IR 05000298/2008402: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 1: Line 1:
{{Adams|number = ML081500781}}
{{Adams
| number = ML081500781
| issue date = 05/29/2008
| title = IR 05000298-08-402, on 05/12/2008 - 05/15/2008, for Cooper
| author name = Shannon M P
| author affiliation = NRC/RGN-IV/DRS/PSB
| addressee name = Minahan S B
| addressee affiliation = Nebraska Public Power District (NPPD)
| docket = 05000298
| license number = DPR-046
| contact person =
| document report number = IR-08-402
| document type = Letter, Inspection Report
| page count = 3
}}


{{IR-Nav| site = 05000298 | year = 2008 | report number = 402 }}
{{IR-Nav| site = 05000298 | year = 2008 | report number = 402 }}
Line 12: Line 26:


==Dear Mr. Minahan:==
==Dear Mr. Minahan:==
On May 15, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Cooper Nuclear Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on May 15, 2008, with you and other members of your staff. The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
On May 15, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Cooper Nuclear Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on May 15, 2008, with you and other members of your staff.


No findings of significance were identified. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
 
No findings of significance were identified.
 
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS.


ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.


Nebraska Public Power District - 2 In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390." and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Nebraska Public Power District - 2 - In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390." and follow the instructions for withholding in 10 CFR 2.390(b)(1).


Sincerely,/RA/
Sincerely,/RA/
Line 27: Line 45:


===w/Attachment:===
===w/Attachment:===
Supplemental Information cc w/o enclosure: Gene Mace Nuclear Asset Manager Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 John C. McClure, Vice President and General Counsel Nebraska Public Power District P.O. Box 499 Columbus, NE 68602-0499 Paul V. Fleming, Director of Nuclear Safety Assurance Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 Nebraska Public Power District - 3 H. Floyd Gilzow Deputy Director for Policy Missouri Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102-0176
Supplemental Information cc w/o enclosure: Gene Mace Nuclear Asset Manager Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 John C. McClure, Vice President and General Counsel Nebraska Public Power District P.O. Box 499 Columbus, NE 68602-0499  
 
Paul V. Fleming, Director of Nuclear Safety Assurance Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 Nebraska Public Power District - 3 - H. Floyd Gilzow Deputy Director for Policy Missouri Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102-0176
}}
}}

Revision as of 18:51, 29 August 2018

IR 05000298-08-402, on 05/12/2008 - 05/15/2008, for Cooper
ML081500781
Person / Time
Site: Cooper Entergy icon.png
Issue date: 05/29/2008
From: Shannon M P
Plant Support Branch Region IV
To: Minahan S B
Nebraska Public Power District (NPPD)
References
IR-08-402
Download: ML081500781 (3)


Text

May 29, 2008

Stewart B. Minahan, Vice President-Nuclear and CNO Nebraska Public Power District 72676 648A Avenue Brownville, NE 68321

SUBJECT: COOPER NUCLEAR STATION - NRC PHYSICAL SECURITY INSPECTION REPORT 05000298/2008402

Dear Mr. Minahan:

On May 15, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Cooper Nuclear Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on May 15, 2008, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS.

ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.

Nebraska Public Power District - 2 - In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390." and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Sincerely,/RA/

Michael P. Shannon, Chief Plant Support Branch Division of Reactor Safety Docket: 50-298 License: DRP-46 Nonpublic

Enclosure:

Inspection Report 05000298/2007402

w/Attachment:

Supplemental Information cc w/o enclosure: Gene Mace Nuclear Asset Manager Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 John C. McClure, Vice President and General Counsel Nebraska Public Power District P.O. Box 499 Columbus, NE 68602-0499

Paul V. Fleming, Director of Nuclear Safety Assurance Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 Nebraska Public Power District - 3 - H. Floyd Gilzow Deputy Director for Policy Missouri Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102-0176