Report on Status of Decommissioning Funding for Shutdown Reactor
ML22077A013
Person / Time
Site: La Crosse  File:Dairyland Power Cooperative icon.png
Issue date: 03/15/2022
From: Gerard van Noordennen
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2022-0006
Download: ML22077A013 (5)


Text

~

LACROSSESOLUTIONS 10 CFR 50.75(f)(l) 10 CFR 50.82(a)(8)

March 15, 2022 LC-2022-0006 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 La Crosse Boiling Water Reactor Facility Operating License No. DPR-45 NRC Docket Nos. 50-409 and 72-046

Subject:

Report on Status of Decommissioning Funding for Shutdown Reactor

References:

1) Barbara Nick, Dairyland Power Cooperative, Letter to U.S. Nuclear Regulatory Commission, "Application for Order Approving License Transfer and Conforming Administrative License Amendments," dated October 8, 2015
2) Marlayna Vaaler, U.S. Nuclear Regulatory Commission, Letter to Barbara Nick, Dairyland Power Cooperative, "Order Approving Transfer of License for the La Crosse Boiling Water Reactor from the Dairyland Power Cooperative to LaCrosseSolutions, LLC and Conforming Administrative License Amendment,"

dated May 20, 2016

3) Gerard van Noordennen, LaCrosseSolutions, Letter to U.S. Nuclear Regulatory Commission, "Notification of Amended Decommissioning Plan and Post-Shutdown Decommissioning Activities Report for La Crosse Boiling Water Reactor," dated June 27, 2016 In accordance with 10 CFR 50.75, "Reporting and recordkeeping for decommissioning planning," paragraph (f)(l), and 10 CFR 50.82, "Termination of license," paragraph (a)(8),

LaCrosseSolutions, LLC (LS) is submitting a report on the status of funding for decommissioning the La Crosse Boiling Water Reactor (LACBWR) facility, and managing the associated irradiated fuel. The annual radiological decommissioning and irradiated fuel management funding assurance report for LACBWR is provided in the attachment to this letter for the period ending December 31, 2021.

The minimum required decommissioning funding assurance amount is based on a site-specific decommissioning cost estimate detennined in accordance with 10 CPR 50.82(a). A change to the spent fuel management strategy was described in the application for license transfer (Reference 1), accepted by the NRC via Reference 2, and further described in the amended Post-Shutdown Decommissioning Activities Report (PSDAR) (Reference 3).

LaCrosseSolutions LC-2022-0006 Page 2 of 2 Each of those references addressed the project's planning and scheduling basis, the associated estimated costs, and the available funds for decommissioning, decontamination, dismantlement, and spent fuel management of the LACBWR facility. As described in those references, radiological decommissioning as represented by the LACBWR plan included decontamination and dismantlement of the radiologically involved systems, structures, and components.

Under the terms of the license transfer, LS became the lead NRC licensee responsible for all activities under the LACBWR License. LS will complete all activities necessary to terminate the License and release the LACBWR Site for unrestricted use as an industrial site, except for a small area surrounding the Independent Spent Fuel Storage Installation (ISFSI) containing the spent nuclear fuel, until its final disposition. Dairyland Power Cooperative (DPC) will remain the owner licensee and will retain title to the spent nuclear fuel. Upon issuance of a safety evaluation providing for termination of the License, except for the ISFSI site, and upon receipt of a future NRC license transfer approval, LS will transfer responsibility for the License back to DPC. Thereafter, DPC will maintain the ISFSI, and the ultimate disposition of the spent nuclear fuel will be provided for under the terms of DPC's Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Waste with the U.S. Department of Energy. These latter, ongoing costs are not included in the estimates herein.

All spent nuclear fuel elements from LACBWR have been transferred to dry cask storage in the ISFSI. LS entered into a "Company Services Agreement" with DPC, pursuant to which DPC provides operations, maintenance, access control, and security services to and for the ISFSI site.

DPC is responsible for the costs relating to the ISFSI.

The attachment provides the aggregated, minimum estimated cost (funds needed) for radiological decommissioning. This estimate has been developed from the site aggregate decommissioning schedule and provides the cost and funding allocation necessary to complete decommissioning consistent with the Commission accepted decommissioning strategy. There are no regulatory commitments contained within this letter.

If you have any questions about this letter, please contact me at (860) 462-9707.

Respectfully, Gerard van r Digitally signed by Gerard van Noordennen

.' DN: cn=Gerard van Noordennen, o=EnergySolutions,

/ ' ,,ou=Regulatory Affairs, Noordennen /)

  • i --email;;'gpvannoordennen@energysolutions,com, c=US Date: *:1022,03.15 14:36:27 -04'00' Gerard van Noordennen Senior Vice President Regulatory Affairs

Attachment:

Annual Radiological Decommissioning and Irradiated Fuel Management Funding Assurance Report for La Crosse Boiling Water Reactor, Aggregate Costs cc: Kimberly Conway, U.S. NRC Project Manager La Crosse Boiling Water Reactor Service List

La Crosse Boiling Water Reactor Service List cc:

Ken Robuck Regional Administrator President and CEO U.S. NRC, Region III EnergySolutions 2443 Warrenville Road 299 South Main Street, Suite 1700 Lisle, IL 60532-4352 Salt Lake City, UT 84111 Paul Schmidt, Manager John Sauger Radiation Protection Section President and Chief Nuclear Officer Bureau of Environmental and Occupational Health ReactorD & D Division of Public Health EnergySolutions Wisconsin Department of Health Services 121 W. Trade Street, Suite 2700 P.O. Box 2659 Charlotte, NC 28202 Madison, WI 53701-2659 Joseph Nowak Brent Ridge General Manager President and CEO LaCrosseSolutions Dairyland Power Cooperative S4601 State Highway 35 3200 East A venue South Genoa, WI 54632-8846 La Crosse, WI 54602-0817 Gerard van Noordennen Cheryl Olson, ISFSI Manager Sr. VP Regulatory Affairs La Crosse Boiling Water Reactor EnergySolutions Dairyland Power Cooperative 121 W. Trade Street, Suite 2700 S4601 State Highway 35 Charlotte, NC 28202 Genoa, WI 54632-8846 Russ Workman John Benkelman General Counsel La Crosse Boiling Water Reactor EnergySolutions Dairyland Power Cooperative 299 South Main Street, Suite 1700 S4601 State Highway 3 5 Salt Lake City, UT 84111 Genoa, WI 54632-8846 Jerome Pedretti, Clerk Andrew J. Parrish Town of Genoa Wheeler, Van Sickle and Anderson, S.C.

E860 Mundsack Road 44 East Mifflin Street, Suite 1000 Genoa, WI 54632 Jeffery Kitsembel Division of Energy Regulation Wisconsin Public Service Commission P.O. Box 7854 Madison, WI 53707-7854

LaCrosseSolutions LC-2022-0006 Attachment Page 1 of 2 Annual Radiological Decommissioning and Irradiated Fuel Management Funding Assurance Report for La Crosse Boiling Water Reactor, Aggregate Costs December 31, 2021 (2021 dollars, millions)

Trust Fund Amount at December 31, 2021 (A) $0.06 1 NRC Required Minimum Funding Assurance Amount at December 31, 2021 (B) $0.06 Difference in Trust Fund Amount versus Required Minimum Funding at December 31, 2021 - Surplus/(Shortfall) (C) = (A) - (B) $0.0 Projected End of Project Surplus at December 31, 2021 (D) $0.0 2 Estimated Costs to Complete Decommissioning at December 31, 2021 (E) $0.06 Projected Costs to Manage Irradiated Fuel at December 31, 2021 (F) ~

Amount Spent on Decommissioning4 (G):

Cumulative (June 2016 - December 31, 2020) $83.3 Calendar Year 2021 $0.0 Cumulative (June 2016 - December 31, 2021) $83.3 1 The LACBWR decommissioning work has been completed. The trust fund amount of $.06 million remains available to complete the NRC approval for transfer of the license back to DPC. Should those funds be depleted prior to license transfer, EnergySolutions' resources and the $15 million performance guarantee agreed to with DPC in the LACBWR Disposal Services Agreement, are available but are not relied upon here. In addition, a $17 million Performance Bond remains in place.

2 The surplus is based on the trust fund amount as of December 31, 2021, less the estimate of costs to complete decommissioning, plus annual earnings and less taxes through the end of the project.

3 A separate account in the trust holds the funds necessary for the ultimate decommissioning of the ISFSI site and final license termination. DPC currently funds and will continue to fund the operation and maintenance of the ISFSI through its annual operating revenue.

4 The amounts spent on decommissioning represents withdrawals made from the trust fund reported for radiological decommissioning.

LaCrosseSolutions LC-2022-0006 Attachment Page 2 of 2 a) The trust fund amount is the actual trust fund balance less outstanding disbursements for decommissioning costs incurred through the same date.

b) The required minimum funding assurance amount is based on the decommissioning scenario from the site-specific decommissioning cost estimate provided in Reference 3. The cost estimate reflects actual experience to date, as well as forecast refinements made through the date of this filing.

c) There are no additional funds to be collected.

d) A 2% annual real rate ofreturn is assumed in these calculations.

e) There are no contracts relied upon pursuant to IO CFR 50.75(e)(l)(v).

f) There are no material changes to the trust fund agreements or financial assurance contracts as described at the time of transfer of the licenses.

g) LS has entered into a "Company Services Agreement" with DPC, pursuant to which DPC will provide operations, maintenance, access control, and security services to and for the ISFSI site. DPC is responsible for the costs relating to the ISFSI and those costs are not included in this decommissioning estimate.

h) DPC has funds sufficient to meet its obligations to manage spent fuel safely as requisite to the current cost estimates for the project and pursuant to IO CFR 50.82(a)(8)(vii). A separate account in the trust holds the funds necessary for the ultimate decommissioning of the ISFSI site and final license termination. DPC's established spent fuel management funding plan is that it currently funds and will continue to fund the operation and maintenance of the ISFSI through its annual operating revenue.

i) DPC has not projected the cost of managing irradiated fuel until title to the fuel and possession of the fuel is transferred to the Secretary of Energy because this cost is indeterminate. ISFSI operating costs are estimated to be $2.5 million per year and are funded from the operations and maintenance budget.

j) Inquiries regarding the management of spent nuclear fuel beyond completion of the decommissioning project should be directed to DPC.