ML070650044: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
(3 intermediate revisions by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML070650044 | | number = ML070650044 | ||
| issue date = 03/06/2007 | | issue date = 03/06/2007 | ||
| title = SONGS, Units 2 & 3 - Decontrolled Version - Admin. Change to F.O.L. in Conjunction W/Commission Order EA-06-037 & Revisions to Physical Security Plan, Training & Qualification Plan, & Safeguards Contingency Plan | | title = SONGS, Units 2 & 3 - Decontrolled Version - Admin. Change to F.O.L. in Conjunction W/Commission Order EA-06-037 & Revisions to Physical Security Plan, Training & Qualification Plan, & Safeguards Contingency Plan | ||
| author name = Kalyanam N | | author name = Kalyanam N | ||
| author affiliation = NRC/NRR/ADRO/DORL/LPLIV | | author affiliation = NRC/NRR/ADRO/DORL/LPLIV | ||
| addressee name = Rosenblum R | | addressee name = Rosenblum R | ||
| addressee affiliation = Southern California Edison Co | | addressee affiliation = Southern California Edison Co | ||
| docket = 05000361, 05000362 | | docket = 05000361, 05000362 | ||
Line 14: | Line 14: | ||
| page count = 6 | | page count = 6 | ||
| project = TAC:MD2275, TAC:MD2276 | | project = TAC:MD2275, TAC:MD2276 | ||
| stage = | | stage = Other | ||
}} | }} | ||
=Text= | =Text= | ||
{{#Wiki_filter:t~pi REG&~UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 6, 2007 | {{#Wiki_filter:>42 t~pi REG&~ | ||
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 6, 2007 Mr. Richard M. Rosenblum Senior Vice President and Chief Nuclear Officer and Security Contact Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128 | |||
==SUBJECT:== | ==SUBJECT:== | ||
SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 -ADMINISTRATIVE CHANGE TO FACILITY OPERATING LICENSE IN CONJUNCTION WITH THE COMMISSION ORDER EA-06-037 AND REVISIONS TO PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN (TAC NOS. MD2275 AND MD2276) | SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 - | ||
ADMINISTRATIVE CHANGE TO FACILITY OPERATING LICENSE IN CONJUNCTION WITH THE COMMISSION ORDER EA-06-037 AND REVISIONS TO PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN (TAC NOS. MD2275 AND MD2276) | |||
==Dear Mr. Rosenblum:== | ==Dear Mr. Rosenblum:== | ||
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated May 15, 2006, Southern California Edison (the licensee), submitted revisions to its security plans at San Onofre Nuclear Generating Station (SONGS), Units 2 and 3, as required by Order EA-06-037 and confirmed the full implementation of Order EA-06-037. | By letter to the U.S. Nuclear Regulatory Commission (NRC) dated May 15, 2006, Southern California Edison (the licensee), submitted revisions to its security plans at San Onofre Nuclear Generating Station (SONGS), Units 2 and 3, as required by Order EA-06-037 and confirmed the full implementation of Order EA-06-037. Order EA-06-037 provided an update to an adversary characteristic of the design basis threat. | ||
Order EA-06-037 provided an update to an adversary characteristic of the design basis threat.The NRC staff has completed its review of the changes related to implementation of Order EA-06-037. | The NRC staff has completed its review of the changes related to implementation of Order EA-06-037. As discussed in the enclosed safeguards evaluation (Enclosure 2), the NRC staff has determined that the licensee's changes to the security plans, as described in its letter dated May 15, 2006, meet the requirements of the NRC Order and Title 10 of the Code of Federal Regulations(10 CFR) Part 73 requirements and are, therefore, acceptable. The effectiveness of these security provisions will continue to be the subject of NRC review and inspection. | ||
As discussed in the enclosed safeguards evaluation (Enclosure 2), the NRC staff has determined that the licensee's changes to the security plans, as described in its letter dated May 15, 2006, meet the requirements of the NRC Order and Title 10 of the Code of Federal Regulations (10 CFR) Part 73 requirements and are, therefore, acceptable. | Consistent with the Order, administrative license changes to Facility Operating License Nos. | ||
The effectiveness of these security provisions will continue to be the subject of NRC review and inspection. | NPF-10 and NPF-15 for SONGS 2 and 3, respectively, are being made to incorporate the NOTICE: Enclosure 2 contains Security-Related Information. Upon separation from Enclosure 2, this letter and Enclosure 1 are DECONTROLLED. | ||
Consistent with the Order, administrative license changes to Facility Operating License Nos.NPF-10 and NPF-15 for SONGS 2 and 3, respectively, are being made to incorporate the NOTICE: Enclosure 2 contains Security-Related Information. | OFFICIAL USE ONLY - SF.U-r*.RLATED INFORMATIe, | ||
Upon separation from Enclosure 2, this letter and Enclosure 1 are DECONTROLLED. | |||
OFFICIAL USE ONLY - | FIlllIAL USE ONLY' - 3eCurInl-RELATE-15 INFORMATION R. Rosenblum reference to the revised Physical Security Plan, Safeguards Contingency Plan, and Training and Qualification Plan. These changes comply with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in 10 CFR Chapter I. | ||
INFORMATIe, FIlllIAL USE ONLY' -3eCurInl-RELATE-15 INFORMATION reference to the revised Physical Security Plan, Safeguards Contingency Plan, and Training and Qualification Plan. These changes comply with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in 10 CFR Chapter I.Please replace Page 8 of the Facility Operating License NPF-10 and Page 7 of the Facility Operating License NPF-1 5 with the enclosed pages (Enclosure 1). The Safeguards Evaluation (Enclosure | Please replace Page 8 of the Facility Operating License NPF-10 and Page 7 of the Facility Operating License NPF-1 5 with the enclosed pages (Enclosure 1). The Safeguards Evaluation (Enclosure 2) to this letter is designated exempt from public disclosure under 10 CFR 2.390(d)(1). | ||
If you have any questions, please contact me at (301) 415-1480. | |||
If you have any questions, please contact me at (301) 415-1480.Sincerely, N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-361 and 50-362 | Sincerely, N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-361 and 50-362 | ||
==Enclosures:== | ==Enclosures:== | ||
: 1. Revised Page 8 of the FOL NPF-1 0 and Page 7 of the FOL NPF-15 2. Safeguards Evaluation cc w/encls 1 and 2: Mr. M. Shannon, Plant Support Branch, Region IV Mr. W. Maier, Regional State Liaison Officer, Region IV cc w/encl 1 only: See next page OFFICIAL USE ONLY - | : 1. Revised Page 8 of the FOL NPF-1 0 and Page 7 of the FOL NPF-15 | ||
The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21 is entitled: "San Onofre Nuclear Generating Station Security, Training and Qualification, and Safeguards Contingency Plan, Revision 2" submitted by letter dated May 15, 2006.F. This license is subject to the following additional condition for the protection of the environment: | : 2. Safeguards Evaluation cc w/encls 1 and 2: Mr. M. Shannon, Plant Support Branch, Region IV Mr. W. Maier, Regional State Liaison Officer, Region IV cc w/encl 1 only: See next page OFFICIAL USE ONLY - SECURern1 -RELATED INFORMATION -I- | ||
San Onofre Nuclear Generating Station Units 2 and 3 cc w/encl 1 and encl 2: | |||
Mr. Michael A. Shannon Mr. William A. Maier Plant Support Branch, Region IV Regional State Liaison Officer, Region IV U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Arlington, TX 76011-8064 cc w/encl 1 only: | |||
Mr. Daniel P. Breig Regional Administrator, Region IV Southern California Edison Company U.S. Nuclear Regulatory Commission San Onofre Nuclear Generating Station 611 Ryan Plaza Drive, Suite 400 P. 0. Box 128 Arlington, TX 76011-8064 San Clemente, CA 92674-0128 Mr. Michael R. Olson Mr. Douglas K. Porter, Esquire San Diego Gas & Electric Company Southern California Edison Company 8315 Century Park Ct. CP21G 2244 Walnut Grove Avenue San Diego, CA 92123-1548 Rosemead, CA 91770 Director, Radiologic Health Branch Mr. David Spath, Chief State Department of Health Services Division of Drinking Water and P.O. Box 997414, MS 7610 Environmental Management Sacramento, CA 95899-7414 P. 0. Box 942732 Sacramento, CA 94234-7320 Resident Inspector/San.Onofre NPS c/o U.S. Nuclear Regulatory Commission Chairman, Board of Supervisors Post Office Box 4329 County of San Diego San Clemente, CA 92674 1600 Pacific Highway, Room 335 San Diego, CA 92101 Mayor City of San Clemente Mark L. Parsons 100 Avenida Presidio Deputy City Attorney San Clemente, CA 92672 City of Riverside 3900 Main Street Mr. James T. Reilly Riverside, CA 92522 Southern California Edison Company San Onofre Nuclear Generating Station Mr. Gary L. Nolff P.O. Box 128 Assistant Director - Resources San Clemente, CA 92674-0128 City of Riverside 3900 Main Street Riverside, CA 92522 March 2006 | |||
San Onofre Nuclear Generating Station Units 2 and 3 cc w/encl 1 only: | |||
Mr. James D. Boyd, Commissioner Mr. Steve Hsu California Energy Commission Department of Health Services 1516 Ninth Street (MS 31) Radiologic Health Branch Sacramento, CA 95814 MS 7610, P.O. Box 997414 Sacramento, CA 95899 Mr. Ray Waldo, Vice President Southern California Edison Company Mr. A. Edward Scherer San Onofre Nuclear Generating Station Southern California Edison Company P.O. Box 128 San Onofre Nuclear Generating Station San Clemente, CA 92764-0128 P.O. Box 128 San Clemente, CA 92674-0128 Mr. Brian Katz Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92764-0128 March 2006 | |||
E. SCE shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21 is entitled: "San Onofre Nuclear Generating Station Security, Training and Qualification, and Safeguards Contingency Plan, Revision 2" submitted by letter dated May 15, 2006. | |||
F. This license is subject to the following additional condition for the protection of the environment: | |||
Before engaging in activities that may result in a significant adverse environmental impact that was not evaluated or that is significantly greater than that evaluated in the Final Environmental Statement, SCE shall provide a written notification of such activities to the NRC Office of Nuclear Reactor Regulation and receive written approval from that office before proceeding with such activities. | Before engaging in activities that may result in a significant adverse environmental impact that was not evaluated or that is significantly greater than that evaluated in the Final Environmental Statement, SCE shall provide a written notification of such activities to the NRC Office of Nuclear Reactor Regulation and receive written approval from that office before proceeding with such activities. | ||
G. DELETED H. SCE shall notify the Commission, as soon as possible but not later than one hour, of any accident at this facility which could result in an unplanned release of quantities of fission products in excess of allowable limits for normal operation established by the Commission. | G. DELETED H. SCE shall notify the Commission, as soon as possible but not later than one hour, of any accident at this facility which could result in an unplanned release of quantities of fission products in excess of allowable limits for normal operation established by the Commission. | ||
I. SCE shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.On September 29, 1983, the Safeguards Contingency Plan was made a separate, companion document to the Physical Security Plan pursuant to the authority of 10 CFR 50.54.Revised by letter dated March 6, 2007 Amendment No. 205 | I. SCE shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims. | ||
The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21 is entitled: "San Onofre Nuclear Generating Station Security, Training and Qualification, and Safeguards Contingency Plan, Revision 2" submitted by letter dated May 15, 2006.F. This license is subject to the following additional condition for the protection of the environment: | On September 29, 1983, the Safeguards Contingency Plan was made a separate, companion document to the Physical Security Plan pursuant to the authority of 10 CFR 50.54. | ||
Revised by letter dated March 6, 2007 Amendment No. 205 | |||
E. SCE shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21 is entitled: "San Onofre Nuclear Generating Station Security, Training and Qualification, and Safeguards Contingency Plan, Revision 2" submitted by letter dated May 15, 2006. | |||
F. This license is subject to the following additional condition for the protection of the environment: | |||
Before engaging in activities that may result in a significant adverse environmental impact that was not evaluated or that is significantly greater than that evaluated in the Final Environmental Statement, SCE shall provide a written notification of such activities to the NRC Office of Nuclear Reactor Regulation and receive written approval from that office before proceeding with such activities. | Before engaging in activities that may result in a significant adverse environmental impact that was not evaluated or that is significantly greater than that evaluated in the Final Environmental Statement, SCE shall provide a written notification of such activities to the NRC Office of Nuclear Reactor Regulation and receive written approval from that office before proceeding with such activities. | ||
G. DELETED H. SCE shall notify the Commission, as soon as possible but not later than one hour, of any accident at this facility which could result in an unplanned release of quantities of fission products in excess of allowable limits for normal operation established by the Commission. | G. DELETED H. SCE shall notify the Commission, as soon as possible but not later than one hour, of any accident at this facility which could result in an unplanned release of quantities of fission products in excess of allowable limits for normal operation established by the Commission. | ||
I. SCE shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.J. This license is effective as of the date of issuance and shall expire at midnight on November 15, 2022.On September 29, 1983, the Safeguards Contingency Plan was made a separate, companion document to the Physical Security Plan pursuant to the authority of 10 CFR 50.54.Revised by letter dated March 6, 2007 Amendment No. 197}} | I. SCE shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims. | ||
J. This license is effective as of the date of issuance and shall expire at midnight on November 15, 2022. | |||
On September 29, 1983, the Safeguards Contingency Plan was made a separate, companion document to the Physical Security Plan pursuant to the authority of 10 CFR 50.54. | |||
Revised by letter dated March 6, 2007 Amendment No. 197}} |
Latest revision as of 20:57, 22 March 2020
ML070650044 | |
Person / Time | |
---|---|
Site: | San Onofre |
Issue date: | 03/06/2007 |
From: | Kalyanam N NRC/NRR/ADRO/DORL/LPLIV |
To: | Rosenblum R Southern California Edison Co |
Kalyanam N, NRR/DORL/LP4, 415-1480 | |
References | |
EA-06-037, TAC MD2275, TAC MD2276 | |
Download: ML070650044 (6) | |
Text
>42 t~pi REG&~
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 6, 2007 Mr. Richard M. Rosenblum Senior Vice President and Chief Nuclear Officer and Security Contact Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128
SUBJECT:
SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 -
ADMINISTRATIVE CHANGE TO FACILITY OPERATING LICENSE IN CONJUNCTION WITH THE COMMISSION ORDER EA-06-037 AND REVISIONS TO PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN (TAC NOS. MD2275 AND MD2276)
Dear Mr. Rosenblum:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated May 15, 2006, Southern California Edison (the licensee), submitted revisions to its security plans at San Onofre Nuclear Generating Station (SONGS), Units 2 and 3, as required by Order EA-06-037 and confirmed the full implementation of Order EA-06-037. Order EA-06-037 provided an update to an adversary characteristic of the design basis threat.
The NRC staff has completed its review of the changes related to implementation of Order EA-06-037. As discussed in the enclosed safeguards evaluation (Enclosure 2), the NRC staff has determined that the licensee's changes to the security plans, as described in its letter dated May 15, 2006, meet the requirements of the NRC Order and Title 10 of the Code of Federal Regulations(10 CFR) Part 73 requirements and are, therefore, acceptable. The effectiveness of these security provisions will continue to be the subject of NRC review and inspection.
Consistent with the Order, administrative license changes to Facility Operating License Nos.
NPF-10 and NPF-15 for SONGS 2 and 3, respectively, are being made to incorporate the NOTICE: Enclosure 2 contains Security-Related Information. Upon separation from Enclosure 2, this letter and Enclosure 1 are DECONTROLLED.
OFFICIAL USE ONLY - SF.U-r*.RLATED INFORMATIe,
FIlllIAL USE ONLY' - 3eCurInl-RELATE-15 INFORMATION R. Rosenblum reference to the revised Physical Security Plan, Safeguards Contingency Plan, and Training and Qualification Plan. These changes comply with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in 10 CFR Chapter I.
Please replace Page 8 of the Facility Operating License NPF-10 and Page 7 of the Facility Operating License NPF-1 5 with the enclosed pages (Enclosure 1). The Safeguards Evaluation (Enclosure 2) to this letter is designated exempt from public disclosure under 10 CFR 2.390(d)(1).
If you have any questions, please contact me at (301) 415-1480.
Sincerely, N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-361 and 50-362
Enclosures:
- 2. Safeguards Evaluation cc w/encls 1 and 2: Mr. M. Shannon, Plant Support Branch, Region IV Mr. W. Maier, Regional State Liaison Officer, Region IV cc w/encl 1 only: See next page OFFICIAL USE ONLY - SECURern1 -RELATED INFORMATION -I-
San Onofre Nuclear Generating Station Units 2 and 3 cc w/encl 1 and encl 2:
Mr. Michael A. Shannon Mr. William A. Maier Plant Support Branch, Region IV Regional State Liaison Officer, Region IV U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Arlington, TX 76011-8064 cc w/encl 1 only:
Mr. Daniel P. Breig Regional Administrator, Region IV Southern California Edison Company U.S. Nuclear Regulatory Commission San Onofre Nuclear Generating Station 611 Ryan Plaza Drive, Suite 400 P. 0. Box 128 Arlington, TX 76011-8064 San Clemente, CA 92674-0128 Mr. Michael R. Olson Mr. Douglas K. Porter, Esquire San Diego Gas & Electric Company Southern California Edison Company 8315 Century Park Ct. CP21G 2244 Walnut Grove Avenue San Diego, CA 92123-1548 Rosemead, CA 91770 Director, Radiologic Health Branch Mr. David Spath, Chief State Department of Health Services Division of Drinking Water and P.O. Box 997414, MS 7610 Environmental Management Sacramento, CA 95899-7414 P. 0. Box 942732 Sacramento, CA 94234-7320 Resident Inspector/San.Onofre NPS c/o U.S. Nuclear Regulatory Commission Chairman, Board of Supervisors Post Office Box 4329 County of San Diego San Clemente, CA 92674 1600 Pacific Highway, Room 335 San Diego, CA 92101 Mayor City of San Clemente Mark L. Parsons 100 Avenida Presidio Deputy City Attorney San Clemente, CA 92672 City of Riverside 3900 Main Street Mr. James T. Reilly Riverside, CA 92522 Southern California Edison Company San Onofre Nuclear Generating Station Mr. Gary L. Nolff P.O. Box 128 Assistant Director - Resources San Clemente, CA 92674-0128 City of Riverside 3900 Main Street Riverside, CA 92522 March 2006
San Onofre Nuclear Generating Station Units 2 and 3 cc w/encl 1 only:
Mr. James D. Boyd, Commissioner Mr. Steve Hsu California Energy Commission Department of Health Services 1516 Ninth Street (MS 31) Radiologic Health Branch Sacramento, CA 95814 MS 7610, P.O. Box 997414 Sacramento, CA 95899 Mr. Ray Waldo, Vice President Southern California Edison Company Mr. A. Edward Scherer San Onofre Nuclear Generating Station Southern California Edison Company P.O. Box 128 San Onofre Nuclear Generating Station San Clemente, CA 92764-0128 P.O. Box 128 San Clemente, CA 92674-0128 Mr. Brian Katz Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92764-0128 March 2006
E. SCE shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21 is entitled: "San Onofre Nuclear Generating Station Security, Training and Qualification, and Safeguards Contingency Plan, Revision 2" submitted by letter dated May 15, 2006.
F. This license is subject to the following additional condition for the protection of the environment:
Before engaging in activities that may result in a significant adverse environmental impact that was not evaluated or that is significantly greater than that evaluated in the Final Environmental Statement, SCE shall provide a written notification of such activities to the NRC Office of Nuclear Reactor Regulation and receive written approval from that office before proceeding with such activities.
G. DELETED H. SCE shall notify the Commission, as soon as possible but not later than one hour, of any accident at this facility which could result in an unplanned release of quantities of fission products in excess of allowable limits for normal operation established by the Commission.
I. SCE shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
On September 29, 1983, the Safeguards Contingency Plan was made a separate, companion document to the Physical Security Plan pursuant to the authority of 10 CFR 50.54.
Revised by letter dated March 6, 2007 Amendment No. 205
E. SCE shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21 is entitled: "San Onofre Nuclear Generating Station Security, Training and Qualification, and Safeguards Contingency Plan, Revision 2" submitted by letter dated May 15, 2006.
F. This license is subject to the following additional condition for the protection of the environment:
Before engaging in activities that may result in a significant adverse environmental impact that was not evaluated or that is significantly greater than that evaluated in the Final Environmental Statement, SCE shall provide a written notification of such activities to the NRC Office of Nuclear Reactor Regulation and receive written approval from that office before proceeding with such activities.
G. DELETED H. SCE shall notify the Commission, as soon as possible but not later than one hour, of any accident at this facility which could result in an unplanned release of quantities of fission products in excess of allowable limits for normal operation established by the Commission.
I. SCE shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
J. This license is effective as of the date of issuance and shall expire at midnight on November 15, 2022.
On September 29, 1983, the Safeguards Contingency Plan was made a separate, companion document to the Physical Security Plan pursuant to the authority of 10 CFR 50.54.
Revised by letter dated March 6, 2007 Amendment No. 197