| issue date = 12/16/2013
| issue date = 12/16/2013
| title = W. Berg Ltr. Request for Additional Information for Decommissioning Fund Status Report for Lacrosse
| title = W. Berg Ltr. Request for Additional Information for Decommissioning Fund Status Report for Lacrosse
| author name = Hickman J B
| author name = Hickman J
| author affiliation = NRC/FSME/DWMEP/DURLD/RDB
| author affiliation = NRC/FSME/DWMEP/DURLD/RDB
| addressee name = Berg W L
| addressee name = Berg W
| addressee affiliation = Dairyland Power Cooperative
| addressee affiliation = Dairyland Power Cooperative
| docket = 05000409
| docket = 05000409
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:December 16, 2013  
{{#Wiki_filter:December 16, 2013 Mr. W. L. Berg President and Chief Executive Officer Dairyland Power Cooperative 3200 East Avenue South P.O. Box 817 La Crosse, WI 54602-0817
 
Mr. W. L. Berg President and Chief Executive Officer Dairyland Power Cooperative 3200 East Avenue South P.O. Box 817 La Crosse, WI 54602-0817  


==SUBJECT:==
==SUBJECT:==
DAIRYLAND POWER COOPERATIVE, LA CROSSE BOILING WATER REACTOR DECOMMISSIONING FUNDING STATUS REPORT - REQUEST FOR ADDITIONAL INFORMATION  
DAIRYLAND POWER COOPERATIVE, LA CROSSE BOILING WATER REACTOR DECOMMISSIONING FUNDING STATUS REPORT - REQUEST FOR ADDITIONAL INFORMATION


==Dear Mr. Berg:==
==Dear Mr. Berg:==


On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR) Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii). In order to complete our review of your Decommissioning Funding Status report we require additional information as detailed in the enclosure. Please provide a response to our request for additional information within 30 days from the date of this letter.  
On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR)
 
Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii). In order to complete our review of your Decommissioning Funding Status report we require additional information as detailed in the enclosure. Please provide a response to our request for additional information within 30 days from the date of this letter.
In accordance with 10 CFR 2.390 of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
Sincerely,
 
                                                  /RA/
      /RA/ John B. Hickman, Project Manager Reactor Decommissioning Branch Decommissioning and Uranium Recovery           Licensing Directorate Division of Waste Management           and Environmental Protection Office of Federal and State Materials and Environmental Management Programs  
John B. Hickman, Project Manager Reactor Decommissioning Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs Docket No.: 50-409
 
Docket No.: 50-409  


==Enclosure:==
==Enclosure:==
Request for Additional Information  
Request for Additional Information cc: La Crosse Boiling Water Reactor Service List


cc:  La Crosse Boiling Water Reactor Service List Mr. W. L. Berg President and Chief Executive Officer Dairyland Power Cooperative 3200 East Avenue South P.O. Box 817 La Crosse, WI 54602-0817  
Mr. W. L. Berg President and Chief Executive Officer Dairyland Power Cooperative 3200 East Avenue South P.O. Box 817 La Crosse, WI 54602-0817


==SUBJECT:==
==SUBJECT:==
DAIRYLAND POWER COOPERATIVE, LA CROSSE BOILING WATER REACTOR DECOMMISSIONING FUNDING STATUS REPORT - REQUEST FOR ADDITIONAL INFORMATION  
DAIRYLAND POWER COOPERATIVE, LA CROSSE BOILING WATER REACTOR DECOMMISSIONING FUNDING STATUS REPORT - REQUEST FOR ADDITIONAL INFORMATION


==Dear Mr. Berg:==
==Dear Mr. Berg:==


On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR) Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii). In order to complete our review of your Decommissioning Funding Status report we require additional information as detailed in the enclosure. Please provide a response to our request for additional information within 30 days from the date of this letter.  
On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR)
 
Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii). In order to complete our review of your Decommissioning Funding Status report we require additional information as detailed in the enclosure. Please provide a response to our request for additional information within 30 days from the date of this letter.
In accordance with 10 CFR 2.390 of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.       Sincerely,
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
 
Sincerely,
      /RA/ John B. Hickman, Project Manager Reactor Decommissioning Branch Decommissioning and Uranium Recovery           Licensing Directorate Division of Waste Management           and Environmental Protection Office of Federal and State Materials and Environmental Management Programs  
                                                  /RA/
 
John B. Hickman, Project Manager Reactor Decommissioning Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs Docket No.: 50-409
Docket No.: 50-409  


==Enclosure:==
==Enclosure:==
Request for Additional Information  
Request for Additional Information cc: La Crosse Boiling Water Reactor Service List DISTRIBUTION:
 
ROrlikowski RIII         AKock, NRR         KLois, NRR ML13347B319 OFC       DWMEP:PM         DWMEP:LA             DWMEP:BC         DWMEP:PM NAME JHickman               CHolston             BWatson           JHickman DATE       12 /16/ 2013     12 /16/ 2013         12 /16/ 2013     12 /16 / 2013 OFFICIAL RECORD COPY
cc: La Crosse Boiling Water Reactor Service List  
 
DISTRIBUTION
: ROrlikowski RIII AKock, NRR KLois, NRR ML13347B319 OFC DWMEP:PM DWMEP:LA DWMEP:BC DWMEP:PM NAME JHickman CHolston BWatson JHickman DATE 12 /16/ 2013 12 /16/ 2013 12 /16/ 2013 12 /16 / 2013 OFFICIAL RECORD COPY  
 
La Crosse Boiling Water Reactor Service List
 
Mr. William L. Berg President and Chief Executive Officer Dairyland Power Cooperative 3200 East Avenue South P.O. Box 817 La Crosse, WI  54602-0817
 
Mr. Thomas Zaremba Wheeler, Van Sickle and Anderson
 
Suite 801 25 West Main Street Madison, WI  53703-3398
 
Mr. George Kruck Chairman, Town of Genoa S5277 Mound Ridge Road Genoa, WI  54632
 
Mr. Jeffery Kitsembel Electric Division
 
Wisconsin Public Service Commission P.O. Box 7854 Madison, WI  53707-7854
 
Mr. Paul Schmidt, Manager Radiation Protection Section Bureau of Environmental and Occupational Health Division of Public Health Wisconsin Department of Health Services P.O. Box 2659 Madison, WI  53701-2659
 
Mr. Don G. Egge, Plant Manager La Crosse Boiling Water Reactor Dairyland Power Cooperative S4601 State Highway 35 Genoa, WI  54632-8846
 
Mr. Jeff McRill, Technical Support Engineer La Crosse Boiling Water Reactor Dairyland Power Cooperative S4601 State Highway 35 Genoa, WI  54632-8846
 
Regional Administrator Region III U.S. Nuclear Regulatory Commission
 
2443 Warrenville Road Lisle, IL  60532-4352
 
Enclosure REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION 2013 DECOMMISSIONING FUNDING STATUS REPORT FOR LA CROSSE BOILING WATER REACTOR
 
The request for additional information (RAI) is in response to the 2013 Decommissioning Funding Status (DFS) report for Lacrosse Boiling Water Reactor. On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR) Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii).


RAI #1: Decommissioning Costs On March 27, 2013, Dairyland Power Cooperative did not provide the difference between actual and estimated costs for decommissioning work performed during the previous year.  
La Crosse Boiling Water Reactor Service List Mr. William L. Berg                          Mr. Paul Schmidt, Manager President and Chief Executive Officer        Radiation Protection Section Dairyland Power Cooperative                  Bureau of Environmental and Occupational 3200 East Avenue South                        Health P.O. Box 817                                Division of Public Health La Crosse, WI 54602-0817                    Wisconsin Department of Health Services P.O. Box 2659 Mr. Thomas Zaremba                          Madison, WI 53701-2659 Wheeler, Van Sickle and Anderson Suite 801                                    Mr. Don G. Egge, Plant Manager 25 West Main Street                          La Crosse Boiling Water Reactor Madison, WI 53703-3398                      Dairyland Power Cooperative S4601 State Highway 35 Mr. George Kruck                            Genoa, WI 54632-8846 Chairman, Town of Genoa S5277 Mound Ridge Road                      Mr. Jeff McRill, Technical Support Engineer Genoa, WI 54632                              La Crosse Boiling Water Reactor Dairyland Power Cooperative Mr. Jeffery Kitsembel                        S4601 State Highway 35 Electric Division                            Genoa, WI 54632-8846 Wisconsin Public Service Commission P.O. Box 7854                                Regional Administrator Madison, WI 53707-7854                      Region III U.S. Nuclear Regulatory Commission 2443 Warrenville Road Lisle, IL 60532-4352


Per 10 CFR 50.82(a)(8)(v), The report must include the following information, current through the end of the previous calendar year: an estimate of the costs to complete decommissioning, reflecting any difference between actual and estimated costs for work performed during the year, and the decommissioning criteria upon which the estimate is based. Provide the difference between actual and estimated costs for decommissioning work performed during the previous year.}}
REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION 2013 DECOMMISSIONING FUNDING STATUS REPORT FOR LA CROSSE BOILING WATER REACTOR The request for additional information (RAI) is in response to the 2013 Decommissioning Funding Status (DFS) report for Lacrosse Boiling Water Reactor. On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR) Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii).
RAI #1: Decommissioning Costs On March 27, 2013, Dairyland Power Cooperative did not provide the difference between actual and estimated costs for decommissioning work performed during the previous year.
Per 10 CFR 50.82(a)(8)(v),
The report must include the following information, current through the end of the previous calendar year: an estimate of the costs to complete decommissioning, reflecting any difference between actual and estimated costs for work performed during the year, and the decommissioning criteria upon which the estimate is based.
Provide the difference between actual and estimated costs for decommissioning work performed during the previous year.
Enclosure}}

Latest revision as of 10:26, 4 November 2019

W. Berg Ltr. Request for Additional Information for Decommissioning Fund Status Report for Lacrosse
ML13347B319
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 12/16/2013
From: John Hickman
NRC/FSME/DWMEP/DURLD/RDB
To: Berg W
Dairyland Power Cooperative
Hickman J
References
Download: ML13347B319 (4)


Text

December 16, 2013 Mr. W. L. Berg President and Chief Executive Officer Dairyland Power Cooperative 3200 East Avenue South P.O. Box 817 La Crosse, WI 54602-0817

SUBJECT:

DAIRYLAND POWER COOPERATIVE, LA CROSSE BOILING WATER REACTOR DECOMMISSIONING FUNDING STATUS REPORT - REQUEST FOR ADDITIONAL INFORMATION

Dear Mr. Berg:

On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR)

Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii). In order to complete our review of your Decommissioning Funding Status report we require additional information as detailed in the enclosure. Please provide a response to our request for additional information within 30 days from the date of this letter.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

John B. Hickman, Project Manager Reactor Decommissioning Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs Docket No.: 50-409

Enclosure:

Request for Additional Information cc: La Crosse Boiling Water Reactor Service List

Mr. W. L. Berg President and Chief Executive Officer Dairyland Power Cooperative 3200 East Avenue South P.O. Box 817 La Crosse, WI 54602-0817

SUBJECT:

DAIRYLAND POWER COOPERATIVE, LA CROSSE BOILING WATER REACTOR DECOMMISSIONING FUNDING STATUS REPORT - REQUEST FOR ADDITIONAL INFORMATION

Dear Mr. Berg:

On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR)

Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii). In order to complete our review of your Decommissioning Funding Status report we require additional information as detailed in the enclosure. Please provide a response to our request for additional information within 30 days from the date of this letter.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

John B. Hickman, Project Manager Reactor Decommissioning Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs Docket No.: 50-409

Enclosure:

Request for Additional Information cc: La Crosse Boiling Water Reactor Service List DISTRIBUTION:

ROrlikowski RIII AKock, NRR KLois, NRR ML13347B319 OFC DWMEP:PM DWMEP:LA DWMEP:BC DWMEP:PM NAME JHickman CHolston BWatson JHickman DATE 12 /16/ 2013 12 /16/ 2013 12 /16/ 2013 12 /16 / 2013 OFFICIAL RECORD COPY

La Crosse Boiling Water Reactor Service List Mr. William L. Berg Mr. Paul Schmidt, Manager President and Chief Executive Officer Radiation Protection Section Dairyland Power Cooperative Bureau of Environmental and Occupational 3200 East Avenue South Health P.O. Box 817 Division of Public Health La Crosse, WI 54602-0817 Wisconsin Department of Health Services P.O. Box 2659 Mr. Thomas Zaremba Madison, WI 53701-2659 Wheeler, Van Sickle and Anderson Suite 801 Mr. Don G. Egge, Plant Manager 25 West Main Street La Crosse Boiling Water Reactor Madison, WI 53703-3398 Dairyland Power Cooperative S4601 State Highway 35 Mr. George Kruck Genoa, WI 54632-8846 Chairman, Town of Genoa S5277 Mound Ridge Road Mr. Jeff McRill, Technical Support Engineer Genoa, WI 54632 La Crosse Boiling Water Reactor Dairyland Power Cooperative Mr. Jeffery Kitsembel S4601 State Highway 35 Electric Division Genoa, WI 54632-8846 Wisconsin Public Service Commission P.O. Box 7854 Regional Administrator Madison, WI 53707-7854 Region III U.S. Nuclear Regulatory Commission 2443 Warrenville Road Lisle, IL 60532-4352

REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION 2013 DECOMMISSIONING FUNDING STATUS REPORT FOR LA CROSSE BOILING WATER REACTOR The request for additional information (RAI) is in response to the 2013 Decommissioning Funding Status (DFS) report for Lacrosse Boiling Water Reactor. On March 27, 2013, Dairyland Power Cooperative submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for the Lacrosse Boiling Water Reactor, as required under Title 10 of the Code of Federal Regulations (10 CFR) Section 50.75(f)(1) and 10 CFR 50.82 (a)(8)(v)-(vii).

RAI #1: Decommissioning Costs On March 27, 2013, Dairyland Power Cooperative did not provide the difference between actual and estimated costs for decommissioning work performed during the previous year.

Per 10 CFR 50.82(a)(8)(v),

The report must include the following information, current through the end of the previous calendar year: an estimate of the costs to complete decommissioning, reflecting any difference between actual and estimated costs for work performed during the year, and the decommissioning criteria upon which the estimate is based.

Provide the difference between actual and estimated costs for decommissioning work performed during the previous year.

Enclosure