IR 05000315/2018005: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:August 28, 2018 Mr. Joel P. Gebbie Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgeman, MI 49106 SUBJECT: UPDATED INSPECTION PLAN FOR DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 (REPORT 05000 315/2018005 and 05000316/2018005) Dear Mr. Gebbie
[[Issue date::August 28, 2018]]
 
Mr. Joel P. Gebbie Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgeman, MI 49106
 
SUBJECT: UPDATED INSPECTION PLAN FOR DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 (REPORT 05000 315/2018005 and 05000316/2018005) Dear Mr. Gebbie
: The enclosed inspection plan lists the inspections scheduled through June 30 , 20 20 , for the Donald C. Cook Nuclear Power Plant, Units 1 and The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issue Routine inspections performed by resident inspectors are not included in the inspection pla The inspections listed during the last twelve months of the inspection plan are tentative and may be revise The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any change This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading
: The enclosed inspection plan lists the inspections scheduled through June 30 , 20 20 , for the Donald C. Cook Nuclear Power Plant, Units 1 and The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issue Routine inspections performed by resident inspectors are not included in the inspection pla The inspections listed during the last twelve months of the inspection plan are tentative and may be revise The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any change This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading
-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."
-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Revision as of 03:00, 16 May 2019

Updated Inspection Plan for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2018005 and 05000316/2018005)
ML18240A337
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 08/28/2018
From: Kenneth Riemer
NRC/RGN-III/DRP/B2
To: Gebbie J P
Indiana Michigan Power Co
References
IR 2018005
Download: ML18240A337 (5)


Text

August 28, 2018 Mr. Joel P. Gebbie Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgeman, MI 49106 SUBJECT: UPDATED INSPECTION PLAN FOR DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 (REPORT 05000 315/2018005 and 05000316/2018005) Dear Mr. Gebbie

The enclosed inspection plan lists the inspections scheduled through June 30 , 20 20 , for the Donald C. Cook Nuclear Power Plant, Units 1 and The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issue Routine inspections performed by resident inspectors are not included in the inspection pla The inspections listed during the last twelve months of the inspection plan are tentative and may be revise The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any change This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading

-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Please contact me at 630-829-9628 with any questions you have regarding this lette

Sincerely,

/RA/ Kenneth Riemer, Chief Branch 2 Division of Reactor Projects Docket No ; 50-31 6 License No DPR-58; DPR-74 Enclosure:

Inspection Plan cc: Distribution via LISTSERV

Letter to Joel Gebbie from Kenneth Riemer dated August 28, 2018 SUBJECT: UPDATED INSPECTION PLAN FOR DONALD