ML12234A517
| ML12234A517 | |
| Person / Time | |
|---|---|
| Site: | Ginna |
| Issue date: | 08/21/2012 |
| From: | Thadani M Plant Licensing Branch 1 |
| To: | Harding T Constellation Energy Nuclear Group |
| Thadani M | |
| References | |
| Download: ML12234A517 (2) | |
Text
From:
Thadani, Mohan To:
Harding Jr, Thomas Cc:
Roundtree, Amy
Subject:
Physical Security Plan Change Per 10 CFR 50.54(p)(2)
Date:
Tuesday, August 21, 2012 10:25:00 AM Attachments:
image001.png Tom:
By letter dated July 31, 2012 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML12215AA119), Constellation Energy Nuclear Group (the licensee) submitted the R.E Ginna Nuclear Power Plants Physical Security Plan (PSP), Training and Qualification Plan (T&QP), and Safeguards Contingency Plan (SCP), Revision 9. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2). The NRC staff has determined that the additional information requested below is needed for the NRC staff to complete its review.
10 CFR 50.54(p)(2) CHANGES TO SECURITY PLAN
CONSTELLATION ENERGY NUCLEAR GROUP
R.E. GINNA NUCLEAR POWER PLANT
DOCKET NOS. 50-244
LICENSE NOS DPR-18
- 1. In section 11.3 of the PSP, the licensee describes protected area (PA) perimeter barriers. Describe the assessment capabilities in the areas where the PA perimeter barrier is comprised of buildings, walls, or roofs in accordance with 10 CFR 73.55(e)(8)(iv) and10 CFR 73.55(i)(3)(ii). Additionally, the licensee should make appropriate changes during the next revision of the sites PSP to ensure the language clearly describes the assessment capabilities in areas where buildings, walls, or roofs comprise a portion of the PA barrier in accordance with 10 CFR 73.55(e)(8)(iv).
I will appreciate if your staff can provide a response to the above RAI.
Thank you for your support.
Mohan C Thadani Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
(301) 415-1476 Mohan.Thadani@nrc.gov