Virtual Public Meeting Presentation Slides - Post Shutdown Decommissioning Activities Report, 08/15/2021 PSDAR Public Webinar Meeting
ML21217A199
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 08/18/2021
From: Bruce Watson
Reactor Decommissioning Branch
To:
Watson B
References
EPID L-2021-LRO-0031
Download: ML21217A199 (12)


Text

For audio, please call 1-888-989-9738 Public passcode: 2331350#

Indian Point Post Shutdown Decommissioning Activities Report PSDAR Public Meeting August 18, 2021 Bruce A. Watson, CHP Chief, Reactor Decommissioning Branch Office of Nuclear Material Safety and Safeguards 1

For audio, please call 1-888-989-9738 Public passcode: 2331350#

Indian Point PSDAR Public Meeting Agenda August 18, 2021 Topic Time Speakers Registration Opens 3:30 PM Online WebEx & Audio Registration

Introductions

  • Welcome U.S. Nuclear Regulatory Commission (NRC)
  • Introductions Elected Officials and Native American Tribes Questions & Answers: Brett Klukan

Reactor Decommissioning Program For audio, please call 1-888-989-9738 Public passcode: 2331350#

  • 26 Power Reactors Currently Undergoing Decommissioning:

- 17 in Active Decommissioning*

- 9 in SAFSTOR Maine Yankee

  • 7 Announced Shutdowns
  • License termination is expected at Humboldt Bay, La Crosse, and Zion Units 1 & 2 by 2021 3

The NRCs Decommissioning Mission For audio, please call 1-888-989-9738 Public passcode: 2331350#

  • The NRCs mission during decommissioning is to ensure safety until the plant has been radiologically decommissioned and the license is terminated.
  • NRC safety oversight continues with licensing and inspections until the license is terminated.

Resident Inspectors

  • The Reactor Oversight Program was observe final shutdown transferred to the Inspection Manual of Indian Point Unit 3 Chapter 2561, Reactor Decommissioning Inspection Program.

4

Reactor Decommissioning Process For audio, please call 1-888-989-9738 Public passcode: 2331350#

  • May 11, 2021, Entergy certified permanent cessation of Unit 3 operations and permanent removal of fuel from reactor. Unit 2 was certified on May 12, 2020.
  • The Holtec PSDAR was submitted to the NRC as supplemental information to the license transfer application on Dec. 19, 2019.

5

NRCs PSDAR Review Process For audio, please call 1-888-989-9738 Public passcode: 2331350#

  • After the licensee submits its certification of permanent removal of fuel from the reactor vessel, radiological decommissioning can start as allowed by the plants license.
  • The decommissioning activities must not endanger the public health and safety or the environment.

6

PSDAR Summary For audio, please call 1-888-989-9738 Public passcode: 2331350#

  • Holtec Indian Point PSDAR Summary:

- Spent fuel in dry cask storage by 2024

- Completion of decommissioning by 2033

- Decommissioning Trust Funds (~ $2.4 B) are adequate to complete the decommissioning

- Environmental impacts will be less than the previously issued Environmental Impact Statement and the site-specific assessment in the PSDAR.

  • NRC staff began formal review the Holtec PSDAR on May 28, 2021, after the license was amended making Holtec the new site owner.

7

License Termination For audio, please call 1-888-989-9738 Public passcode: 2331350#

  • NRC will continue to inspect the site to ensure the site is decommissioned safely.
  • NRC will continue to inspect the spent fuel in dry storage to ensure it is safe and secure until removed from the site.
  • License Termination Plan (LTP) must be submitted to NRC at least 2 years prior to requesting license termination.
  • The LTP is approved by license amendment after NRC review; there will be a public meeting and opportunity for a hearing.

8

Reminders!

For audio, please call 1-888-989-9738 Public passcode: 2331350#

  • We are here to listen to your comments on the Indian Point PSDAR.
  • The NRC staff will do our best to answer your questions.
  • The meeting is being transcribed and will be publicly available.
  • A meeting summary will be published and will be publicly available.

9

New York Reactor Decommissioning For audio, please call 1-888-989-9738 Public passcode: 2331350#

Shoreham Nuclear State University of Power Plant (Long New York at Buffalo Island, NY) Research Reactor 10

PSDAR Comments For audio, please call 1-888-989-9738 Public passcode: 2331350#

  • This public meeting
  • By Mail:

Office of Administration, Mail Stop: TWFN-7-A60M U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTN: Program Management, Announcements and Editing Staff

  • Federal Rulemaking website:

http://www.regulations.gov

- Search for Docket ID NRC-2021-0125

- Due by Oct. 22, 2021 11

For audio, please call 1-888-989-9738 Public passcode: 2331350#

Questions?

Neil.Sheehan@NRC.GOV or 610-337-5331 Region 1, Public Affairs Officer 12