{{Adams
{{Adams
| number = ML19261A083
| number = ML19322A009
| issue date = 09/18/2019
| issue date = 11/14/2019
| title = R. E. Ginna Nuclear Power Plant: Design Bases Assurance Inspection (Teams) Report 05000244/2019010 and Notice of Violation
| title = U.S. Nuclear Regulatory Commission Acknowledgement of Disputed Cited Violation 05000244/2019010-02
| author name = Gray M
| author name = Krohn P
| author affiliation = NRC/RGN-I/DRS
| author affiliation = NRC/RGN-I/DRS
| addressee name = Hanson B
| addressee name = Hanson B
Line 9: Line 9:
| docket = 05000244
| docket = 05000244
| license number = DPR-018
| license number = DPR-018
| contact person =  
| contact person = Gray M
| case reference number = EA-19-122
| document report number = IR 2019010
| document report number = IR 2019010
| document type = Inspection Report, Letter, Notice of Violation
| document type = Letter
| page count = 21
| page count = 3
}}
}}


Line 18: Line 19:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION
 
==REGION I==
2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 November 14, 2019 EA-19-122 Mr. Bryan Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 SUBJECT: U.S. NUCLEAR REGULATORY COMMISSION ACKNOWLEDGEMENT OF DISPUTED CITED VIOLATION 05000244/2019010-02
 
==Dear Mr. Hanson:==
I am writing to acknowledge receipt of Exelon Generation Company, LLCs (Exelons) letter dated October 16, 2019, in response to U.S. Nuclear Regulatory Commission (NRC) Inspection Report 05000244/2019010 issued on September 18, 2019 (ML19261A083)1.
 
In the letter (ML19291A173), Exelon contested a finding of very low safety significance (Green)
and associated Notice of Violation (NOV 05000244/2019010-02) issued to R. E. Ginna Nuclear Power Plant (Ginna). The finding and violation involved a failure by Ginna to design or ensure that in the event of a design-basis earthquake, the safety-related Emergency Diesel Generator (EDG) Motor Control Centers (MCCs) H and J would not be lost due to an electrical circuit fault in the non-safety-related sump pump motors. Exelon stated that Ginna met the NRC's standards in effect at the time of its construction as well as those in effect at the time of Application for Full-Term Operating License (1972) and as such, Exelon views that the NOV is unwarranted and should be rescinded. Additionally, Exelon believes that the position reflected in the inspection report constitutes a backfit and asks that the NRC assess these concerns consistent with agency backfitting processes. The NRC intends to review Exelons response and provide a letter documenting the basis for any decision relative to the disputed NOV and backfitting.
 
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available
 
Designation refers to an Agencywide Documents Access and Management System (ADAMS) accession number. Documents referenced in this letter are publicly available using the accession number in ADAMS at https://adams.nrc.gov/wba/. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209; 301-415-4737, or by e-mail to pdr.resource@nrc.gov Records component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRCs website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
Should you have any questions concerning this letter, please contact me at (610) 337-5081.
 
Sincerely,
/RA/
Paul G. Krohn, Deputy Director Division of Reactor Safety Docket No. 50-244 License No. DPR-18 cc: Distribution via ListServ
 
ML19322A009 Non-Sensitive  Publicly Available SUNSI Review Sensitive  Non-Publicly Available OFFICE RI/DRS RI/DRS  RI/DRP RI/EAGL  RI/RC NAME KMangan via email MGray  ECarfang RMcKinley  BKlukan DATE 11/13/19 11/13/19 11/13/19 11/14/19  11/14/19 OFFICE RI/DRS NAME PKrohn DATE 11/14/19
}}
}}

Revision as of 13:26, 28 November 2019

U.S. Nuclear Regulatory Commission Acknowledgement of Disputed Cited Violation 05000244/2019010-02
ML19322A009
Person / Time
Site: Ginna Constellation icon.png
Issue date: 11/14/2019
From: Paul Krohn
Division of Reactor Safety I
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Gray M
References
EA-19-122 IR 2019010
Download: ML19322A009 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 November 14, 2019 EA-19-122 Mr. Bryan Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 SUBJECT: U.S. NUCLEAR REGULATORY COMMISSION ACKNOWLEDGEMENT OF DISPUTED CITED VIOLATION 05000244/2019010-02

Dear Mr. Hanson:

I am writing to acknowledge receipt of Exelon Generation Company, LLCs (Exelons) letter dated October 16, 2019, in response to U.S. Nuclear Regulatory Commission (NRC) Inspection Report 05000244/2019010 issued on September 18, 2019 (ML19261A083)1.

In the letter (ML19291A173), Exelon contested a finding of very low safety significance (Green)

and associated Notice of Violation (NOV 05000244/2019010-02) issued to R. E. Ginna Nuclear Power Plant (Ginna). The finding and violation involved a failure by Ginna to design or ensure that in the event of a design-basis earthquake, the safety-related Emergency Diesel Generator (EDG) Motor Control Centers (MCCs) H and J would not be lost due to an electrical circuit fault in the non-safety-related sump pump motors. Exelon stated that Ginna met the NRC's standards in effect at the time of its construction as well as those in effect at the time of Application for Full-Term Operating License (1972) and as such, Exelon views that the NOV is unwarranted and should be rescinded. Additionally, Exelon believes that the position reflected in the inspection report constitutes a backfit and asks that the NRC assess these concerns consistent with agency backfitting processes. The NRC intends to review Exelons response and provide a letter documenting the basis for any decision relative to the disputed NOV and backfitting.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available

Designation refers to an Agencywide Documents Access and Management System (ADAMS) accession number. Documents referenced in this letter are publicly available using the accession number in ADAMS at https://adams.nrc.gov/wba/. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209; 301-415-4737, or by e-mail to pdr.resource@nrc.gov Records component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRCs website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this letter, please contact me at (610) 337-5081.

Sincerely,

/RA/

Paul G. Krohn, Deputy Director Division of Reactor Safety Docket No. 50-244 License No. DPR-18 cc: Distribution via ListServ

ML19322A009 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRS RI/DRS RI/DRP RI/EAGL RI/RC NAME KMangan via email MGray ECarfang RMcKinley BKlukan DATE 11/13/19 11/13/19 11/13/19 11/14/19 11/14/19 OFFICE RI/DRS NAME PKrohn DATE 11/14/19