IR 05000237/2012010: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 05/03/2012 | | issue date = 05/03/2012 | ||
| title = NRC Integrated Inspection Report 05000237-12-010 and 05000249/2012010 | | title = NRC Integrated Inspection Report 05000237-12-010 and 05000249/2012010 | ||
| author name = Cameron J | | author name = Cameron J | ||
| author affiliation = NRC/RGN-III/DRP/B6 | | author affiliation = NRC/RGN-III/DRP/B6 | ||
| addressee name = Pacilio M | | addressee name = Pacilio M | ||
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear | | addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear | ||
| docket = 05000237, 05000249 | | docket = 05000237, 05000249 | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:May 3, 2012 | ||
SUBJECT: DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - NRC INTEGRATED INSPECTION REPORT 05000237/ | ==SUBJECT:== | ||
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - NRC INTEGRATED INSPECTION REPORT 05000237/2012010 AND 05000249/2012010 | |||
==Dear Mr. Pacilio:== | ==Dear Mr. Pacilio:== | ||
On March 31, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Dresden Nuclear Power Station, Units 2 and 3. The enclosed inspection report documents the inspection results which were discussed on April 19, 2012, with Mr. | On March 31, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Dresden Nuclear Power Station, Units 2 and 3. The enclosed inspection report documents the inspection results which were discussed on April 19, 2012, with Mr. D. Czufin, and other members of your staff. | ||
The inspections examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license. | |||
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. | |||
One NRC identified finding of very low safety significance (Green) was identified during this inspection. This finding was determined to involve a violation of NRC requirements. The NRC is treating this violation as a non cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy. | One NRC identified finding of very low safety significance (Green) was identified during this inspection. This finding was determined to involve a violation of NRC requirements. The NRC is treating this violation as a non cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy. | ||
Line 34: | Line 34: | ||
If you contest this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555 0001, with copies to the Regional Administrator, Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532 4352; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001; and the NRC Resident Inspector Office at the Dresden Nuclear Power Station. | If you contest this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555 0001, with copies to the Regional Administrator, Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532 4352; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001; and the NRC Resident Inspector Office at the Dresden Nuclear Power Station. | ||
Enclosure transmitted herewith contains Sensitive Unclassified Non | Enclosure transmitted herewith contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | ||
-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading | |||
-rm/adams.html (the Public Electronic Reading Room). | |||
However, the material enclosed herewith contains Security | However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system. | ||
-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system. | |||
If Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security | If Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information in accordance with 10 CFR 2.390(d)(1) | ||
-Related Information in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response. | and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response. | ||
Sincerely,/RA/ Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50 | Sincerely, | ||
-237 and 50 | /RA/ | ||
-249 License Nos. DPR | Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50-237 and 50-249 License Nos. DPR-19 and DPR-25 Non-Public Enclosure: Inspection Report 05000237/2012010; 05000249/2012010 w/Attachment: Supplemental Information cc w/encl: S. Coker, NSIR/DSO/DDSO/ST R. Albert, NSIR C. Johnson, NSIR J. Trapp, RI B. Desai, RII M. Hay, RIV D. OFlanagan, Security Director, Dresden J. Klinger, State Liaison Officer, Illinois Emergency Management Agency cc w/o encl: Distribution via ListServ | ||
-19 and DPR | |||
-25 Non-Public | |||
Inspection Report 05000237/2012010; 05000249/2012010 | |||
Supplemental Information cc w/encl: S. Coker, NSIR/DSO/DDSO/ST R. Albert, NSIR C. Johnson, NSIR J. Trapp, RI B. Desai, RII M. Hay, RIV D. | |||
cc w/o encl: Distribution via ListServ | |||
}} | }} |
Latest revision as of 04:04, 12 November 2019
ML12124A268 | |
Person / Time | |
---|---|
Site: | Dresden |
Issue date: | 05/03/2012 |
From: | Jamnes Cameron NRC/RGN-III/DRP/B6 |
To: | Pacilio M Exelon Generation Co, Exelon Nuclear |
References | |
IR-12-010 | |
Download: ML12124A268 (4) | |
Text
May 3, 2012
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - NRC INTEGRATED INSPECTION REPORT 05000237/2012010 AND 05000249/2012010
Dear Mr. Pacilio:
On March 31, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Dresden Nuclear Power Station, Units 2 and 3. The enclosed inspection report documents the inspection results which were discussed on April 19, 2012, with Mr. D. Czufin, and other members of your staff.
The inspections examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
One NRC identified finding of very low safety significance (Green) was identified during this inspection. This finding was determined to involve a violation of NRC requirements. The NRC is treating this violation as a non cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555 0001, with copies to the Regional Administrator, Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532 4352; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001; and the NRC Resident Inspector Office at the Dresden Nuclear Power Station.
Enclosure transmitted herewith contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system.
If Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information in accordance with 10 CFR 2.390(d)(1)
and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA/
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50-237 and 50-249 License Nos. DPR-19 and DPR-25 Non-Public Enclosure: Inspection Report 05000237/2012010; 05000249/2012010 w/Attachment: Supplemental Information cc w/encl: S. Coker, NSIR/DSO/DDSO/ST R. Albert, NSIR C. Johnson, NSIR J. Trapp, RI B. Desai, RII M. Hay, RIV D. OFlanagan, Security Director, Dresden J. Klinger, State Liaison Officer, Illinois Emergency Management Agency cc w/o encl: Distribution via ListServ