ML092600586: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 September 18, 2009 LICENSEE:
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 18, 2009 LICENSEE:       Entergy Operations, Inc. (ENO)
Entergy Operations, Inc. (ENO)
FACILITIES:     Palisades Nuclear Plant (PNP)
FACILITIES:
Palisades Nuclear Plant (PNP)  


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 19, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there are certain tasks which are taking longer than originally anticipated. They will review the resource allocation and may decide to put additional resources on these tasks. However, the final completion date for the project appeared to be on track and at present there are no significant barriers and no scope additions. Enclosure 2 provides the list of all attendees.
OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 19, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
Background On December 9,2008 (Agencywide Documents Access and Management System (ADAMS) Accession No.
STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there are certain tasks which are taking longer than originally anticipated. They will review the resource allocation and may decide to put additional resources on these tasks. However, the final completion date for the project appeared to be on track and at present there are no significant barriers and no scope additions. Enclosure 2 provides the list of all attendees.
ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct monthly teleconference with the NRC staff to discuss progress on the Palisades Nuclear Plant NFPA 805 transition activities. Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255  
 
===Background===
On December 9,2008 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct monthly teleconference with the NRC staff to discuss progress on the Palisades Nuclear Plant NFPA 805 transition activities.
                                                ~#-
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255


==Enclosures:==
==Enclosures:==
: 1. Table -Palisades NFPA 805 Project Milestones
: 1. Table - Palisades NFPA 805 Project Milestones
: 2. Table -List of Attendees cc w/encls: Distribution via ListServ 6/19/2009 Palisades NFPA 805 Project Milestones NEJTask No. Tille Milestone Date' Status' Slart Date' Task 1: Transition of Nuclear SafetyPerforrrenceCriteria (NEI 04-02 Table B-2) 08125100 See Comnents Task2 Furdarrental Fire ProtectionProgram  
: 2. Table - List of Attendees cc w/encls: Distribution via ListServ
&Design Elerrents(NEI 04-02 Table B-1) 09121109 See Conments Task3: Radoacti'" ReleaseTransition (NEI 04-02TableG-1) 09118100 See Conments Task4: Nuclear Safety AnalYSIs Transition (NEI 04-02Table B-3) 12128100 See Conments ST 41:1 Off-Site P""", Cable SelectionandAnalysis 09128100 See Corrments ST 4.12 Other PDNer Cable SeleclionandAnalysis Corrpete ST 413 SubseouentCablellnstrurrenlldentlficatlon
 
&AnalYSis 09114100 On Track TaskS: Non-PDNer Operational ModesTransition NEI 04-02Table F-1) 10100I0O See Corrrrents Task6: Inlernal E-.ents PRA 02119110 On Track ST621 Prepare LERF Model 08131/00 See Corrrrents ST 6.2.2 UpdateFioocing AnalYSiS 08I28lOO See Conments ST63 Thermal Hidraulic AnalYSIS fc.-MSO/HRA 11/16109 On Track ST 6.4 Internal E-.ents PRA Peer 10l3OI00 Not Started 1012*100 Task7 FirePRA 01128110 See Corrrrents ST 7.6.4 R31nternal E\6nts Model Corrpete ST 7.7 QuantificationRiskScreel1lng 10l29I09 See Corrments ST 7.8 Scaping fc.-Fire Modeling Corrpete ST 79110 Circut Failure Mode UlaihoodAi1ays,s 09I30I09 OnTrack ST 712 Post Fire HRA 10121/00 See Conments ST 7.13 Sasrnc Fire Intera::tion Assessrrent Corrplete ST 7.14 Fire Risk Quantification 11/17/09 See Conments 10114100 ST 715 Uncertainly and 11/11/09 See Corrments ST 717 Fire PRA Peer 01122110 Not Started 01/18110 Task8: NFPA 805Change Evaluations 02101/10 On Track ST 81 Change Evaluations 12116100 See Conments ST 8.2 Non-COIl1iiance Risk Evaluations 01/01/10 See Corrments 11/18109 Task 9: PalisadesMappng of PostTransition Procedures
6/19/2009 Palisades NFPA 805 Project Milestones NEJTask                                                                                                                               Milestone                                    Slart Tille                                                                                Status' No.                                                                                                                                 Date'                                   Date' See Task 1:             Transition of Nuclear SafetyPerforrrenceCriteria (NEI 04-02 Table B-2)                                               08125100 Comnents Furdarrental Fire ProtectionProgram & Design Elerrents(NEI 04-02                                                                                 See Task2                                                                                                                                      09121109 Table B-1)                                                                                                                                 Conments See Task3:             Radoacti'" ReleaseTransition (NEI 04-02Table G-1)                                                                     09118100 Conments See Task4:               Nuclear SafetyAnalYSIs Transition (NEI 04-02Table B-3)                                                               12128100 Conments See ST 41:1         Off-Site P""", Cable SelectionandAnalysis                                                                             09128100 Corrments ST 4.12         Other PDNer Cable SeleclionandAnalysis                                                                                                     Corrpete ST 413 SubseouentCablellnstrurrenlldentlficatlon &AnalYSis                                                                             09114100             On Track Non-PDNer Operational ModesTransition                                                                                                           See TaskS:                                                                                                                                    10100I0O NEI 04-02Table F-1)                                                                                                                     Corrrrents Task6:               Inlernal E-.ents PRA                                                                                                 02119110             On Track See ST621           Prepare LERF Model                                                                                                   08131/00 Corrrrents See ST 6.2.2 UpdateFioocing AnalYSiS                                                                                                       08I28lOO Conments ST63             Thermal Hidraulic AnalYSIS fc.- MSO/HRA                                                                               11/16109             On Track ST 6.4           InternalE-.ents PRA Peer Re~ew                                                                                        10l3OI00           Not Started 1012100 See Task7               FirePRA                                                                                                               01128110 Corrrrents ST 7.6.4 R31nternal E\6nts Model                                                                                                                           Corrpete See ST 7.7           QuantificationRiskScreel1lng                                                                                         10l29I09 Corrments ST 7.8           Scaping fc.- Fire Modeling                                                                                                                 Corrpete ST 79110 Circut Failure Mode UlaihoodAi1ays,s                                                                                         09I30I09             OnTrack See ST 712           Post Fire HRA                                                                                                         10121/00 Conments ST 7.13         Sasrnc Fire Intera::tion Assessrrent                                                                                                       Corrplete See ST 7.14         Fire Risk Quantification                                                                                             11/17/09                                 10114100 Conments See ST 715           Uncertainly and Sensiti~lyAnalysis                                                                                    11/11/09 Corrments ST 717           Fire PRA Peer R~ew                                                                                                    01122110           Not Started 01/18110 Task8:               NFPA 805Change Evaluations                                                                                           02101/10             On Track See ST 81           Change Evaluations                                                                                                   12116100 Conments See           11/18109 ST 8.2           Non-COIl1iiance Risk Evaluations                                                                                     01/01/10 Corrments Task 9:             PalisadesMappng of PostTransition Procedures& Docurent                                       R~s'ons                  01/08110           Not Started 11I02I09 See Task 10:             Transition R"IX"t                                                                                                     03'18110                                 11100I0O Corrrrents Task 11:             UcenseAmendrrentRequest (LAR)                                                                                       03119110 T TheofQ,nelm.rntme dall!ls     p", schedl/Ill PlPB05 51*3 WFC Schedulll 12NOWBend are tub/OcttJ change           The clIf'enlsehed",1a (805 S6_8Fl OJAUG09) deEs were valid311!ldtJ be 2 "On f,u:"" me8nl tlellhelllsk currotnll)ercenlage COlrlJllltllld IS;t Ill! upecllldcomplelio'l perc.nlandl'le ,,~pecll!ldcolTlj:l"liondall!llo'!he Iask is projecll!ldlo b...... t 3 Slartdall!ls provided lI,e .sti~11U  and maV   ~erv con~ngenlupon  predecessor complebon and BVBllat:>le resllurceslttlat,,",, Even     ~tlis slandlllt  ~ adJu311td,tleCllmpleliondalit is sliMupeclltd tl b. malunle'.lIldicalltd otlen"'isa
&Docurent 01/08110 Not Started 11I02I09 Task 10: Transition R"IX"t 03'18110 See Corrrrents 11100I0O Task 11: UcenseAmendrrentRequest (LAR) 03119110 T TheofQ,nelm.rntme dall!ls p", schedl/Ill PlPB05 51*3 WFC Schedulll 12NOWBend are tub/OcttJ change The clIf'enlsehed",1a (805 S6_8FlOJAUG09) deEs were valid311!ldtJ be 2 "On f,u:"" me8nl tlellhelllsk currotnll)ercenlage COlrlJllltllld IS;t Ill!
~
upecllldcomplelio'l perc.nlandl'le dall!llo'!he Iask is projecll!ldlo b
.Iui.J:     8*2 TaI:lle r~lfNi talongImger Ih<r1 Orlglnalty a'1tClPated
......t 3 Slartdall!ls provided lI,e and maV predecessor complebon and BVBllat:>le resllurceslttlat,,",, Even slandlllt  adJu311td,tleCllmpleliondalit is sliMupeclltd tl b. malunle'.lIldicalltd otlen"'isa .Iui.J: 8*2 TaI:lle talongImger Ih<r1 Orlglnalty a'1tClPated 8-1 TaI:lle review Uiliking longer tlla'1expected I.iWI..,,;1 Peeseoes InrormatlUl laking Ior;ger t!"l<rt expectedto Obtiln I..iaJ.' B-3 T aI:lle takTlgImger th<rt orignalty iI"ltctpal.ed  
~          8-1 TaI:lle reviewUiliking longer tlla'1expected I.iWI..,,;1 Peeseoes InrormatlUl laking Ior;ger t!"l<rt expectedto Obtiln I..iaJ.' B-3 T aI:lle r~~      takTlgImger th<rt orignalty iI"ltctpal.ed I.~.Is..L1J: Pili:sades lI"lformaticn takingIor;ger 111<1'1 expectedto obt~
..L1J: Pili:sades lI"lformaticn taking Ior;ger 111<1'1 expectedto NPO cal:lle IcEntrl'icatm  
~ NPO             cal:lle IcEntrl'icatm & ~alyslS lakng longer then expected
&
~-              LERF Modelliflal eece-ce       oott task remall'llng l.iU.L Addlialal components ldentrl'ied feq.Jlre eooeoceoe seectco <nl enayslS IW.l.Z       Ad:Jtlonal COOlporlentS ldentrl'ied reqJre added caI:lle Selection end eoevse I.u.Il..l..12' Ad:Jtionai ccmpc.-.ents identrl'ied reqjre ~ cal:lle         seecneo :;nd a'SySIS
lakng longer then expected LERF Modelliflal eece-ce oott task remall'llng l.iU.L Addlialal components ldentrl'ied feq.Jlre eooeoceoe seectco <nl enayslS IW.l.Z Ad:Jtlonal COOlporlentS ldentrl'ied reqJre added caI:lle Selection end eoevse I.u.Il..l..12' Ad:Jtionai ccmpc.-.ents identrl'ied reqjre cal:lle seecneo :;nd a'SySIS Preoecessc-task PJShed the stet and completlUl dates L1:lJl..L.1S..
~.              Preoecessc- task PJShed the stet andcompletlUl dates L1:lJl..L.1S.. Predecessor task p.JShed the comple'!fal date
Predecessor task p.JShed the comple'!fal date Preoecesscr pUShed the completimdate Prececesso-pushedthe stat completion dates LIU...1Q., Preoecessce pushedthe stat date Completion remaos the same Enclosure 1
~              PreoecesscrpUShed the completimdate
TELEPHONE CONFERENCE ON NFPA 805 TRANSITION PROGRESS U.S. NUCLEAR REGULATORY AND ENTERGY OPERATIONS, LIST OF AUGUST 19, PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC) Mahesh Chawla Proiect Manaaer HEADQUARTERS Harrv Barrett Senior Fire Protection Enaineer Thomas Taylor Resident Inspector REGION ENTERGY Bob VanWagner Program Engineering Manager PALISADES NUCLEAR PLANT Tom Swiecicki Engineering Programs Senior Lead Engineer Brian Brogan Probabilistic Safety Assessment (PSA) Engineer Frank Yanik Probabilistic Safety Assessment Engineer Roger Stobert Contract Project Manager NFPA 805 Jim Kuemin Licensing Engineer Enclosure 2
~:            Prececesso- pushedthe stat ~d completion dates LIU...1Q.,   Preoecessce pushedthe stat date Completion remaos the same Enclosure 1
 
TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.
LIST OF PARTICIPANTS AUGUST 19, 2009 PARTICIPANTS   TITLE/POSITION                             AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)
Mahesh Chawla   Proiect Manaaer                           HEADQUARTERS Harrv Barrett Senior Fire Protection Enaineer Thomas Taylor   Resident Inspector                       REGION ENTERGY Bob VanWagner   Program Engineering Manager               PALISADES NUCLEAR PLANT Tom Swiecicki   Engineering Programs Senior Lead Engineer Brian Brogan   Probabilistic Safety Assessment (PSA)
Engineer Frank Yanik     Probabilistic Safety Assessment Engineer Roger Stobert Contract Project Manager NFPA 805 Jim Kuemin     Licensing Engineer Enclosure 2
 
LICENSEE:          Entergy Operations, Inc. (ENO)
FACILITIES:        Palisades Nuclear Plant (PNP)


Entergy Operations, Inc. (ENO) Palisades Nuclear Plant (PNP)
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 19, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see ) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there are certain tasks which are taking longer than originally anticipated. They will review the resource allocation and may decide to put additional resources on these tasks. However, the final completion date for the project appeared to be on track and at present there are no significant barriers and no scope additions. Enclosure 2 provides the list of all attendees.
OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 19, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
Background On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct monthly teleconference with the NRC staff to discuss progress on the Palisades Nuclear Plant NFPA 805 transition activities.
STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there are certain tasks which are taking longer than originally anticipated. They will review the resource allocation and may decide to put additional resources on these tasks. However, the final completion date for the project appeared to be on track and at present there are no significant barriers and no scope additions. Enclosure 2 provides the list of all attendees.
IRA! Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255  
 
===Background===
On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct monthly teleconference with the NRC staff to discuss progress on the Palisades Nuclear Plant NFPA 805 transition activities.
IRA!
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255


==Enclosures:==
==Enclosures:==
: 1. Table -Palisades NFPA 805 Project Milestones
: 1. Table - Palisades NFPA 805 Project Milestones
: 2. Table -List of Attendees cc w/encls: Distribution via ListServ Distribution:
: 2. Table - List of Attendees cc w/encls: Distribution via ListServ Distribution:
PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource JEliegood, Rill Paul Lain, NRR HBarrett RidsNrrLABTully ADAMS Accession No'.. ML092600586 OFFICE LPL3-1/PM LPL3-1/LA DRNAFPB/BC LPL3-1/BC(A)
PUBLIC           LPL3-1 r/f         RidsRgn3MailCenter Resource     AKlein, NRR   JGeissner, Rill RidsNrrDorLpl3-1 Resource           RidsNrrPMANO Resource           MVaaler, NRR   TTaylor, Rill RidsNrrPMPalisades Resource         JEliegood, Rill                 Paul Lain, NRR HBarrett RidsNrrLABTully ADAMS Accession No'.. ML092600586 OFFICE       LPL3-1/PM     LPL3-1/LA         DRNAFPB/BC         LPL3-1/BC(A)
NAME MChawla BTuily (THarris for)
BTuily NAME         MChawla                           AKlein              TWengert (THarris for)
AKlein TWengert DATE 09/18/09 09/18/09 09/17/09 09/18/09 OFFICIAL RECORD COpy}}
DATE         09/18/09       09/18/09           09/17/09           09/18/09 OFFICIAL RECORD COpy}}

Revision as of 02:11, 14 November 2019

08/19/2009 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc Regarding Progress on National Fire Protection Association (NFPA) Standard 805 Transition Activities
ML092600586
Person / Time
Site: Palisades Entergy icon.png
Issue date: 09/18/2009
From: Mahesh Chawla
Plant Licensing Branch III
To:
Office of Nuclear Reactor Regulation
Chawla M, NRR/DORL, 415-8371
References
Download: ML092600586 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 18, 2009 LICENSEE: Entergy Operations, Inc. (ENO)

FACILITIES: Palisades Nuclear Plant (PNP)

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 19, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there are certain tasks which are taking longer than originally anticipated. They will review the resource allocation and may decide to put additional resources on these tasks. However, the final completion date for the project appeared to be on track and at present there are no significant barriers and no scope additions. Enclosure 2 provides the list of all attendees.

Background

On December 9,2008 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct monthly teleconference with the NRC staff to discuss progress on the Palisades Nuclear Plant NFPA 805 transition activities.

~#-

Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1. Table - Palisades NFPA 805 Project Milestones
2. Table - List of Attendees cc w/encls: Distribution via ListServ

6/19/2009 Palisades NFPA 805 Project Milestones NEJTask Milestone Slart Tille Status' No. Date' Date' See Task 1: Transition of Nuclear SafetyPerforrrenceCriteria (NEI 04-02 Table B-2) 08125100 Comnents Furdarrental Fire ProtectionProgram & Design Elerrents(NEI 04-02 See Task2 09121109 Table B-1) Conments See Task3: Radoacti'" ReleaseTransition (NEI 04-02Table G-1) 09118100 Conments See Task4: Nuclear SafetyAnalYSIs Transition (NEI 04-02Table B-3) 12128100 Conments See ST 41:1 Off-Site P""", Cable SelectionandAnalysis 09128100 Corrments ST 4.12 Other PDNer Cable SeleclionandAnalysis Corrpete ST 413 SubseouentCablellnstrurrenlldentlficatlon &AnalYSis 09114100 On Track Non-PDNer Operational ModesTransition See TaskS: 10100I0O NEI 04-02Table F-1) Corrrrents Task6: Inlernal E-.ents PRA 02119110 On Track See ST621 Prepare LERF Model 08131/00 Corrrrents See ST 6.2.2 UpdateFioocing AnalYSiS 08I28lOO Conments ST63 Thermal Hidraulic AnalYSIS fc.- MSO/HRA 11/16109 On Track ST 6.4 InternalE-.ents PRA Peer Re~ew 10l3OI00 Not Started 1012100 See Task7 FirePRA 01128110 Corrrrents ST 7.6.4 R31nternal E\6nts Model Corrpete See ST 7.7 QuantificationRiskScreel1lng 10l29I09 Corrments ST 7.8 Scaping fc.- Fire Modeling Corrpete ST 79110 Circut Failure Mode UlaihoodAi1ays,s 09I30I09 OnTrack See ST 712 Post Fire HRA 10121/00 Conments ST 7.13 Sasrnc Fire Intera::tion Assessrrent Corrplete See ST 7.14 Fire Risk Quantification 11/17/09 10114100 Conments See ST 715 Uncertainly and Sensiti~lyAnalysis 11/11/09 Corrments ST 717 Fire PRA Peer R~ew 01122110 Not Started 01/18110 Task8: NFPA 805Change Evaluations 02101/10 On Track See ST 81 Change Evaluations 12116100 Conments See 11/18109 ST 8.2 Non-COIl1iiance Risk Evaluations 01/01/10 Corrments Task 9: PalisadesMappng of PostTransition Procedures& Docurent R~s'ons 01/08110 Not Started 11I02I09 See Task 10: Transition R"IX"t 03'18110 11100I0O Corrrrents Task 11: UcenseAmendrrentRequest (LAR) 03119110 T TheofQ,nelm.rntme dall!ls p", schedl/Ill PlPB05 51*3 WFC Schedulll 12NOWBend are tub/OcttJ change The clIf'enlsehed",1a (805 S6_8Fl OJAUG09) deEs were valid311!ldtJ be 2 "On f,u:"" me8nl tlellhelllsk currotnll)ercenlage COlrlJllltllld IS;t Ill! upecllldcomplelio'l perc.nlandl'le ,,~pecll!ldcolTlj:l"liondall!llo'!he Iask is projecll!ldlo b...... t 3 Slartdall!ls provided lI,e .sti~11U and maV ~erv con~ngenlupon predecessor complebon and BVBllat:>le resllurceslttlat,,",, Even ~tlis slandlllt ~ adJu311td,tleCllmpleliondalit is sliMupeclltd tl b. malunle'.lIldicalltd otlen"'isa

~

.Iui.J: 8*2 TaI:lle r~lfNi talongImger Ih<r1 Orlglnalty a'1tClPated

~ 8-1 TaI:lle reviewUiliking longer tlla'1expected I.iWI..,,;1 Peeseoes InrormatlUl laking Ior;ger t!"l<rt expectedto Obtiln I..iaJ.' B-3 T aI:lle r~~ takTlgImger th<rt orignalty iI"ltctpal.ed I.~.Is..L1J: Pili:sades lI"lformaticn takingIor;ger 111<1'1 expectedto obt~

~ NPO cal:lle IcEntrl'icatm & ~alyslS lakng longer then expected

~- LERF Modelliflal eece-ce oott task remall'llng l.iU.L Addlialal components ldentrl'ied feq.Jlre eooeoceoe seectco <nl enayslS IW.l.Z Ad:Jtlonal COOlporlentS ldentrl'ied reqJre added caI:lle Selection end eoevse I.u.Il..l..12' Ad:Jtionai ccmpc.-.ents identrl'ied reqjre ~ cal:lle seecneo  :;nd a'SySIS

~. Preoecessc- task PJShed the stet andcompletlUl dates L1:lJl..L.1S.. Predecessor task p.JShed the comple'!fal date

~ PreoecesscrpUShed the completimdate

~: Prececesso- pushedthe stat ~d completion dates LIU...1Q., Preoecessce pushedthe stat date Completion remaos the same Enclosure 1

TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.

LIST OF PARTICIPANTS AUGUST 19, 2009 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)

Mahesh Chawla Proiect Manaaer HEADQUARTERS Harrv Barrett Senior Fire Protection Enaineer Thomas Taylor Resident Inspector REGION ENTERGY Bob VanWagner Program Engineering Manager PALISADES NUCLEAR PLANT Tom Swiecicki Engineering Programs Senior Lead Engineer Brian Brogan Probabilistic Safety Assessment (PSA)

Engineer Frank Yanik Probabilistic Safety Assessment Engineer Roger Stobert Contract Project Manager NFPA 805 Jim Kuemin Licensing Engineer Enclosure 2

LICENSEE: Entergy Operations, Inc. (ENO)

FACILITIES: Palisades Nuclear Plant (PNP)

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 19, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there are certain tasks which are taking longer than originally anticipated. They will review the resource allocation and may decide to put additional resources on these tasks. However, the final completion date for the project appeared to be on track and at present there are no significant barriers and no scope additions. Enclosure 2 provides the list of all attendees.

Background

On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct monthly teleconference with the NRC staff to discuss progress on the Palisades Nuclear Plant NFPA 805 transition activities.

IRA!

Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1. Table - Palisades NFPA 805 Project Milestones
2. Table - List of Attendees cc w/encls: Distribution via ListServ Distribution:

PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource JEliegood, Rill Paul Lain, NRR HBarrett RidsNrrLABTully ADAMS Accession No'.. ML092600586 OFFICE LPL3-1/PM LPL3-1/LA DRNAFPB/BC LPL3-1/BC(A)

BTuily NAME MChawla AKlein TWengert (THarris for)

DATE 09/18/09 09/18/09 09/17/09 09/18/09 OFFICIAL RECORD COpy