ML17160A195: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(13 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML17160A195
| number = ML17160A195
| issue date = 06/12/2017
| issue date = 06/12/2017
| title = 06/20/2017, Meeting Slides for Pre-Submittal Meeting with Entergy Regarding the Plan for Decommissioning Licensing Actions (CAC Nos. MF9624, MF9625, MF9626, MF9627, and MF9628)
| title = Meeting Slides for Pre-Submittal Meeting with Entergy Regarding the Plan for Decommissioning Licensing Actions
| author name =  
| author name =  
| author affiliation = Entergy Nuclear Operations, Inc
| author affiliation = Entergy Nuclear Operations, Inc
| addressee name = Wall S P
| addressee name = Wall S
| addressee affiliation = NRC/NRR/DORL/LPLIII
| addressee affiliation = NRC/NRR/DORL/LPLIII
| docket = 05000247, 05000255, 05000271, 05000286
| docket = 05000247, 05000255, 05000271, 05000286
Line 14: Line 14:
| page count = 21
| page count = 21
| project = CAC:MF9624, CAC:MF9625, CAC:MF9626, CAC:MF9627, CAC:MF9628
| project = CAC:MF9624, CAC:MF9625, CAC:MF9626, CAC:MF9627, CAC:MF9628
| stage = Meeting
}}
}}


=Text=
=Text=
{{#Wiki_filter:Palisades Nuclear PlantJune 12, 2017 1Palisades Nuclear Plant (PNP)Pre-Application Meeting License Amendment Requests (LAR) Supporting a Permanently Defueled Condition1 Introduction of Entergy Team*Otto Gustafson -Director, Regulatory Assurance and Performance Improvement*Dan Malone -Manager, Emergency Planning *Amy Hazelhoff -Licensing Support*David Daigle -Emergency Planning Support 2 Agenda*Purpose *Background*Technical Specification (TS) ADMIN Section 5.0 LAR-Scope-Precedent Reviewed-Examples-Precedent Deviation*Post Shutdown Emergency Plan LAR-Overview-Scope-Staffing Levels-Offsite Response Organizations-Precedent Deviations*Schedule3 Purpose*Provide overview of:-ADMIN 5.0 LAR-PSEP LAR*Facilitate NRC review*Ensure LAR acceptance4 Background*Certification to Permanently Cease Power Operations on October 1, 2018-Submitted January 4, 2017 (ADAMS #ML17004A062)*LARs support PNP Transition from an operating plant to a permanently defueled facility*Supporting Submittals-Certified Fuel Handler (CFH) Training and Retraining Program *Submitted March 28, 2017 (ADAMS #ML17087A016)-Severe Weather Exemption (10 CFR 73.55)*Target submittal July 20185 ADMIN Section 5.0 LAR*Scope-TS Section 1.0 -Use and Application-TS Section 5.0 -Administrative Controls*Precedent Reviewed-Entergy Nuclear Operations, Inc. (ENO)*Vermont Yankee Amendment 260*James A. Fitzpatrick LAR & RAIs -Exelon*Oyster Creek Amendment 290 (3/7/17)-NRC*Power Reactor Transition from Operations to Decommissioning -Lessons Learned Report (10/16)6 ADMIN Section 5.0 LARExamples of Proposed Changes*Position Title Changes-"Plant Superintendent" to "Plant Manager"-"Shift Supervisor" to "Shift Manager"*Description Changes-"Safety of PNP" to "safe storage and handling of spent nuclear fuel" -"Plant staff" to "facility staff"-"Control Room command function" to "Shift command function"*Added Specifications-Definitions for CERTIFIED FUEL HANDLER and NON-CERTIFIED OPERATOR-Requirement that the  Shift Manager shall be a CERTIFIED FUEL HANDLER-Requirement for a NRC-approved Certified Fuel Handler training program*Deleted Specifications-Licensed Operators-Shift Technical Advisor7 ADMIN Section 5.0 LARPrecedent Deviation*Precedence: NON-CERTIFIED OPERATOR-A NON-CERTIFIED OPERATOR is a non-licensed operator who complies with the qualification requirements of Specification 5.3.1, but is not a CERTIFIED FUEL HANDLER.*PNP Proposed: NON-CERTIFIED OPERATOR-A NON-CERTIFIED OPERATOR is a non-licensed operator who complies with the qualification requirements of Specification 5.3.1.*Basis: Eliminate potential conflict with proposed TS Section 5.2.2a.-Each duty shift shall be composed of at least one shift  manager and one NON-CERTIFIED OPERATOR. The NON-CERTIFIED OPERATOR position may be filled by a CERTIFIED FUEL HANDLER.8 Post-Shutdown Emergency Plan LAR*LAR Overview-Attachment 1 -License Amendment Request-Attachment 2 -Emergency Plan Change Summary-Attachment 3 -PSEP Markup-Attachment 4 -PSEP Clean-Attachment 5 -Analysis of Proposed Post-Shutdown On-Shift Staffing-Attachment 6 -Emergency Response Organization Task Analysis -Attachment 7 -Commitments9 Post-Shutdown Emergency Plan LAR*Precedent Reviewed-Entergy Nuclear Operations, Inc. (ENO)*Vermont Yankee Amendment 261*James A. Fitzpatrick LAR & RAIs -Omaha Public Power District *Ft. Calhoun Station LAR and RAIs -NRC*Power Reactor Transition from Operations to Decommissioning -Lessons Learned Report (10/16)10 Post-Shutdown Emergency Plan LAR*Analysis of Proposed Post-Shutdown On-Shift Staffing-Post-Shutdown staffing was evaluated in conjunction with the postulated accidents that remain applicable in the permanently shutdown and defueled condition-Post-Shutdown analysis considers the following scenarios:*Design Basis Threat*Fuel Handling Accident*Aircraft Probable Threat*Control Room Fire Requiring Evacuation*General Emergency with Radioactive Release and Protective Action Recommendation (assumed for analysis purposes)-Precedent Alignment*Consistent with noted precedent 11 Post-Shutdown Emergency Plan LAR*On-Shift Staff-Permanently defueled condition:*One (1) Shift Manager*Two (2) Non-Certified Operators *One (1) Radiation Protection Technician *Five (5) person Fire Brigade maintained -Precedent Alignment*Consistent with noted precedent12 Post-Shutdown Emergency Plan LAR*ERO Augmentation by Facility:-Technical Support Center (TSC) *Emergency Plant Manager*Engineering Coordinator*Security Coordinator *Emergency Notification System Communicator 13 Post-Shutdown Emergency Plan LAR*ERO Augmentation by Facility:-Operations Support Center (OSC)*OSC Manager*Radiation/Chemistry Coordinator*Radiation Protection Technicians (3)14 Post-Shutdown Emergency Plan LAR*ERO Augmentation by Facility:-Emergency Operations Facility (EOF)*Emergency Director*Technical Advisor*Radiation Assessment Coordinator*Offsite Communicator*Offsite Team Coordinator*Dose Assessor*Offsite Field Monitoring Team -Offsite Liaisons (4)15 Post-Shutdown Emergency Plan LAR*ERO Augmentation by Facility:-Joint Information Center (JIC)*Company Spokesperson*Media Liaison*Media Monitor*Public Inquiry16 Post-Shutdown Emergency Plan LAR*ERO Position Differences -Generally consistent with precedent*Field Monitoring Team-Proposed elimination of the 90-minute augmenting team-No tasks identified for an additional augmenting team -PNP would retain resources to supplement an additional Field Monitoring Team on an as-needed basis*Chemistry Technician-Proposed elimination of 60-minute augmenting Chemistry Technician-No task identified in the post-shutdown condition that requires augmenting chemistry technician*EOF Lead Offsite Liaison-Proposed elimination of Lead Offsite Liaison-Function of the Lead Offsite Liaison is being transferred to other EOF staff-All necessary post-shutdown functions have been maintained and the ability of the ERO to perform these functions will be validated17 Post-Shutdown Emergency Plan*No Impacts to Offsite Response Organizations (ORO)-OROs briefed on draft PSEP organization and interfaces  -PNP Offsite Liaison positions remain intact and will continue to be dispatched to the State and County Emergency Operations Centers (EOC) to act as communication liaisons between the EOCs and plant technical staff and to provide clarification of emergency response information-Existing robust communication protocols remain in place-State and County Radiological Emergency Plans (REPs)reviewed and no impacts were identified to existing support and interface18 LAR Schedule*Plan to submit in July 2017*Validation Drill timing second quarter 2018*Request NRC approval in July 2018*Request an effective date: -After PNP CFH Training and Retraining Program ApprovalAND-After PNP Certifies Fuel Permanently removed from the reactor*Request a 60 day implementation period19
{{#Wiki_filter:Palisades Nuclear Plant June 12, 2017


}}
Palisades Nuclear Plant (PNP)
Pre-Application Meeting License Amendment Requests (LAR)
Supporting a Permanently Defueled Condition 1
1
 
Introduction of Entergy Team
* Otto Gustafson - Director, Regulatory Assurance and Performance Improvement
* Dan Malone - Manager, Emergency Planning
* Amy Hazelhoff - Licensing Support
* David Daigle - Emergency Planning Support 2
 
Agenda
* Purpose
* Background
* Technical Specification (TS) ADMIN Section 5.0 LAR
    - Scope
    - Precedent Reviewed
    - Examples
    - Precedent Deviation
* Post Shutdown Emergency Plan LAR
    - Overview
    - Scope
    - Staffing Levels
    - Offsite Response Organizations
    - Precedent Deviations
* Schedule 3
 
Purpose
* Provide overview of:
    - ADMIN 5.0 LAR
    - PSEP LAR
* Facilitate NRC review
* Ensure LAR acceptance 4
 
===
Background===
* Certification to Permanently Cease Power Operations on October 1, 2018
    - Submitted January 4, 2017 (ADAMS #ML17004A062)
* LARs support PNP Transition from an operating plant to a permanently defueled facility
* Supporting Submittals
    - Certified Fuel Handler (CFH) Training and Retraining Program
* Submitted March 28, 2017 (ADAMS #ML17087A016)
    - Severe Weather Exemption (10 CFR 73.55)
* Target submittal July 2018 5
 
ADMIN Section 5.0 LAR
* Scope
    - TS Section 1.0 - Use and Application
    - TS Section 5.0 - Administrative Controls
* Precedent Reviewed
    - Entergy Nuclear Operations, Inc. (ENO)
* Vermont Yankee Amendment 260
* James A. Fitzpatrick LAR & RAIs
    - Exelon
* Oyster Creek Amendment 290 (3/7/17)
    - NRC
* Power Reactor Transition from Operations to Decommissioning - Lessons Learned Report (10/16) 6
 
ADMIN Section 5.0 LAR Examples of Proposed Changes
* Position Title Changes
    - Plant Superintendent to Plant Manager
    - Shift Supervisor to Shift Manager
* Description Changes
    - Safety of PNP to safe storage and handling of spent nuclear fuel
    - Plant staff to facility staff
    - Control Room command function to Shift command function
* Added Specifications
    - Definitions for CERTIFIED FUEL HANDLER and NON-CERTIFIED OPERATOR
    - Requirement that the Shift Manager shall be a CERTIFIED FUEL HANDLER
    - Requirement for a NRC-approved Certified Fuel Handler training program
* Deleted Specifications
    - Licensed Operators
    - Shift Technical Advisor 7
 
ADMIN Section 5.0 LAR Precedent Deviation
* Precedence: NON-CERTIFIED OPERATOR
  - A NON-CERTIFIED OPERATOR is a non-licensed operator who complies with the qualification requirements of Specification 5.3.1, but is not a CERTIFIED FUEL HANDLER.
* PNP Proposed: NON-CERTIFIED OPERATOR
  - A NON-CERTIFIED OPERATOR is a non-licensed operator who complies with the qualification requirements of Specification 5.3.1.
* Basis: Eliminate potential conflict with proposed TS Section 5.2.2a.
  - Each duty shift shall be composed of at least one shift manager and one NON-CERTIFIED OPERATOR. The NON- CERTIFIED OPERATOR position may be filled by a CERTIFIED FUEL HANDLER.
8
 
Post-Shutdown Emergency Plan LAR
* LAR Overview
  - Attachment 1 - License Amendment Request
  - Attachment 2 - Emergency Plan Change Summary
  - Attachment 3 - PSEP Markup
  - Attachment 4 - PSEP Clean
  - Attachment 5 - Analysis of Proposed Post-Shutdown On-Shift Staffing
  - Attachment 6 - Emergency Response Organization Task Analysis
  - Attachment 7 - Commitments 9
 
Post-Shutdown Emergency Plan LAR
* Precedent Reviewed
    - Entergy Nuclear Operations, Inc. (ENO)
* Vermont Yankee Amendment 261
* James A. Fitzpatrick LAR & RAIs
    - Omaha Public Power District
* Ft. Calhoun Station LAR and RAIs
    - NRC
* Power Reactor Transition from Operations to Decommissioning - Lessons Learned Report (10/16) 10
 
Post-Shutdown Emergency Plan LAR
* Analysis of Proposed Post-Shutdown On-Shift Staffing
  - Post-Shutdown staffing was evaluated in conjunction with the postulated accidents that remain applicable in the permanently shutdown and defueled condition
  - Post-Shutdown analysis considers the following scenarios:
* Design Basis Threat
* Fuel Handling Accident
* Aircraft Probable Threat
* Control Room Fire Requiring Evacuation
* General Emergency with Radioactive Release and Protective Action Recommendation (assumed for analysis purposes)
  - Precedent Alignment
* Consistent with noted precedent 11
 
Post-Shutdown Emergency Plan LAR
* On-Shift Staff
  - Permanently defueled condition:
* One (1) Shift Manager
* Two (2) Non-Certified Operators
* One (1) Radiation Protection Technician
* Five (5) person Fire Brigade maintained
  - Precedent Alignment
* Consistent with noted precedent 12
 
Post-Shutdown Emergency Plan LAR
* ERO Augmentation by Facility:
  - Technical Support Center (TSC)
* Emergency Plant Manager
* Engineering Coordinator
* Security Coordinator
* Emergency Notification System Communicator 13
 
Post-Shutdown Emergency Plan LAR
* ERO Augmentation by Facility:
    - Operations Support Center (OSC)
* OSC Manager
* Radiation/Chemistry Coordinator
* Radiation Protection Technicians (3) 14
 
Post-Shutdown Emergency Plan LAR
* ERO Augmentation by Facility:
  - Emergency Operations Facility (EOF)
* Emergency Director
* Technical Advisor
* Radiation Assessment Coordinator
* Offsite Communicator
* Offsite Team Coordinator
* Dose Assessor
* Offsite Field Monitoring Team
  - Offsite Liaisons (4) 15
 
Post-Shutdown Emergency Plan LAR
* ERO Augmentation by Facility:
  - Joint Information Center (JIC)
* Company Spokesperson
* Media Liaison
* Media Monitor
* Public Inquiry 16
 
Post-Shutdown Emergency Plan LAR
* ERO Position Differences
  - Generally consistent with precedent
* Field Monitoring Team
          - Proposed elimination of the 90-minute augmenting team
          - No tasks identified for an additional augmenting team
          - PNP would retain resources to supplement an additional Field Monitoring Team on an as-needed basis
* Chemistry Technician
          - Proposed elimination of 60-minute augmenting Chemistry Technician
          - No task identified in the post-shutdown condition that requires augmenting chemistry technician
* EOF Lead Offsite Liaison
          - Proposed elimination of Lead Offsite Liaison
          - Function of the Lead Offsite Liaison is being transferred to other EOF staff
  - All necessary post-shutdown functions have been maintained and the ability of the ERO to perform these functions will be validated 17
 
Post-Shutdown Emergency Plan
* No Impacts to Offsite Response Organizations (ORO)
  - OROs briefed on draft PSEP organization and interfaces
  - PNP Offsite Liaison positions remain intact and will continue to be dispatched to the State and County Emergency Operations Centers (EOC) to act as communication liaisons between the EOCs and plant technical staff and to provide clarification of emergency response information
  - Existing robust communication protocols remain in place
  - State and County Radiological Emergency Plans (REPs) reviewed and no impacts were identified to existing support and interface 18
 
LAR Schedule
* Plan to submit in July 2017
* Validation Drill timing second quarter 2018
* Request NRC approval in July 2018
* Request an effective date:
    - After PNP CFH Training and Retraining Program Approval AND
    - After PNP Certifies Fuel Permanently removed from the reactor
* Request a 60 day implementation period 19}}

Latest revision as of 16:45, 18 March 2020

Meeting Slides for Pre-Submittal Meeting with Entergy Regarding the Plan for Decommissioning Licensing Actions
ML17160A195
Person / Time
Site: Palisades, Indian Point, Vermont Yankee  Entergy icon.png
Issue date: 06/12/2017
From:
Entergy Nuclear Operations
To: Scott Wall
Plant Licensing Branch III
Wall S
References
CAC MF9624, CAC MF9625, CAC MF9626, CAC MF9627, CAC MF9628
Download: ML17160A195 (21)


Text

Palisades Nuclear Plant June 12, 2017

Palisades Nuclear Plant (PNP)

Pre-Application Meeting License Amendment Requests (LAR)

Supporting a Permanently Defueled Condition 1

1

Introduction of Entergy Team

  • Otto Gustafson - Director, Regulatory Assurance and Performance Improvement
  • Dan Malone - Manager, Emergency Planning
  • Amy Hazelhoff - Licensing Support
  • David Daigle - Emergency Planning Support 2

Agenda

  • Purpose
  • Background
  • Technical Specification (TS) ADMIN Section 5.0 LAR

- Scope

- Precedent Reviewed

- Examples

- Precedent Deviation

- Overview

- Scope

- Staffing Levels

- Offsite Response Organizations

- Precedent Deviations

  • Schedule 3

Purpose

  • Provide overview of:

- ADMIN 5.0 LAR

- PSEP LAR

  • Facilitate NRC review
  • Ensure LAR acceptance 4

=

Background===

  • Certification to Permanently Cease Power Operations on October 1, 2018

- Submitted January 4, 2017 (ADAMS #ML17004A062)

  • LARs support PNP Transition from an operating plant to a permanently defueled facility
  • Supporting Submittals

- Certified Fuel Handler (CFH) Training and Retraining Program

  • Submitted March 28, 2017 (ADAMS #ML17087A016)

- Severe Weather Exemption (10 CFR 73.55)

  • Target submittal July 2018 5

ADMIN Section 5.0 LAR

  • Scope

- TS Section 1.0 - Use and Application

- TS Section 5.0 - Administrative Controls

  • Precedent Reviewed

- Entergy Nuclear Operations, Inc. (ENO)

- Exelon

  • Oyster Creek Amendment 290 (3/7/17)

- NRC

  • Power Reactor Transition from Operations to Decommissioning - Lessons Learned Report (10/16) 6

ADMIN Section 5.0 LAR Examples of Proposed Changes

  • Position Title Changes

- Plant Superintendent to Plant Manager

- Shift Supervisor to Shift Manager

  • Description Changes

- Safety of PNP to safe storage and handling of spent nuclear fuel

- Plant staff to facility staff

- Control Room command function to Shift command function

  • Added Specifications

- Definitions for CERTIFIED FUEL HANDLER and NON-CERTIFIED OPERATOR

- Requirement that the Shift Manager shall be a CERTIFIED FUEL HANDLER

- Requirement for a NRC-approved Certified Fuel Handler training program

  • Deleted Specifications

- Licensed Operators

- Shift Technical Advisor 7

ADMIN Section 5.0 LAR Precedent Deviation

  • Precedence: NON-CERTIFIED OPERATOR

- A NON-CERTIFIED OPERATOR is a non-licensed operator who complies with the qualification requirements of Specification 5.3.1, but is not a CERTIFIED FUEL HANDLER.

  • PNP Proposed: NON-CERTIFIED OPERATOR

- A NON-CERTIFIED OPERATOR is a non-licensed operator who complies with the qualification requirements of Specification 5.3.1.

- Each duty shift shall be composed of at least one shift manager and one NON-CERTIFIED OPERATOR. The NON- CERTIFIED OPERATOR position may be filled by a CERTIFIED FUEL HANDLER.

8

Post-Shutdown Emergency Plan LAR

- Attachment 1 - License Amendment Request

- Attachment 2 - Emergency Plan Change Summary

- Attachment 3 - PSEP Markup

- Attachment 4 - PSEP Clean

- Attachment 5 - Analysis of Proposed Post-Shutdown On-Shift Staffing

- Attachment 6 - Emergency Response Organization Task Analysis

- Attachment 7 - Commitments 9

Post-Shutdown Emergency Plan LAR

  • Precedent Reviewed

- Entergy Nuclear Operations, Inc. (ENO)

- Omaha Public Power District

- NRC

  • Power Reactor Transition from Operations to Decommissioning - Lessons Learned Report (10/16) 10

Post-Shutdown Emergency Plan LAR

  • Analysis of Proposed Post-Shutdown On-Shift Staffing

- Post-Shutdown staffing was evaluated in conjunction with the postulated accidents that remain applicable in the permanently shutdown and defueled condition

- Post-Shutdown analysis considers the following scenarios:

  • Design Basis Threat
  • Fuel Handling Accident
  • Aircraft Probable Threat
  • Control Room Fire Requiring Evacuation
  • General Emergency with Radioactive Release and Protective Action Recommendation (assumed for analysis purposes)

- Precedent Alignment

  • Consistent with noted precedent 11

Post-Shutdown Emergency Plan LAR

  • On-Shift Staff

- Permanently defueled condition:

  • One (1) Shift Manager
  • Two (2) Non-Certified Operators
  • One (1) Radiation Protection Technician
  • Five (5) person Fire Brigade maintained

- Precedent Alignment

  • Consistent with noted precedent 12

Post-Shutdown Emergency Plan LAR

  • ERO Augmentation by Facility:

- Technical Support Center (TSC)

  • Emergency Plant Manager
  • Engineering Coordinator
  • Security Coordinator
  • Emergency Notification System Communicator 13

Post-Shutdown Emergency Plan LAR

  • ERO Augmentation by Facility:

- Operations Support Center (OSC)

  • Radiation/Chemistry Coordinator
  • Radiation Protection Technicians (3) 14

Post-Shutdown Emergency Plan LAR

  • ERO Augmentation by Facility:

- Emergency Operations Facility (EOF)

  • Emergency Director
  • Technical Advisor
  • Radiation Assessment Coordinator
  • Offsite Communicator
  • Offsite Team Coordinator
  • Dose Assessor
  • Offsite Field Monitoring Team

- Offsite Liaisons (4) 15

Post-Shutdown Emergency Plan LAR

  • ERO Augmentation by Facility:

- Joint Information Center (JIC)

  • Company Spokesperson
  • Media Liaison
  • Media Monitor
  • Public Inquiry 16

Post-Shutdown Emergency Plan LAR

  • ERO Position Differences

- Generally consistent with precedent

  • Field Monitoring Team

- Proposed elimination of the 90-minute augmenting team

- No tasks identified for an additional augmenting team

- PNP would retain resources to supplement an additional Field Monitoring Team on an as-needed basis

  • Chemistry Technician

- Proposed elimination of 60-minute augmenting Chemistry Technician

- No task identified in the post-shutdown condition that requires augmenting chemistry technician

- Proposed elimination of Lead Offsite Liaison

- Function of the Lead Offsite Liaison is being transferred to other EOF staff

- All necessary post-shutdown functions have been maintained and the ability of the ERO to perform these functions will be validated 17

Post-Shutdown Emergency Plan

  • No Impacts to Offsite Response Organizations (ORO)

- OROs briefed on draft PSEP organization and interfaces

- PNP Offsite Liaison positions remain intact and will continue to be dispatched to the State and County Emergency Operations Centers (EOC) to act as communication liaisons between the EOCs and plant technical staff and to provide clarification of emergency response information

- Existing robust communication protocols remain in place

- State and County Radiological Emergency Plans (REPs) reviewed and no impacts were identified to existing support and interface 18

LAR Schedule

  • Plan to submit in July 2017
  • Validation Drill timing second quarter 2018
  • Request NRC approval in July 2018
  • Request an effective date:

- After PNP CFH Training and Retraining Program Approval AND

- After PNP Certifies Fuel Permanently removed from the reactor

  • Request a 60 day implementation period 19