VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION MONTHLY OPERATING REPORT MONTH Sept. | |||
YEAR 1978 (Revised 11-05-79) | YEAR 1978 (Revised 11-05-79) | ||
SUBMITTED: | SUBMITTED: | ||
\ | \\D | ||
_d1.,,.L SUPERINTENDENT - OrtRATIONS APPROVED: | |||
MANAGER " | |||
1367 298 2911s0054 6 | |||
OPERATLNG DATA REPORT DOCKET NO. | |||
DATE 11 W COMPLETED fly W. R. idadison TELEPliONE (703) 894-5151 OPERATING STATUS | DATE 11 W COMPLETED fly W. R. idadison TELEPliONE (703) 894-5151 OPERATING STATUS | ||
? orth Anna Notes .1. Unit Name: | ? orth Anna Notes. | ||
: 1. Unit Name: | |||
: 2. Reportin3 eriod: | |||
Septeraber 19/8 (iMvised) | Septeraber 19/8 (iMvised) | ||
P 3. Licenxd Thermal Power (5tWr): | P | ||
2775 4. Nameplate Rating (Gross SIWE): | : 3. Licenxd Thermal Power (5tWr): | ||
947 | 2775 | ||
907 6. Slaximum Dependable Capacity (Gross SlWe): | : 4. Nameplate Rating (Gross SIWE): | ||
928 098 7. Slaximtun Dependable Capacity (Net SIWE): | 947 | ||
: 5. Design Electrical Rating (Net 51We): | |||
907 | |||
: 6. Slaximum Dependable Capacity (Gross SlWe): | |||
928 098 | |||
: 7. Slaximtun Dependable Capacity (Net SIWE): | |||
: 8. If Changs Occur in Capacity Ratings (Items Number 3 Thmny.h 7) Since Last Report, Give Reasons: | : 8. If Changs Occur in Capacity Ratings (Items Number 3 Thmny.h 7) Since Last Report, Give Reasons: | ||
fl/A 9. Power Level To Which Restricted,If Any (Net SIW-): | fl/A | ||
U/A 10. Reasons For Restrictions.lf Any: | : 9. Power Level To Which Restricted,If Any (Net SIW-): | ||
b/b | U/A | ||
: 10. Reasons For Restrictions.lf Any: | |||
b/b This 5fonth | |||
._ Yr.-to-Date Cumulative | ._ Yr.-to-Date Cumulative | ||
: 11. Hours in Reporting Period 720 2,808 2,808 12. Number Of Hours Reactor Was Criticaj 526.7 2,562.7 2,562.7 13. Reactor Reserve Shutdown Hours 1 23.4 23.4 14. Hours Generator On Line 526.4 2,554.2 2,554.2 15. Unit Rurve Shutdowrt Hours 0 0 0 16. Gron Thermal Energy Generated (MWH) | : 11. Hours in Reporting Period 720 2,808 2,808 | ||
'1,436,384 6,629,199 6,629,199 17. Gr<ns Electrical Energy Generated (SiwH) 462.507 18. Net Electrical Energy Generated (MWH) 436, | : 12. Number Of Hours Reactor Was Criticaj 526.7 2,562.7 2,562.7 | ||
1.989.097 1. 0R 0 . 091_ | : 13. Reactor Reserve Shutdown Hours 1 | ||
: 19. Unit Service Factor 73.1 91.0 91.. Q, 20. Unit Avaibbility Factor 73.1 91.0~78.9 91.0 21. Unit Capacity F2ctor (Using MDC Net) 67.5 78.9 22. Unit Capadcy Factor (Using DER Net) 66.8 78.'l 78.1 0 0.4 0.4 23. Unit Forced Outage Rate | 23.4 23.4 | ||
: 14. Hours Generator On Line 526.4 2,554.2 2,554.2 | |||
: 15. Unit Rurve Shutdowrt Hours 0 | |||
0 0 | |||
: 16. Gron Thermal Energy Generated (MWH) | |||
'1,436,384 6,629,199 6,629,199 | |||
: 17. Gr<ns Electrical Energy Generated (SiwH) 462.507 | |||
: 18. Net Electrical Energy Generated (MWH) 436,174 2.123.910 2.191_. 91L_ | |||
1.989.097 | |||
: 1. 0R 0. 091_ | |||
: 19. Unit Service Factor 73.1 91.0 91.. Q, | |||
: 20. Unit Avaibbility Factor 73.1 91.0~ | |||
78.9 91.0 | |||
: 21. Unit Capacity F2ctor (Using MDC Net) 67.5 78.9 | |||
: 22. Unit Capadcy Factor (Using DER Net) 66.8 78.'l 78.1 0 | |||
0.4 0.4 | |||
: 23. Unit Forced Outage Rate | |||
: 24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each): | : 24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each): | ||
: 25. If Shut Down At End Of Report Period Estimated Date of Startup: | |||
Oct. 3, 1978 | Oct. 3, 1978 | ||
: 26. Units In Test Status (Prior to Commercial Operation): | : 26. Units In Test Status (Prior to Commercial Operation): | ||
Forecast Achieved | Forecast Achieved INITIA L CRITICA LITY INIIIAL ELECTRICITY CO3tM ERCIAL OPERATION 1367 299 | ||
("/77) | |||
.. -.}} | |||
Latest revision as of 21:39, 4 January 2025
| ML19210D130 | |
| Person / Time | |
|---|---|
| Site: | North Anna |
| Issue date: | 11/05/1979 |
| From: | Wil Madison VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.) |
| To: | |
| Shared Package | |
| ML19210D121 | List: |
| References | |
| NUDOCS 7911200565 | |
| Download: ML19210D130 (2) | |
Text
.
VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION MONTHLY OPERATING REPORT MONTH Sept.
YEAR 1978 (Revised 11-05-79)
SUBMITTED:
\\D
_d1.,,.L SUPERINTENDENT - OrtRATIONS APPROVED:
MANAGER "
1367 298 2911s0054 6
OPERATLNG DATA REPORT DOCKET NO.
DATE 11 W COMPLETED fly W. R. idadison TELEPliONE (703) 894-5151 OPERATING STATUS
? orth Anna Notes.
- 1. Unit Name:
- 2. Reportin3 eriod:
Septeraber 19/8 (iMvised)
P
- 3. Licenxd Thermal Power (5tWr):
2775
- 4. Nameplate Rating (Gross SIWE):
947
- 5. Design Electrical Rating (Net 51We):
907
- 6. Slaximum Dependable Capacity (Gross SlWe):
928 098
- 7. Slaximtun Dependable Capacity (Net SIWE):
- 8. If Changs Occur in Capacity Ratings (Items Number 3 Thmny.h 7) Since Last Report, Give Reasons:
fl/A
- 9. Power Level To Which Restricted,If Any (Net SIW-):
U/A
- 10. Reasons For Restrictions.lf Any:
b/b This 5fonth
._ Yr.-to-Date Cumulative
- 11. Hours in Reporting Period 720 2,808 2,808
- 12. Number Of Hours Reactor Was Criticaj 526.7 2,562.7 2,562.7
- 13. Reactor Reserve Shutdown Hours 1
23.4 23.4
- 14. Hours Generator On Line 526.4 2,554.2 2,554.2
- 15. Unit Rurve Shutdowrt Hours 0
0 0
- 16. Gron Thermal Energy Generated (MWH)
'1,436,384 6,629,199 6,629,199
- 17. Gr<ns Electrical Energy Generated (SiwH) 462.507
- 18. Net Electrical Energy Generated (MWH) 436,174 2.123.910 2.191_. 91L_
1.989.097
- 1. 0R 0. 091_
- 19. Unit Service Factor 73.1 91.0 91.. Q,
- 20. Unit Avaibbility Factor 73.1 91.0~
78.9 91.0
- 21. Unit Capacity F2ctor (Using MDC Net) 67.5 78.9
- 22. Unit Capadcy Factor (Using DER Net) 66.8 78.'l 78.1 0
0.4 0.4
- 23. Unit Forced Outage Rate
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each):
- 25. If Shut Down At End Of Report Period Estimated Date of Startup:
Oct. 3, 1978
- 26. Units In Test Status (Prior to Commercial Operation):
Forecast Achieved INITIA L CRITICA LITY INIIIAL ELECTRICITY CO3tM ERCIAL OPERATION 1367 299
("/77)
.. -.