ML092600586

From kanterella
Jump to navigation Jump to search
Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc Regarding Progress on National Fire Protection Association (NFPA) Standard 805 Transition Activities
ML092600586
Person / Time
Site: Palisades Entergy icon.png
Issue date: 09/18/2009
From: Mahesh Chawla
Plant Licensing Branch III
To:
Office of Nuclear Reactor Regulation
Chawla M, NRR/DORL, 415-8371
References
Download: ML092600586 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 18, 2009 LICENSEE: Entergy Operations, Inc. (ENO)

FACILITIES: Palisades Nuclear Plant (PNP)

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 19, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there are certain tasks which are taking longer than originally anticipated. They will review the resource allocation and may decide to put additional resources on these tasks. However, the final completion date for the project appeared to be on track and at present there are no significant barriers and no scope additions. Enclosure 2 provides the list of all attendees.

Background

On December 9,2008 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct monthly teleconference with the NRC staff to discuss progress on the Palisades Nuclear Plant NFPA 805 transition activities.

~#-

Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1. Table - Palisades NFPA 805 Project Milestones
2. Table - List of Attendees cc w/encls: Distribution via ListServ

6/19/2009 Palisades NFPA 805 Project Milestones NEJTask Milestone Slart Tille Status' No. Date' Date' See Task 1: Transition of Nuclear SafetyPerforrrenceCriteria (NEI 04-02 Table B-2) 08125100 Comnents Furdarrental Fire ProtectionProgram & Design Elerrents(NEI 04-02 See Task2 09121109 Table B-1) Conments See Task3: Radoacti'" ReleaseTransition (NEI 04-02Table G-1) 09118100 Conments See Task4: Nuclear SafetyAnalYSIs Transition (NEI 04-02Table B-3) 12128100 Conments See ST 41:1 Off-Site P""", Cable SelectionandAnalysis 09128100 Corrments ST 4.12 Other PDNer Cable SeleclionandAnalysis Corrpete ST 413 SubseouentCablellnstrurrenlldentlficatlon &AnalYSis 09114100 On Track Non-PDNer Operational ModesTransition See TaskS: 10100I0O NEI 04-02Table F-1) Corrrrents Task6: Inlernal E-.ents PRA 02119110 On Track See ST621 Prepare LERF Model 08131/00 Corrrrents See ST 6.2.2 UpdateFioocing AnalYSiS 08I28lOO Conments ST63 Thermal Hidraulic AnalYSIS fc.- MSO/HRA 11/16109 On Track ST 6.4 InternalE-.ents PRA Peer Re~ew 10l3OI00 Not Started 1012100 See Task7 FirePRA 01128110 Corrrrents ST 7.6.4 R31nternal E\6nts Model Corrpete See ST 7.7 QuantificationRiskScreel1lng 10l29I09 Corrments ST 7.8 Scaping fc.- Fire Modeling Corrpete ST 79110 Circut Failure Mode UlaihoodAi1ays,s 09I30I09 OnTrack See ST 712 Post Fire HRA 10121/00 Conments ST 7.13 Sasrnc Fire Intera::tion Assessrrent Corrplete See ST 7.14 Fire Risk Quantification 11/17/09 10114100 Conments See ST 715 Uncertainly and Sensiti~lyAnalysis 11/11/09 Corrments ST 717 Fire PRA Peer R~ew 01122110 Not Started 01/18110 Task8: NFPA 805Change Evaluations 02101/10 On Track See ST 81 Change Evaluations 12116100 Conments See 11/18109 ST 8.2 Non-COIl1iiance Risk Evaluations 01/01/10 Corrments Task 9: PalisadesMappng of PostTransition Procedures& Docurent R~s'ons 01/08110 Not Started 11I02I09 See Task 10: Transition R"IX"t 03'18110 11100I0O Corrrrents Task 11: UcenseAmendrrentRequest (LAR) 03119110 T TheofQ,nelm.rntme dall!ls p", schedl/Ill PlPB05 51*3 WFC Schedulll 12NOWBend are tub/OcttJ change The clIf'enlsehed",1a (805 S6_8Fl OJAUG09) deEs were valid311!ldtJ be 2 "On f,u:"" me8nl tlellhelllsk currotnll)ercenlage COlrlJllltllld IS;t Ill! upecllldcomplelio'l perc.nlandl'le ,,~pecll!ldcolTlj:l"liondall!llo'!he Iask is projecll!ldlo b...... t 3 Slartdall!ls provided lI,e .sti~11U and maV ~erv con~ngenlupon predecessor complebon and BVBllat:>le resllurceslttlat,,",, Even ~tlis slandlllt ~ adJu311td,tleCllmpleliondalit is sliMupeclltd tl b. malunle'.lIldicalltd otlen"'isa

~

.Iui.J: 8*2 TaI:lle r~lfNi talongImger Ih<r1 Orlglnalty a'1tClPated

~ 8-1 TaI:lle reviewUiliking longer tlla'1expected I.iWI..,,;1 Peeseoes InrormatlUl laking Ior;ger t!"l<rt expectedto Obtiln I..iaJ.' B-3 T aI:lle r~~ takTlgImger th<rt orignalty iI"ltctpal.ed I.~.Is..L1J: Pili:sades lI"lformaticn takingIor;ger 111<1'1 expectedto obt~

~ NPO cal:lle IcEntrl'icatm & ~alyslS lakng longer then expected

~- LERF Modelliflal eece-ce oott task remall'llng l.iU.L Addlialal components ldentrl'ied feq.Jlre eooeoceoe seectco <nl enayslS IW.l.Z Ad:Jtlonal COOlporlentS ldentrl'ied reqJre added caI:lle Selection end eoevse I.u.Il..l..12' Ad:Jtionai ccmpc.-.ents identrl'ied reqjre ~ cal:lle seecneo  :;nd a'SySIS

~. Preoecessc- task PJShed the stet andcompletlUl dates L1:lJl..L.1S.. Predecessor task p.JShed the comple'!fal date

~ PreoecesscrpUShed the completimdate

~: Prececesso- pushedthe stat ~d completion dates LIU...1Q., Preoecessce pushedthe stat date Completion remaos the same Enclosure 1

TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.

LIST OF PARTICIPANTS AUGUST 19, 2009 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)

Mahesh Chawla Proiect Manaaer HEADQUARTERS Harrv Barrett Senior Fire Protection Enaineer Thomas Taylor Resident Inspector REGION ENTERGY Bob VanWagner Program Engineering Manager PALISADES NUCLEAR PLANT Tom Swiecicki Engineering Programs Senior Lead Engineer Brian Brogan Probabilistic Safety Assessment (PSA)

Engineer Frank Yanik Probabilistic Safety Assessment Engineer Roger Stobert Contract Project Manager NFPA 805 Jim Kuemin Licensing Engineer Enclosure 2

LICENSEE: Entergy Operations, Inc. (ENO)

FACILITIES: Palisades Nuclear Plant (PNP)

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 19, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there are certain tasks which are taking longer than originally anticipated. They will review the resource allocation and may decide to put additional resources on these tasks. However, the final completion date for the project appeared to be on track and at present there are no significant barriers and no scope additions. Enclosure 2 provides the list of all attendees.

Background

On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct monthly teleconference with the NRC staff to discuss progress on the Palisades Nuclear Plant NFPA 805 transition activities.

IRA!

Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1. Table - Palisades NFPA 805 Project Milestones
2. Table - List of Attendees cc w/encls: Distribution via ListServ Distribution:

PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource JEliegood, Rill Paul Lain, NRR HBarrett RidsNrrLABTully ADAMS Accession No'.. ML092600586 OFFICE LPL3-1/PM LPL3-1/LA DRNAFPB/BC LPL3-1/BC(A)

BTuily NAME MChawla AKlein TWengert (THarris for)

DATE 09/18/09 09/18/09 09/17/09 09/18/09 OFFICIAL RECORD COpy