MONTHYEARIR 05000282/20230042024-02-0101 February 2024 Integrated Inspection Report 05000282/2023004 and 05000306/2023004 ML23356A1232024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML24024A0722024-01-24024 January 2024 Independent Spent Fuel Storage Installation, Onticello, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24017A0182024-01-19019 January 2024 Confirmation of Initial License Examination ML23356A0032024-01-17017 January 2024 Issuance of Amendments Revise Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-23-034, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System,2024-01-0202 January 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System, L-PI-23-035, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report2023-12-20020 December 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report IR 07200010/20234012023-12-20020 December 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200010/2023401 ML23349A0572023-12-15015 December 2023 and Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota ML23215A1672023-12-15015 December 2023 Acceptance of Requested Licensing Action Amendment Request to Revise Surveillance Requirement 3.8.1.2 Note 3 IR 05000282/20234012023-12-13013 December 2023 Security Baseline Inspection Report 05000282/2023401 and 05000306/2023401 L-PI-23-033, Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-12-0505 December 2023 Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 ML23304A1632023-11-15015 November 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Revise SR 3.8.1.2 Note 3 ML23319A3182023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000282/20230032023-11-0808 November 2023 Integrated Inspection Report 05000282/2023003 and 05000306/2023003 ML23311A3572023-11-0707 November 2023 Core Operating Limits Report (COLR) for Prairie Island Nuclear Generating Plant (PINGP) Unit 2. Cycle 33. Revision 0 ML23285A3062023-10-12012 October 2023 Implementation of the Fleet Standard Emergency Plan for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant ML23270B9022023-09-29029 September 2023 Review of Reactor Vessel Material Surveillance Program Capsule N Technical Report L-PI-23-025, License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-09-28028 September 2023 License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 ML23265A2532023-09-26026 September 2023 Review of Reactor Vessel Material Surveillance Program Capsule N Technical Report ML23262B0372023-09-19019 September 2023 Response to NRC Request for Additional Information Regarding the 2023 Monticello and Prairie Island Plant Decommissioning Funding Status Reports ML23256A1682023-09-13013 September 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Voluntary Security Clearance Program 2023 Insider Threat Program Self-Inspection L-PI-23-023, Baffle Former Bolts Alternate Aging Management Strategy2023-09-11011 September 2023 Baffle Former Bolts Alternate Aging Management Strategy IR 05000282/20230052023-08-30030 August 2023 Updated Inspected Plan for Prairie Island Nuclear Generating Plant Report 05000282/2023005 and 05000306/2023005 IR 05000282/20230102023-08-17017 August 2023 NRC Inspection Report 05000282/2023010 and 05000306/2023010 ML23222A0122023-08-10010 August 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Changes in Foreign Ownership, Control or Influence IR 05000282/20230022023-08-0303 August 2023 Integrated Inspection Report 05000282/2023002 and 05000306/2023002 ML23214A2032023-08-0202 August 2023 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000282/2024010; 05000306/2024010 ML23206A2342023-07-25025 July 2023 Independent Spent Fuel Storage Installation, and Monticello Nuclear Generating Plant, Changes in Foreign Ownership, Control or Influence ML23202A0032023-07-21021 July 2023 Independent Spent Fuel and Independent Spent Fuel Storage Installation, Monticello Nuclear Generating Plant, Submittal of Quality Assurance Topical Report (NSPM-1) ML23199A0922023-07-18018 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000306/2023004 ML23195A1732023-07-14014 July 2023 Revision of Standard Practice Procedures Plan L-PI-23-018, License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT2023-07-14014 July 2023 License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT ML23181A0192023-06-30030 June 2023 Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-PI-23-006, License Amendment Request to Revise Technical Specification 3.7.8 Required Actions2023-06-22022 June 2023 License Amendment Request to Revise Technical Specification 3.7.8 Required Actions L-PI-23-016, 2022 10 CFR 50.46 LOCA Annual Report2023-06-14014 June 2023 2022 10 CFR 50.46 LOCA Annual Report IR 05000282/20234202023-06-0101 June 2023 Security Baseline Inspection Report 05000282/2023420 and 05000306/2023420 ML23150A1722023-05-30030 May 2023 Preparation and Scheduling of Operator Licensing Examinations 2024-02-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23335A1152023-12-0101 December 2023 NRR E-mail Capture - Prairie Island Units 1 and 2 - Request for Additional Information LAR to Revise TS 3.7.8 Required Actions ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23214A2032023-08-0202 August 2023 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000282/2024010; 05000306/2024010 ML23199A0922023-07-18018 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000306/2023004 ML23096A3082023-04-0707 April 2023 Notification of Inspection an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23055B0562023-02-27027 February 2023 Request for Information for NRC Commercial Grade Dedication Inspection Inspection Report 05000282/2023010 and 05000306/2023010 ML23053A1432023-02-22022 February 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant ML22166A4112022-06-15015 June 2022 NRR E-mail Capture - Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-08, PIV Leakage ML22160A6022022-06-0909 June 2022 NRR E-mail Capture - Draft Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, 24-Month Operating Cycle Amendment ML22145A4152022-05-25025 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000282/2022402 05000306/2022402 ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22130A5792022-05-11011 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21321A0452021-11-10010 November 2021 Request for Additional Information: Prairie Island 24-Month Cycle Amendment Request ML21305A0102021-10-29029 October 2021 NRR E-mail Capture - Request for Additional Information Prairie Island Cooling Water Amendment ML21252A0122021-08-30030 August 2021 NRR E-mail Capture - Request for Additional Information Amendment Request to Adopt TSTF-471 and 517-T for Prairie Island ML21147A5232021-06-0303 June 2021 Prarie Island Nuclear Generating Plant, Units 1 and 2 - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21131A0752021-05-10010 May 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2021004; 05000306/2021004 ML21099A0972021-04-0909 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000282/2021012 and 05000306/2021012 ML21062A0532021-03-0202 March 2021 Information Request to Support Upcomng Problem Identification and Resolution (Pi&R) Inspection at the Prairie Island Nuclear Generating Plant ML21033A6112021-02-0101 February 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000282/2021010 and 05000306/2021010 ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information ML20192A1442020-07-0707 July 2020 NRR E-mail Capture - Request for Additional Information Prairie Island License Amendment Request to Adopt TSTF-505 ML20189A1782020-07-0606 July 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2020004; 05000306/2020004 ML20133K0692020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20077K6242020-04-13013 April 2020 License Amendment Request - Request for Additional Information ML20052F4102020-02-21021 February 2020 Notification of Nrc Design Bases Assurance Inspection (Programs) (05000282/202010; 05000306/202010) and Initial Request for Information ML20035F1552020-02-0404 February 2020 NRR E-mail Capture - Request for Additional Information Monticello and Prairie Island Alternative Requests to Adopt Code Cases N-786-3 and N-789-3 (Epids: L-2019-LLR-0078 and L-2019-LLR-0079) ML19233A0032019-08-14014 August 2019 NRR E-mail Capture - Request for Additional Information Prairie Island Relief Requests 1-RR-10 and 2-RR-10 ML19057A1652019-02-26026 February 2019 NRR E-mail Capture - Request for Additional Information Prairie Island 50.69 Amendment Request ML18313A0832018-11-0707 November 2018 NRR E-mail Capture - Request for Additional Information Prairie Island NFPA-805 License Condition Modification Amendment Request ML18264A1912018-09-19019 September 2018 NRC Information Request (9/19/2018); Part B Items (Onsite) IP 71111.08 - E-Mailed 09/19/18 (DRS-M.Holmberg) ML18235A2982018-08-23023 August 2018 NRR E-mail Capture - Request for Additional Information Prairie Island TSTF-425 License Amendment Request ML18169A4202018-06-25025 June 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Modify Renewed Facility Operating License Paragraph 2.C(4)(c) ML18025C0152018-01-24024 January 2018 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000282/2018011; 05000306/2018011 (DRS-A.Dunlop) ML17277B3332017-10-0404 October 2017 NRR E-mail Capture - Request for Additional Information Prairie Island Special Heavy Lifting Devices LAR ML17249A9232017-09-0606 September 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2017004; 05000306/2017004 (Exf) ML17235A9982017-08-23023 August 2017 NRR E-mail Capture - Request for Additional Information Prairie Island EAL Scheme Change ML17221A3892017-08-0909 August 2017 NRR E-mail Capture - Request for Additional Information for Prairie Island Nuclear Generating Plant License Amendment Request Dated February 23, 2017 Emergency Response Organization ML17219A0762017-08-0707 August 2017 NRR E-mail Capture - Request for Additional Information for Prairie Island Nuclear Generating Plant License Amendment Request Dated February 23, 2017 Emergency Response Organization ML17038A5132017-02-0707 February 2017 NRR E-mail Capture - Prairie Island NFPA 805 LAR, PRA RAI 21.01 ML17018A4272017-01-18018 January 2017 NRR E-mail Capture - Request for Additional Information: Prairie Island License Amendment Request to Revise Technical Specification 3.8.7 to Remove Non-Conservative Required Action ML16326A3532016-11-18018 November 2016 NRR E-mail Capture - Draft Request for Information Related to Prairie Island NFPA-805 License Amendment ML16265A1652016-09-20020 September 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2016004; 05000306/2016004 (Gfo) ML16189A2052016-07-0707 July 2016 Notification of NRC Inspection and Request for Information ML16113A1612016-04-21021 April 2016 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant, Units 1 and 2 ML16075A0802016-03-15015 March 2016 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 Request for Additional Information Related to License Amendment Request to Adopt TSTF-523, GL 2008-01, Managing Gas Accumulation ML16008A1092016-01-0808 January 2016 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Requests for Additional Information (Afpb) License Amendment Request to Adopt NFPA 805 ML15195A6562015-07-10010 July 2015 Prairie Island Notification of NRC Inspection and Request for Information ML15149A1662015-05-28028 May 2015 Plan - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15121A6512015-04-29029 April 2015 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection (CDBI) Inspection Report 05000282/2015007; 05000306/2015007 (Jen) 2023-09-05
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 September 18, 2013 Mr. James E. Lynch Site Vice President Northern States Power Company -Minnesota Prairie Island Nuclear Generating Plant 1717 Wakonade Drive East Welch,'MN 55089-9642 PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 REQUEST FOR ADDITIONAL INFORMATION RELATED TO REACTOR VESSEL INTERNALS PROGRAM SUBMITTAL FOR FULFILLMENT OF LICENSE RENEWAL COMMITMENT 25 (TAC NOS. MF0052 AND MF0053)
Dear Mr. Lynch:
By letter dated October 1, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12276A041), as supplemented by letters dated March 7, 2013, March 22, 2013, and June 24,2013 (ADAMS Accession Nos. ML 13067A284, ML 13084A378, and ML 13175A333, respectively), Northern States Power Company, a Minnesota corporation (NSPM, the licensee), doing business as Xcel Energy, submitted an aging management program (AMP) for the reactor vessel internals at Prairie Island Nuclear Generating Plant (PINGP), Units 1 and 2. Materials Reliability Program-227-A report, "Pressurized Water Reactor (PWR) Internals Inspection and Evaluation Guidelines," and its supporting reports were used as technical bases for developing the PINGP AMP. The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information reques.ted is addressed in the enclosureto this letter. On August 27,2013, a draft version of this request for additional information (RAI) was discussed between the licensee and the NRC staff to clarify the request. Following the teleconference, it was agreed that you would provide a response to this request within 30 days of the date of this letter. The NRC staff acknowledged that the licensee may not be able to respond to RAI 2-1 until that issue-is resolved on an industry-wide basis. Therefore, the schedule for the licensee's response to RAJ 2-1 will be determined at a later date. The NRC staff considers that timely responses to RAls help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources.
J. Lynch -2 If circumstances result in the need to revise the requested response date, please contact me at (301)415-4037.
Sincerely.
Thomas J. Wengert, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and Request for Additional cc w/encl: Distribution via REQUEST FOR ADDITIONAL INFORMATION ) PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 DOCKET NOS. 50-282 AND 50-306 By letter dated October 1, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12276A041), as supplemented by letters dated March 7,2013, March 22,2013, and June 24,2013 (ADAMS Accession Nos. ML 13067A284, ML 13084A378, and ML 13175A333, respectively), Northern States Power Company, a Minnesota corporation (NSPM, the licensee), doing business as Xcel Energy, submitted an aging management program (AMP) for the reactor vessel internals (RVI) at Prairie Island Nuclear Generating Plant (PINGP), Units 1 and 2. MRP-227-A report, "Pressurized Water Reactor (PWR) Internals Inspection and Evaluation Guidelines," and its supporting reports were used as the technical bases for developing the PINGP AMP. The U.S. Nuclear Regulatory Commission (NRC) staff reviewed this report and issued a final safety evaluation (SE) on December 16, 2011. Based on the review of PINGP's AMP conducted thus far,the staff has developed a second round of requests for additional information (RAI), as addressed below. The NRC staff may, however, issue additional RAls based on the resolution of Action Items 1 and 2 addressed in the staff's SE for the MRP-227 -A report. RAI2-1: As discussed in References 1 and 2 below, provide the following information related to verification of the applicability of MRP-227-A to PINGP, Units 1 and 2: Do the PINGP, Units 1 and 2, RVI have non-weld or bolting austenitic stainless steel components with 20 percent cold work or greater and, if so, do the affected components have operating stresses greater than 30 ksi? If so, perform a plant-specific evaluation to determine the aging management requirements for the affected components. Have PINGP, Units 1 and 2, ever utilized atypical fuel design or fuel management that could make the assumptions of MRP-227-A regarding core loading/core design non-representative for that plant, including power changes/uprates?
If so, describe how the differences were reconciled with the assumptions of MRP-227 -A, or provide a specific aging management program for the affected components, as appropriate.
References Meeting Summary Electric Power Research Institute (EPRI) -Westinghouse January 22-23, 2013, dated February 21, 2013 (ADAMS Accession No. ML 13042A048) February 25,2013 Summary of Teleconference with EPRI and Westinghouse Electric Company, dated March 15, 2013 (ADAMS Accession No. ML 13067A262)
Enclosure
-2 RAI.2-2: In the licensee's March 22, 2013, submittal it is not evident which of the RVI components in the PINGP design are specifically defined in the current licensing basis (CLB) as ASME Section XI, Examination Category B-N-3 removable core support structure components, or how these components relate to the four inspection categories that are defined for Westinghouse-designed . RVI components in Technical Report (TR) No. MRP-227-A (Le., as MRP-defined "Primary Category," "Expansion Category," "Existing Program," or "No Additional Measures" com ponents).
Part (a) -Identify all RVI components in the PINGP plant design that are defined in the CLB as ASME Section XI, Examination Category B-N-3 core support structure components.
For each of these components, identify which of the four inspection categories in MRP-227 -A is applicable to the component.
Part (b) -If a component identified in the reply to Part (a) is defined as either a "Primary Category" or "Expansion Category" component, identify any differences between the inspections that would be performed on the components under MRP-227 -A versus the plant's ASME Section XI inservice inspection (lSI) program. For each of these components identified in Part (b), clarify how the differences in inspection bases for these components will be reconciled consistent with the CLB for the facility.
RAI2-3: By letter dated March 7,2013, the licensee provided a response to Action Item 3 that was addressed in the NRC staff's SE for the MRP-227-A.
In its response to Action Item 3, the licensee provided its basis for why the replacement control rod guide tube (CRGT) assembly support pins (i.e., split pins) at PINGP (which are made from Type 316 cold-worked austenitic stainless steel) would not need to be inspected under the augmented inspection basis in TR MRP-227-A.
However, Updated Safety Analysis Report (USAR) Section 3.6.2.2 establishes the following bases with respect to the design of the CRGT assemblies:
The guide tube assemblies, shown on Figure 3.6-3, sheath and guide the control rod drive shafts and control rods and provide no other mechanical functions.
They are fastened to the upper support plate and are guided by pins in the upper core plate for proper orientation and support. Additional guidance for the control rod drive shafts is provided by the upper guide tube which is bolted to the upper 'support plate and guide tube. Based on this USAR information, it is not evident why the replacement CRGT split pins not need to be inspected in accordance with the ASME Section XI, Table Examination Category S-N-3 lSI requirements, as invoked by the lSI requirements *10 CFR 50.55a. Part (a) -Clarify whether the CRGT split pins are defined as ASME Section XI, Examination Category B-N-3 components for the PINGP CLB. If the CRGT split pins are defined in the CLB as ASME Section XI, Examination Category B-N-3 core support structure components, justify why the CRGT split pins would not need to be inspected as a part of the "Existing Program"
-bases of the PWR Vessel Internals Program or alternatively in accordance with the aging management program (AMP) for the facility that corresponds to GALL AMP XI.Ml, "ASME Section Xllnservice Inspection, Subsections IWB, IWC, and IWD" Program. Part (b) -Justify why the response to Applicant/Licensee Action Item #3 did not specifically address whether the ASME Section XI "Existing Program" bases in the CLBfor the CRGT split pins is sufficient for ensuring adequate aging management of the split pins during the period of extended operation.
Otherwise, amend the submittal to provide a response to the AI LA I that specifically addresses the adequacy of ASME Section XI lSI bases for the CRGT split pins and whether these bases are sufficient to manage aging in the components during the period of extended operation.
RAI2-4: The NRC staff requests that the licensee address the following issues: Pages 43 -45 of Attachment 1 of the licensee's March 22, 2013, submittal includes the "Expansion Category" components.
Clarify whether the "Expansion Link" column for that "Expansion Coniponent" Table should be interpreted as a "Primary Link" column for the table. Page 46 of Attachment 1 of the licensee's March 22, 2013, submittal includes the "Existing Program" components.
Clarify whether the "Expansion Link" col.umn for that "Existing Program Component" Table should be interpreted as an "Existing Program Reference" column for the table. .
J. E. Lynch -2 If circumstances result in the need to revise the requested response date, please contact me at (301) 415-4037.
Sincerely, IRA! Thomas J. Wengert, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306 .
Enclosure:
Request for Additional Information cc w/encl: Distribution via ListServ DISTRIBUTION:
PUBLIC RidsNrrDorlLpl3-1 Resource RidsNrrDorlDpr Resource RidsNrrPMPrairielsland Resource RidsNrrLAMHendersonResource JMedoff, NRR RidsAcrsAcnw_MailCTR Resource GCheruvenki, NRR LPL3-1 RlF RidsRgn3MailCenter Resource RidsNrrDeEvib Resource ADAMS Accession Number: ML 13253A 122 '" via memo LPL3-1/PM LPL3-1/LAiT . LPL3-1/LA EVIB/BC TWengert MHender rer SRosenberg*