ML090490612: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 12: | Line 12: | ||
| document type = Meeting Briefing Package/Handouts | | document type = Meeting Briefing Package/Handouts | ||
| page count = 1 | | page count = 1 | ||
| project = | |||
| stage = Other | |||
}} | }} | ||
=Text= | =Text= | ||
{{#Wiki_filter:NFPA 805 Pilot License Amendment Request Review | {{#Wiki_filter:NFPA 805 Pilot License Amendment Request Review | ||
5/29/08 ML081560641 LAR Enclosure 3: Publically Available Transition Report* | & Infrastructure Update SHEARON HARRIS NFPA 805 LAR REVIEW Date Available Information LAR Letter and Enclosures 1 & 2* 5/29/08 ML081560641 LAR Enclosure 3: Publically Available Transition Report* 5/29/08 ML081840706 LAR Submission Ceremony 7/17/08 ML082060554 NRC LAR Acceptance Review Letter to Progress Energy 9/26/08 ML082701158 Public Meeting to Discuss Harris Supplement 9/29/08 ML082960153 Harris LAR Supplement Due to NRC 11/14/08 ML083240593 Harris LAR Supplement (Part 2) 12/11/08 *** | ||
5/29/08 ML081840706 LAR Submission Ceremony 7/17/08 ML082060554 NRC LAR Acceptance Review Letter to Progress Energy 9/26/08 ML082701158 Public Meeting to Discuss Harris Supplement 9/29/08 ML082960153 Harris LAR Supplement Due to NRC 11/14/08 ML083240593 Harris LAR Supplement (Part 2) 12/11/08 *** Harris LAR Site Audit Plan (3/16-20/09) 3/09 | Harris LAR Site Audit Plan (3/16-20/09) 3/09 Issue Harris RAIs to Progress Energy 3/09** | ||
5/30/08 ML081650475 Transition Report: | Receive Harris RAI Responses from Progress Energy 5/09** | ||
5/30/08 ML082041014 LAR Submission Ceremony 7/17/08 ML082060554 LAR Supplement (Part 2) 10/31/08 *** NRC LAR Conditional Acceptance Review Letter to Duke Energy 2/2/09 ML090330496 Oconee Site Audit Plan (Audit 2/23 - 27/09) 2/12/09 ML090290196 Issue Oconee LAR Site Audit Summary 3/09 | Harris Safety Evaluation Issued to Progress Energy 9/09** | ||
* The Pilots submitted partial LARs, non-Pilot Licensees are expected to have complete LAR submittals. ** | OCONEE NFPA 805 LAR REVIEW Date Available Information LAR Letter and Transition Report: Attachment A & B* 5/30/08 ML081650475 Transition Report: Attachment D* 5/30/08 ML082041014 LAR Submission Ceremony 7/17/08 ML082060554 LAR Supplement (Part 2) 10/31/08 *** | ||
NRC LAR Conditional Acceptance Review Letter to Duke Energy 2/2/09 ML090330496 Oconee Site Audit Plan (Audit 2/23 - 27/09) 2/12/09 ML090290196 Issue Oconee LAR Site Audit Summary 3/09 Issue LAR RAIs to Duke Energy 3/09** | |||
Receive LAR RAI Responses from Duke Energy 5/09** | |||
LAR Safety Evaluation Issued to Duke Energy 9/09** | |||
NFPA 805 INFRASTRUCTURE DEVELOPMENT SCHEDULE Date Available Information Received NEI 00-01, Revision 2 from NEI 12/21/07 ML082050625 Received NEI 04-02, Revision 2 from NEI 4/15/08 ML081400332 NRC Comments on NEI 00-01, Rev 2 sent to NEI 6/2/08 ML081640340 SRP 9.5.1.2, Risk-Informed, Performance-Based Fire Protection 10/9/08 ML082830934 Public Meeting Summary NFPA 805 Regulatory Audit Plan Template Memo 12/10/08 ML083100575 SRP 9.5.1.2 Published for Public Comment 1/09 ML090050052 Send NRC Comments on NEI 04-02, Rev 2 3/09 (unless covered in RG 1.205, Revision 1) | |||
Publish Draft RG 1.205, Revision 1 for Public Comment 3/09 Publish RG 1.200, Revision 1 4/09 | |||
* The Pilots submitted partial LARs, non-Pilot Licensees are expected to have complete LAR submittals. | |||
** These milestone dates are estimates based on a high-quality supplemental submittal. | |||
*** Material is considered SUNSI, awaiting a publically available redacted version from the Licensee. | |||
2/18/2009}} | 2/18/2009}} |
Latest revision as of 08:50, 14 November 2019
ML090490612 | |
Person / Time | |
---|---|
Site: | Oconee, Harris |
Issue date: | 02/18/2009 |
From: | NRC/NRR/DRA/AFPB |
To: | |
References | |
Download: ML090490612 (1) | |
Text
NFPA 805 Pilot License Amendment Request Review
& Infrastructure Update SHEARON HARRIS NFPA 805 LAR REVIEW Date Available Information LAR Letter and Enclosures 1 & 2* 5/29/08 ML081560641 LAR Enclosure 3: Publically Available Transition Report* 5/29/08 ML081840706 LAR Submission Ceremony 7/17/08 ML082060554 NRC LAR Acceptance Review Letter to Progress Energy 9/26/08 ML082701158 Public Meeting to Discuss Harris Supplement 9/29/08 ML082960153 Harris LAR Supplement Due to NRC 11/14/08 ML083240593 Harris LAR Supplement (Part 2) 12/11/08 ***
Harris LAR Site Audit Plan (3/16-20/09) 3/09 Issue Harris RAIs to Progress Energy 3/09**
Receive Harris RAI Responses from Progress Energy 5/09**
Harris Safety Evaluation Issued to Progress Energy 9/09**
OCONEE NFPA 805 LAR REVIEW Date Available Information LAR Letter and Transition Report: Attachment A & B* 5/30/08 ML081650475 Transition Report: Attachment D* 5/30/08 ML082041014 LAR Submission Ceremony 7/17/08 ML082060554 LAR Supplement (Part 2) 10/31/08 ***
NRC LAR Conditional Acceptance Review Letter to Duke Energy 2/2/09 ML090330496 Oconee Site Audit Plan (Audit 2/23 - 27/09) 2/12/09 ML090290196 Issue Oconee LAR Site Audit Summary 3/09 Issue LAR RAIs to Duke Energy 3/09**
Receive LAR RAI Responses from Duke Energy 5/09**
LAR Safety Evaluation Issued to Duke Energy 9/09**
NFPA 805 INFRASTRUCTURE DEVELOPMENT SCHEDULE Date Available Information Received NEI 00-01, Revision 2 from NEI 12/21/07 ML082050625 Received NEI 04-02, Revision 2 from NEI 4/15/08 ML081400332 NRC Comments on NEI 00-01, Rev 2 sent to NEI 6/2/08 ML081640340 SRP 9.5.1.2, Risk-Informed, Performance-Based Fire Protection 10/9/08 ML082830934 Public Meeting Summary NFPA 805 Regulatory Audit Plan Template Memo 12/10/08 ML083100575 SRP 9.5.1.2 Published for Public Comment 1/09 ML090050052 Send NRC Comments on NEI 04-02, Rev 2 3/09 (unless covered in RG 1.205, Revision 1)
Publish Draft RG 1.205, Revision 1 for Public Comment 3/09 Publish RG 1.200, Revision 1 4/09
- The Pilots submitted partial LARs, non-Pilot Licensees are expected to have complete LAR submittals.
- These milestone dates are estimates based on a high-quality supplemental submittal.
- Material is considered SUNSI, awaiting a publically available redacted version from the Licensee.
2/18/2009