Standard for Level 1/Large Early Release Frequency Probabilistic Risk Assessment for Nuclear Power Plant Applications." The NRC staff will get back to PSEG with additional information on which method(s) the NRC staff would find appropriate for this submittal.
The licensee clarified that two separate LARs will be submitted-one for Salem and one for Hope Creek, with the anticipated submittal by March 30, 2018.
There were no members of the public in attendance. The NRC staff did not receive any public meeting feedback forms.
Please direct any inquiries to me at 301-415-1602 or Carleen.Parker Docket Nos. 50-272, 50-311, and 50-354
Enclosure:
List of Attendees cc: Listserv
~;'.. VJ--
Carleen £.r: rker, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
LIST OF ATTENDEES FEBRUARY 1, 2018, MEETING WITH PSEG NUCLEAR LLC SALEM NUCELR GENERATING STATION, UNIT NOS. 1 AND 2 HOPE CREEK GENERATING STATION PLANNED INVERTER ALLOWED OUTAGE TIME LICENSE AMENDMENT REQUESTS ATTENDEE Carleen Parker Brandon Hartle Adakou Foli Jonathan Evans James Danna Pete Snyder Paul Duke Ed Kane Gary DeMoss David Bartlett Chris Serata Bill Kopchick Tom Mulholland Karen Hernandez Mike Phillips Lee Marabella Chris Rahn Robert Wolfgang Eric Thornsbury Alai'na Vivanco Craig Matos Jerry Humphreys Elliot Rosenfeld ORGANIZATION U.S. Nuclear Regulatory Commission (NRC)
NRC NRC NRC NRC NRC PSEG Nuclear LLC (PSEG)
PSEG PSEG PSEG PSEG PSEG PSEG PSEG PSEG PSEG Jensen Hughes Jensen Hughes Jensen Hughes Jensen Hughes Jensen Hughes New Jersey Department of Environmental Protection New Jersey Department of Environmental Protection Enclosure
SUBJECT:
SUMMARY
OF FEBRUARY 1, 2018, MEETING WITH PSEG NUCLEAR LLC ON PLANNED SUBMITTAL OF LICENSE AMENDMENT REQUESTS TO EXTEND THE ALLOWED OUTAGE TIME FOR THE INVERTERS (EPID L-2018-LRM-0002) DATED FEBRUARY 26, 2018 DISTRIBUTION:
PUBLIC PM Reading File RidsACRS_MailCTR Resource RidsNrrDorlLpl1 Resource RidsNrrPMHopeCreek Resource RidsNrrPMSalem Resource RidsNrrLALRonewicz Resource RidsNrrLAIBetts Resource RidsRgn1 MailCenter Resource RidsNrrDssStsb Resource RidsNrrDraApla Resource RidsNrrDeEeob Resource TWertz, NRR JBowen, EDO PSnyder, NRR JEvans, NRR AFoli, NRR BHartle, NRR ADAMS A ccess1on N os.: M f
S ee mg OFFICE NRR/DORL/LPL 1/PM NAME CParker DATE 02/22/18 OFFICE NRR/DORL/LPL 1/BC NAME JDanna DATE 02/23/18 ummary ML18044A994 NRR/DORL/LSPB/LA I Betts 02/21/18 NRR/DORL/LPL 1/PM CParker 02/26/18 OFFICIAL RECORD COPY p
k ac age ML180448007 NRR/DORL/LPL 1 /LA LRonewicz 02/21/18