{{#Wiki_filter:March 23, 2006Mrs. Mary G. KorsnickVice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519
{{#Wiki_filter:March 23, 2006 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519


==SUBJECT:==
==SUBJECT:==
R.E. GINNA NUCLEAR POWER PLANT - REQUEST FOR ADDITIONALINFORMATION REGARDING MOVEMENT OF FUEL WITH EQUIPMENT HATCH OPEN (TAC NO. MC8910)
R.E. GINNA NUCLEAR POWER PLANT - REQUEST FOR ADDITIONAL INFORMATION REGARDING MOVEMENT OF FUEL WITH EQUIPMENT HATCH OPEN (TAC NO. MC8910)


==Dear Mrs. Korsnick:==
==Dear Mrs. Korsnick:==


By a letter dated November 7, 2005, R.E. Ginna Nuclear Power Plant, LLC (Ginna LLC)requested an amendment to the Technical Specifications (TSs) for the R. E. Ginna NuclearPower Plant. Specifically, Ginna LLC proposed to revise TS 3.9.3, "Containment Penetrations,"
By a letter dated November 7, 2005, R.E. Ginna Nuclear Power Plant, LLC (Ginna LLC) requested an amendment to the Technical Specifications (TSs) for the R. E. Ginna Nuclear Power Plant. Specifically, Ginna LLC proposed to revise TS 3.9.3, Containment Penetrations, to allow an emergency egress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment.
to allow an emergency egress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment.The Nuclear Regulatory Commission staff has reviewed the information provided in theapplication and has determined that additional information is needed. The specific information is described in the enclosed request for additional information (RAI). During a telephone discussion with the Ginna LLC staff on March 22, 2006, it was agreed that a response would be provided within 45 days from the date of this letter.If you have any questions, please contact me at 301-415-1457.Sincerely,/RA/Patrick D. Milano, Senior Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-244
The Nuclear Regulatory Commission staff has reviewed the information provided in the application and has determined that additional information is needed. The specific information is described in the enclosed request for additional information (RAI). During a telephone discussion with the Ginna LLC staff on March 22, 2006, it was agreed that a response would be provided within 45 days from the date of this letter.
If you have any questions, please contact me at 301-415-1457.
Sincerely,
                                            /RA/
Patrick D. Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244


==Enclosure:==
==Enclosure:==
RAIcc w/encl: See next page March 23, 2006Mrs. Mary G. KorsnickVice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519
 
RAI cc w/encl: See next page
 
March 23, 2006 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519


==SUBJECT:==
==SUBJECT:==
R.E. GINNA NUCLEAR POWER PLANT - REQUEST FOR ADDITIONALINFORMATION REGARDING MOVEMENT OF FUEL WITH EQUIPMENT HATCH OPEN (TAC NO. MC8910)
R.E. GINNA NUCLEAR POWER PLANT - REQUEST FOR ADDITIONAL INFORMATION REGARDING MOVEMENT OF FUEL WITH EQUIPMENT HATCH OPEN (TAC NO. MC8910)


==Dear Mrs. Korsnick:==
==Dear Mrs. Korsnick:==


By a letter dated November 7, 2005, R.E. Ginna Nuclear Power Plant, LLC (Ginna LLC)requested an amendment to the Technical Specifications (TSs) for the R. E. Ginna NuclearPower Plant. Specifically, Ginna LLC proposed to revise TS 3.9.3, "Containment Penetrations,"
By a letter dated November 7, 2005, R.E. Ginna Nuclear Power Plant, LLC (Ginna LLC) requested an amendment to the Technical Specifications (TSs) for the R. E. Ginna Nuclear Power Plant. Specifically, Ginna LLC proposed to revise TS 3.9.3, Containment Penetrations, to allow an emergency egress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment.
to allow an emergency egress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment.The Nuclear Regulatory Commission staff has reviewed the information provided in theapplication and has determined that additional information is needed. The specific information is described in the enclosed request for additional information (RAI). During a telephone discussion with the Ginna LLC staff on March 22, 2006, it was agreed that a response would be provided within 45 days from the date of this letter.If you have any questions, please contact me at 301-415-1457.Sincerely,/RA/Patrick D. Milano, Senior Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-244
The Nuclear Regulatory Commission staff has reviewed the information provided in the application and has determined that additional information is needed. The specific information is described in the enclosed request for additional information (RAI). During a telephone discussion with the Ginna LLC staff on March 22, 2006, it was agreed that a response would be provided within 45 days from the date of this letter.
If you have any questions, please contact me at 301-415-1457.
Sincerely,
                                              /RA/
Patrick D. Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244


==Enclosure:==
==Enclosure:==
RAIcc w/encl: See next page Accession Number: ML060810211OFFICELPLI-1\PMLPLI-1\LAAADB\BCLPLI-1\BCNAMEPMilanoSLittleMKotzalasRLauferDATE03/22/0603/22/0602/24/0603/23/06Official Record Copy REQUEST FOR ADDITIONAL INFORMATION RE: AMENDMENT TO RENEWED FACILITYOPERATING LICENSE NO. DPR-18 FOR FUEL MOVEMENT WITH EQUIPMENT HATCH OPEN AT R.E. GINNA NUCLEAR POWER PLANTDISTRIBUTION:PUBLICLPLI-1 Reading File R. LauferRidsNrrDorlLpla S. LittleRidsNrrLASLittle P. MilanoRidsNrrPMPMilano M. KotzalasRidsNrrDraAadb L. Brown OGC RidsOgcMailCenter ACRSRidsAcrsAcnwMailCenter B. McDermott, R-IRidsRgn1MailCenterB. SingalRidsNrrDorlLdprcc: Plant Service list R.E. Ginna Nuclear Power Plant cc:
 
Mr. Michael J. WallacePresident R.E. Ginna Nuclear Power Plant, LLC c/o Constellation Energy 750 East Pratt Street Baltimore, MD 21202Mr. John M. HeffleySenior Vice President and Chief Nuclear Officer Constellation Generation Group 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401Kenneth Kolaczyk, Sr. Resident InspectorR.E. Ginna Nuclear Power Plant U.S. Nuclear Regulatory Commission 1503 Lake Road Ontario, NY 14519Regional Administrator, Region IU.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406Mr. Peter R. Smith, PresidentNew York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399Mr. Carey W. Fleming, EsquireSenior Counsel - Nuclear Generation Constellation Generation Group, LLC 750 East Pratt Street, 17th Floor Baltimore, MD 21202Mr. Charles Donaldson, EsquireAssistant Attorney General New York Department of Law 120 Broadway New York, NY 10271Ms. Thelma Wideman, DirectorWayne County Emergency Management Office Wayne County Emergency Operations Center 7336 Route 31 Lyons, NY  14489Ms. Mary Louise MeisenzahlAdministrator, Monroe County Office of Emergency Preparedness 1190 Scottsville Road, Suite 200Rochester, NY  14624Mr. Paul EddyNew York State Department of Public Service 3 Empire State Plaza, 10th Floor Albany, NY  12223 REQUEST FOR ADDITIONAL INFORMATIONREGARDING FUEL MOVEMENT WITH EQUIPMENT HATCH OPENR.E. GINNA NUCLEAR POWER PLANT, LLCR.E. GINNA NUCLEAR POWER PLANTDOCKET NO. 50-244By a letter dated November 7, 2005 (Agencywide Documents Access and Management SystemAccession No. ML053190213), R.E. Ginna Nuclear Power Plant, LLC (the licensee) proposed a revision to Technical Specification 3.9.3, "Containment Penetrations," to allow an emergencyegress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment. In order to complete its review of the information in the application, the Nuclear Regulatory Commission (NRC) staff requests the following information:1.In Enclosure 1 to the November 7, 2005, application, the licensee states that theproposed amendment would permit either both equipment hatch doors, the closure plateaccess door, or the roll-up door associated with the enclosure building to be open during refueling. The control room atmospheric dispersion factor (/Q value) used in the doseassessment to support this amendment request assumes that the equipment hatch is the limiting case because it is the largest penetration and has the shortest distance to the control room air intake. However, the equipment hatch to control room /Q valueswere generated assuming a diffuse (area) release, which could result in lower /Qvalues than for a point source release slightly further from the control room intake.Confirm that the control room X/Q values associated with a postulated release from theequipment hatch are more limiting than the postulated releases from the closure plateaccess door or the roll-up door associated with the enclosure building.Enclosure}}
RAI cc w/encl: See next page Accession Number: ML060810211 OFFICE        LPLI-1\PM LPLI-1\LA              AADB\BC          LPLI-1\BC NAME          PMilano      SLittle            MKotzalas        RLaufer DATE          03/22/06      03/22/06          02/24/06        03/23/06 Official Record Copy
 
REQUEST FOR ADDITIONAL INFORMATION RE: AMENDMENT TO RENEWED FACILITY OPERATING LICENSE NO. DPR-18 FOR FUEL MOVEMENT WITH EQUIPMENT HATCH OPEN AT R.E. GINNA NUCLEAR POWER PLANT DISTRIBUTION:
PUBLIC LPLI-1 Reading File R. Laufer              RidsNrrDorlLpla S. Little              RidsNrrLASLittle P. Milano              RidsNrrPMPMilano M. Kotzalas            RidsNrrDraAadb L. Brown OGC                   RidsOgcMailCenter ACRS                  RidsAcrsAcnwMailCenter B. McDermott, R-I      RidsRgn1MailCenter B. Singal              RidsNrrDorlLdpr cc: Plant Service list
 
R.E. Ginna Nuclear Power Plant cc:
Mr. Michael J. Wallace                  Ms. Thelma Wideman, Director President                                Wayne County Emergency Management R.E. Ginna Nuclear Power Plant, LLC       Office c/o Constellation Energy                 Wayne County Emergency Operations 750 East Pratt Street                   Center Baltimore, MD 21202                      7336 Route 31 Lyons, NY 14489 Mr. John M. Heffley Senior Vice President and               Ms. Mary Louise Meisenzahl Chief Nuclear Officer                   Administrator, Monroe County Constellation Generation Group           Office of Emergency Preparedness 1997 Annapolis Exchange Parkway         1190 Scottsville Road, Suite 200 Suite 500                               Rochester, NY 14624 Annapolis, MD 21401 Mr. Paul Eddy Kenneth Kolaczyk, Sr. Resident Inspector New York State Department of R.E. Ginna Nuclear Power Plant           Public Service U.S. Nuclear Regulatory Commission       3 Empire State Plaza, 10th Floor 1503 Lake Road                           Albany, NY 12223 Ontario, NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Carey W. Fleming, Esquire Senior Counsel - Nuclear Generation Constellation Generation Group, LLC 750 East Pratt Street, 17th Floor Baltimore, MD 21202 Mr. Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271
 
REQUEST FOR ADDITIONAL INFORMATION REGARDING FUEL MOVEMENT WITH EQUIPMENT HATCH OPEN R.E. GINNA NUCLEAR POWER PLANT, LLC R.E. GINNA NUCLEAR POWER PLANT DOCKET NO. 50-244 By a letter dated November 7, 2005 (Agencywide Documents Access and Management System Accession No. ML053190213), R.E. Ginna Nuclear Power Plant, LLC (the licensee) proposed a revision to Technical Specification 3.9.3, Containment Penetrations, to allow an emergency egress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment. In order to complete its review of the information in the application, the Nuclear Regulatory Commission (NRC) staff requests the following information:
: 1.     In Enclosure 1 to the November 7, 2005, application, the licensee states that the proposed amendment would permit either both equipment hatch doors, the closure plate access door, or the roll-up door associated with the enclosure building to be open during refueling. The control room atmospheric dispersion factor (/Q value) used in the dose assessment to support this amendment request assumes that the equipment hatch is the limiting case because it is the largest penetration and has the shortest distance to the control room air intake. However, the equipment hatch to control room /Q values were generated assuming a diffuse (area) release, which could result in lower /Q values than for a point source release slightly further from the control room intake.
Confirm that the control room X/Q values associated with a postulated release from the equipment hatch are more limiting than the postulated releases from the closure plate access door or the roll-up door associated with the enclosure building.
Enclosure}}

Latest revision as of 21:51, 23 November 2019

R. E. Ginna Nuclear Power Plant - Request for Additional Information Movement of Fuel with Eqiupment Hatch Open
ML060810211
Person / Time
Site: Ginna Constellation icon.png
Issue date: 03/23/2006
From: Milano P
NRC/NRR/ADRO/DORL/LPLA
To: Korsnick M
Ginna
Boska J, NRR, 301-415-2901
References
TAC MC8910
Download: ML060810211 (5)


Text

March 23, 2006 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519

SUBJECT:

R.E. GINNA NUCLEAR POWER PLANT - REQUEST FOR ADDITIONAL INFORMATION REGARDING MOVEMENT OF FUEL WITH EQUIPMENT HATCH OPEN (TAC NO. MC8910)

Dear Mrs. Korsnick:

By a letter dated November 7, 2005, R.E. Ginna Nuclear Power Plant, LLC (Ginna LLC) requested an amendment to the Technical Specifications (TSs) for the R. E. Ginna Nuclear Power Plant. Specifically, Ginna LLC proposed to revise TS 3.9.3, Containment Penetrations, to allow an emergency egress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment.

The Nuclear Regulatory Commission staff has reviewed the information provided in the application and has determined that additional information is needed. The specific information is described in the enclosed request for additional information (RAI). During a telephone discussion with the Ginna LLC staff on March 22, 2006, it was agreed that a response would be provided within 45 days from the date of this letter.

If you have any questions, please contact me at 301-415-1457.

Sincerely,

/RA/

Patrick D. Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosure:

RAI cc w/encl: See next page

March 23, 2006 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519

SUBJECT:

R.E. GINNA NUCLEAR POWER PLANT - REQUEST FOR ADDITIONAL INFORMATION REGARDING MOVEMENT OF FUEL WITH EQUIPMENT HATCH OPEN (TAC NO. MC8910)

Dear Mrs. Korsnick:

By a letter dated November 7, 2005, R.E. Ginna Nuclear Power Plant, LLC (Ginna LLC) requested an amendment to the Technical Specifications (TSs) for the R. E. Ginna Nuclear Power Plant. Specifically, Ginna LLC proposed to revise TS 3.9.3, Containment Penetrations, to allow an emergency egress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment.

The Nuclear Regulatory Commission staff has reviewed the information provided in the application and has determined that additional information is needed. The specific information is described in the enclosed request for additional information (RAI). During a telephone discussion with the Ginna LLC staff on March 22, 2006, it was agreed that a response would be provided within 45 days from the date of this letter.

If you have any questions, please contact me at 301-415-1457.

Sincerely,

/RA/

Patrick D. Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosure:

RAI cc w/encl: See next page Accession Number: ML060810211 OFFICE LPLI-1\PM LPLI-1\LA AADB\BC LPLI-1\BC NAME PMilano SLittle MKotzalas RLaufer DATE 03/22/06 03/22/06 02/24/06 03/23/06 Official Record Copy

REQUEST FOR ADDITIONAL INFORMATION RE: AMENDMENT TO RENEWED FACILITY OPERATING LICENSE NO. DPR-18 FOR FUEL MOVEMENT WITH EQUIPMENT HATCH OPEN AT R.E. GINNA NUCLEAR POWER PLANT DISTRIBUTION:

PUBLIC LPLI-1 Reading File R. Laufer RidsNrrDorlLpla S. Little RidsNrrLASLittle P. Milano RidsNrrPMPMilano M. Kotzalas RidsNrrDraAadb L. Brown OGC RidsOgcMailCenter ACRS RidsAcrsAcnwMailCenter B. McDermott, R-I RidsRgn1MailCenter B. Singal RidsNrrDorlLdpr cc: Plant Service list

R.E. Ginna Nuclear Power Plant cc:

Mr. Michael J. Wallace Ms. Thelma Wideman, Director President Wayne County Emergency Management R.E. Ginna Nuclear Power Plant, LLC Office c/o Constellation Energy Wayne County Emergency Operations 750 East Pratt Street Center Baltimore, MD 21202 7336 Route 31 Lyons, NY 14489 Mr. John M. Heffley Senior Vice President and Ms. Mary Louise Meisenzahl Chief Nuclear Officer Administrator, Monroe County Constellation Generation Group Office of Emergency Preparedness 1997 Annapolis Exchange Parkway 1190 Scottsville Road, Suite 200 Suite 500 Rochester, NY 14624 Annapolis, MD 21401 Mr. Paul Eddy Kenneth Kolaczyk, Sr. Resident Inspector New York State Department of R.E. Ginna Nuclear Power Plant Public Service U.S. Nuclear Regulatory Commission 3 Empire State Plaza, 10th Floor 1503 Lake Road Albany, NY 12223 Ontario, NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Carey W. Fleming, Esquire Senior Counsel - Nuclear Generation Constellation Generation Group, LLC 750 East Pratt Street, 17th Floor Baltimore, MD 21202 Mr. Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271

REQUEST FOR ADDITIONAL INFORMATION REGARDING FUEL MOVEMENT WITH EQUIPMENT HATCH OPEN R.E. GINNA NUCLEAR POWER PLANT, LLC R.E. GINNA NUCLEAR POWER PLANT DOCKET NO. 50-244 By a letter dated November 7, 2005 (Agencywide Documents Access and Management System Accession No. ML053190213), R.E. Ginna Nuclear Power Plant, LLC (the licensee) proposed a revision to Technical Specification 3.9.3, Containment Penetrations, to allow an emergency egress door, access door, or roll-up door, as associated with the equipment hatch, to be open, but capable of being closed, during core alterations or movement of irradiated fuel within containment. In order to complete its review of the information in the application, the Nuclear Regulatory Commission (NRC) staff requests the following information:

1. In Enclosure 1 to the November 7, 2005, application, the licensee states that the proposed amendment would permit either both equipment hatch doors, the closure plate access door, or the roll-up door associated with the enclosure building to be open during refueling. The control room atmospheric dispersion factor (/Q value) used in the dose assessment to support this amendment request assumes that the equipment hatch is the limiting case because it is the largest penetration and has the shortest distance to the control room air intake. However, the equipment hatch to control room /Q values were generated assuming a diffuse (area) release, which could result in lower /Q values than for a point source release slightly further from the control room intake.

Confirm that the control room X/Q values associated with a postulated release from the equipment hatch are more limiting than the postulated releases from the closure plate access door or the roll-up door associated with the enclosure building.

Enclosure