Indian Point Post Shutdown Decommissioning Activities Report PSDAR Public Meeting August 18, 2021 Bruce A. Watson, CHP Chief, Reactor Decommissioning Branch Office of Nuclear Material Safety and Safeguards 1
For audio, please call 1-888-989-9738 Public passcode: 2331350#
Topic Time Speakers Registration Opens 3:30 PM Online WebEx & Audio Registration
Introductions
- Welcome
- NRC Introductions
- Meeting Rules 4:00 PM U.S. Nuclear Regulatory Commission (NRC)
Bruce Watson, NMSS Brett Klukan, Region 1 Discussion Topics
- NRC Presentation
- Introductions Elected Officials and Native American Tribes
- Public Comments 4:15 PM NRC Presentation: Bruce Watson Questions & Answers: Brett Klukan Summary of Proceedings and Discussions 6:45 PM Bruce Watson Adjourn 7:00 PM Brett Klukan For audio, please call 1-888-989-9738 Public passcode: 2331350#
Indian Point PSDAR Public Meeting Agenda August 18, 2021
Reactor Decommissioning Program
- 26 Power Reactors Currently Undergoing Decommissioning:
- 17 in Active Decommissioning*
- 9 in SAFSTOR
- 7 Announced Shutdowns
- License termination is expected at Humboldt Bay, La Crosse, and Zion Units 1 & 2 by 2021 Maine Yankee 3
For audio, please call 1-888-989-9738 Public passcode: 2331350#
The NRCs Decommissioning Mission The NRCs mission during decommissioning is to ensure safety until the plant has been radiologically decommissioned and the license is terminated.
NRC safety oversight continues with licensing and inspections until the license is terminated.
The Reactor Oversight Program was transferred to the Inspection Manual Chapter 2561, Reactor Decommissioning Inspection Program.
Resident Inspectors observe final shutdown of Indian Point Unit 3 4
For audio, please call 1-888-989-9738 Public passcode: 2331350#
Reactor Decommissioning Process
- May 11, 2021, Entergy certified permanent cessation of Unit 3 operations and permanent removal of fuel from reactor. Unit 2 was certified on May 12, 2020.
- The Holtec PSDAR was submitted to the NRC as supplemental information to the license transfer application on Dec. 19, 2019.
5 For audio, please call 1-888-989-9738 Public passcode: 2331350#
The PSDAR must contain the information required by regulation; Regulatory Guide 1.185 provides guidance on content and format.
After the licensee submits its certification of permanent removal of fuel from the reactor vessel, radiological decommissioning can start as allowed by the plants license.
The decommissioning activities must not endanger the public health and safety or the environment.
NRCs PSDAR Review Process 6
For audio, please call 1-888-989-9738 Public passcode: 2331350#
PSDAR Summary
- Holtec Indian Point PSDAR Summary:
- Spent fuel in dry cask storage by 2024
- Completion of decommissioning by 2033
- Decommissioning Trust Funds (~ $2.4 B) are adequate to complete the decommissioning
- Environmental impacts will be less than the previously issued Environmental Impact Statement and the site-specific assessment in the PSDAR.
- NRC staff began formal review the Holtec PSDAR on May 28, 2021, after the license was amended making Holtec the new site owner.
7 For audio, please call 1-888-989-9738 Public passcode: 2331350#
License Termination NRC will continue to inspect the site to ensure the site is decommissioned safely.
NRC will continue to inspect the spent fuel in dry storage to ensure it is safe and secure until removed from the site.
License Termination Plan (LTP) must be submitted to NRC at least 2 years prior to requesting license termination.
The LTP is approved by license amendment after NRC review; there will be a public meeting and opportunity for a hearing.
8 For audio, please call 1-888-989-9738 Public passcode: 2331350#
Reminders!
- We are here to listen to your comments on the Indian Point PSDAR.
- The NRC staff will do our best to answer your questions.
- The meeting is being transcribed and will be publicly available.
- A meeting summary will be published and will be publicly available.
9 For audio, please call 1-888-989-9738 Public passcode: 2331350#
New York Reactor Decommissioning Shoreham Nuclear Power Plant (Long Island, NY)
State University of New York at Buffalo Research Reactor 10 For audio, please call 1-888-989-9738 Public passcode: 2331350#
PSDAR Comments
- This public meeting
- By Mail:
Office of Administration, Mail Stop: TWFN-7-A60M U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTN: Program Management, Announcements and Editing Staff
- Federal Rulemaking website:
- Search for Docket ID NRC-2021-0125
- Due by Oct. 22, 2021 11 For audio, please call 1-888-989-9738 Public passcode: 2331350#
Questions?