Submittal of Decommissioning Plan and Post-Shutdown Decommissioning Activities Report, and License Termination Plan Changes
ML22033A147
Person / Time
Site: La Crosse  File:Dairyland Power Cooperative icon.png
Issue date: 01/26/2022
From: Van Noordennen G
LaCrosseSolutions
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
Shared Package
ML22033A165 List:
References
LS-2022-0002
Download: ML22033A147 (4)


Text

~..~

LACROSSESOLUTIONS 10 CFR 50.4 10 CFR 50.71 10 CFR2.39 0 January 26, 2022 LS-2022-0002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 La Crosse Boiling Water Reactor Facility Operating License No. DPR-45 NRC Docket Nos. 50-409 and 72-046

Subject:

La Crosse Boiling Water Reactor Submittal of Decommissioning Plan and Post-Shutdown Decommissioning Activities Report, and License Termination Plan Changes

References:

I) LaCrosseSolutions, LLC letter, La Crosse Boiling Water Reactor (LACBWR)

Submittal of Decommissioning Plan and Post-Shutdown Decommissioning Activities Report Changes," dated June 12, 2020

2) NRC Regulatory Issue Summary 2015-17, "Review and Submission of Updates to Final Safety Analysis Reports, Emergency Preparedness Documents, and Fire Protection Documen ts"
3) Gerard van Noorde1men,. LaCrosseSolutions, Letter to U.S. Nuclear Regulatory Commission, "License Amendment Request for the License Termination Plan," dated June 27, 2016
4) Gerard van Noordennen, LaCrosseSolutions, Letter to U.S. Nuclear Regulatory Commission, <<License Termination Plan Revision l ," dated May 3 J, 2018
5) Marlayna Vaaler, U.S. Nuclear Regulatory Commission, Letter to John Saug~r, EnergySolutions, "La Crosse Boiling Water Reactor- Issuance of License Amendment No. 75 to Approve the LaCrosseSolutions, LLC License Termination Plan," dated May 21, 2019 The La Crosse Boiling Water Reactor (LACBWR) Decommissioning Plan and Post Shutdown Decommissioning Activities Repo1t (D-Pla_n/PSDAR) is recognized as the LACBWR Safety Analysis Report (SAR) equivalent as it contains the plant post-fuel accid~nt analysis. Therefore, the D-Plan/PSDAR is subject to revisions being submitted to the NRC on a 24-month interval in accordance with IO CFR 50.7l(e)(4 ).

In accordance with the requirements of l O CFR 50.4, "Written Communications," paragraph (b)(6), LaCrosseSolutions, LLC (LS) is submitting the January 2022 revision of the D-Plan/PSDAR for LACBWR. In accordance with 10 CFR 50.71(e)(4), the update is being submitted within 24 months of the previous revision which was submitted in Reference I.

frD-5.~

S4601 State Highway 35, Genoa, WI 54632

/Vf-/S52(p fl/ IR.

/0fv15S

LaCrosseSolutions, LLC LS-202 2-0002 Page2 of4 This D_;Plan/PSDAR update is being provide d electron ically on a total replace ment basis, satisfyi ng the submitt al requirem ents of IO CFR 50.4(b) (6), as discuss ed in Referen ce 2.

The changes to the D-Plan /PSDAR reflect comple tion of decomm issionin g activitie s includin g final status surveys . The January 2022 D-Plan /PSDAR revision includes changes made from June 2020 through January 2022.

Section 3 of the D-Plan /PSDAR contains the proprie tary financial infmma tion LS is providi ng to the NRC and seeks to have withhel d from public disclosu re in its entirety.

Therefo re, this submitt al contain s a LS Proprie tary Financial Informa tion Affidav it pursuan t to 10 CFR 2.390.

The Affidav it sets forth the basis for which the informa tion may be withhel d from public disclosu re by the Commi ssion and aqdress es with specific ity the conside rations listed in 10 CFR 2.390(b )(4).

The enc1osed CD contain s the public version of the January 2022 update of the D-Plan /PSDAR and the non-pub lic version of Section 3 of the D-Plan / PSDAR . It also contain s a matrix which lists changes incorpo rated in this revision of the D-Plan /PSDAR .

The LACBW R License Termin ation Plan (L TP) was submitt ed to the U.S.

Nuclea r Regulat ory Commi ssion (NRC) for review on June 27, 2016, as docume nted in Referen ce 3. Revisio n 1 of the L TP was submitt ed to the NRC on May 3 I, 2018, as docume nted in Referen ce 4. The NRC approve d Revisio n 1 of the L TP as docume nted in Referen ce 5.

The L TP is a supplem ent to the D-Plan/ PSDAR . The LTP has been revised to incorpo rate changes resultin g from decomm issionin g activities. In accorda nce with IO CFR 50.4 and 10 CFR 50.71, LS hereby submits Revisio ns 2 and 3 of the LTP. Revisio n 3 replace s Revisio n 2 in its entirety.

Chapter 7 of the L TP contain s financial informa tion. LS conside rs this proprie taiy financial informa tion to be confide ntial and requests the NRC withhold it from public disclosu re under l O CFR 2.390. Therefo re, the LS Proprie tary Financi al Informa tion Affidav it pursuan t to 10 CFR 2.390 in this submitt al is also applicable to the L TP.

The enclose d CD contain s the public versions of all chapter s of Revisio ns 2 and 3 of the LTP and proprie truy version of Chapte r 7 of Revisio n 3 (pdf copies). Microso ft Word' version s of all chapter s in Revisio n 3 of the LTP, with the "track change " option enabled

, are provide d to assist in identify ing the changes . In addition, the enclosu re contain s a matrix which lists changes incorporated into Revisio ns 2 and 3 of the LTP.

As Senior Vice Preside nt of Regulat ory Affairs, [ certify that the informa tion provide d in this submitt al accurat ely present s changes made to the D-Plan /PSDAR and the L TP since they were previou sly submitt ed.

There are no regulato ry commit ments made in this submitt al. If you should have any questio ns regardi ng this submitt al, please contact me at (860) 462-970 7.

LaCrosseSolutions, LLC LS-2022- 0002 Page 3 of 4 Respectfµlly, G~~~

Gerard van Noordennen Senior Vice President Regulatory Affairs

Enclosure:

CD containing the following files

1. LACBWR D-Plan/PSDAR, January 2022, Public
2. Section 3, LACBWR D-Plan/PSDAR, January 2022, Non-Public
3. D-Plan/PS DAR Change Matrix
4. License Termination Plan, Revisions 2 and 3, Public
5. Chapter 7, LACBWR LTP, Revision 3, Non-Public
6. LTP Cbgmge Matrix cc: Kimberly Conway, U.S. NRC Senior Project Manager (letter and enclosure)

Regional Administrator, U.S. NRC, Region III (letter and enclosure)

La Crosse Boiling Water Reactor S-ervice List (letter only)

LaCrosseSolutions, LLC LS.:2022-0002 Page 4 of 4 LaCrosseSolutions, LLC PROPRIETARY FINANCIAL INFORMATI ON AFFIDAVIT Affidavit of Gerard van Noordennen, Senior Vice President Regulato1y Affairs, LaCrosseSolutions, LLC.

The proprietary versions ofSection 3 of the D-Plan!PSDAR and LTP Chapter 7, containedin the Enclosure to this submittal, consist of proprietary financial information that LaCrosseSolutions, LLC considers confidential. Release of this information would cause irreparable harm to the competitive position of L~CrosseSolutions, LLC. The basis for this declaration is:

i. This information is owned and maintained as proprietary by LaCrosseSolutions, LLC, ii. This information is routii1ely held in confidence by LaCrosseSolutions, LLC and not disclosed to the public, iii. This information is being requested to be held in confidence by the NRC by this petition, iv. This information is not available in public sources,
v. This inf01mation would cause substantial harm to LaCrosseSolutions, LLC ifit were released publicly, and vi. The information to be withheld is being transmitted to the NRC in confidence.

I~ Gerard van Noordennen, being duly sworn, state that I am the person who subscribes my name the foregoing stateni.ent, I am authorized to execute the Affidavit on behalf of LaCrosseSolutions, LLC, and that the matters and facts set forth in the statement are true to the best of my knowledge, information, and belief.

Name: Gerard van Noordennen

Title:

Senior Vice President Regulatory Affairs Company: LaCrosseSolutions, LLC SUBSCRIBED AND SWORN TO BEFORE ME THIS Ab'H1nAY o f ~ , 2022

~Jtf p.l Notary Public A'

  • DANA S CHAPEL

- ..

  • Notary Public My Commission Expires 01/~M;Q~4