#REDIRECT [[05000461/LER-2016-010]]
{{Adams
| number = ML17067A413
| issue date = 03/06/2017
| title = LER 16-010-01 for Clinton Power Station, Unit 1 Failure to Complete Technical Specification Required Actions within the Completion Time Resulted in a Condition Prohibited by Technical Specifications
| author name = Stoner T R
| author affiliation = Exelon Generation Co, LLC
| addressee name =
| addressee affiliation = NRC/Document Control Desk, NRC/NRR
| docket = 05000461
| license number = NPF-062
| contact person =
| case reference number = U-604334
| document report number = LER 16-010-01
| document type = Letter, Licensee Event Report (LER)
| page count = 4
| revision = 0
}}

Revision as of 18:24, 24 February 2018

LER 16-010-01 for Clinton Power Station, Unit 1 Failure to Complete Technical Specification Required Actions within the Completion Time Resulted in a Condition Prohibited by Technical Specifications
ML17067A413
Person / Time
Site: Clinton Constellation icon.png
Issue date: 03/06/2017
Revision: 0
From: Stoner T R
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
U-604334 LER 16-010-01
Download: ML17067A413 (4)