MONTHYEARML23348A3472023-12-12012 December 2023 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Minnesota Regarding a Prairie Island Nuclear Generating Plant, Units 1 & 2, Amendment ML23335A1152023-12-0101 December 2023 NRR E-mail Capture - Prairie Island Units 1 and 2 - Request for Additional Information LAR to Revise TS 3.7.8 Required Actions ML23312A0882023-11-0808 November 2023 Acceptance of Request to Revise Alternatives 1-RR-5-10 and 2-RR-5-10 ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23207A1962023-07-26026 July 2023 NRR E-mail Capture - Prairie Island Units 1 and 2 - Acceptance of Requested Licensing Action Request to Revise Technical Specification 3.7.8 Required Actions ML23075A2802023-03-16016 March 2023 NRR E-mail Capture - Prairie Island Units 1 and 2 - Acceptance of Relief Requests 1-RR-5-15 and 2-RR-5-15 to Use Subsequent ASME Code Edition and Addenda ML23065A0592023-02-27027 February 2023 NRR E-mail Capture - (External_Sender) Prairie Island Request for Pre-application Meeting for Proposed LAR to Change TS 3.7.8, Condition B Required Actions ML23018A2952023-01-18018 January 2023 Acceptance of Requested Licensing Action to Revise Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) (EPID L-2022-LLA-0184) (Email) ML22167A0452022-06-16016 June 2022 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Request to Adopt TSTF-277 ML22166A4112022-06-15015 June 2022 NRR E-mail Capture - Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-08, PIV Leakage ML22160A6022022-06-0909 June 2022 NRR E-mail Capture - Draft Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, 24-Month Operating Cycle Amendment ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22045A4972022-02-14014 February 2022 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Unit 2 - Acceptance of Alternative Request Alternative Related PIV Leakage Monitoring ML21347A0082021-12-10010 December 2021 NRR E-mail Capture - Monticello and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested License Amendment Standard Emergency Plan and Consolidated Emergency Operations Facility ML21321A0452021-11-10010 November 2021 Request for Additional Information: Prairie Island 24-Month Cycle Amendment Request ML21302A1252021-10-29029 October 2021 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action RTS Power Range Amendment ML21305A0102021-10-29029 October 2021 NRR E-mail Capture - Request for Additional Information Prairie Island Cooling Water Amendment ML21252A0152021-09-0202 September 2021 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Change in the Maximum Surveillance Intervals from 24 Months to 30 Months ML21252A0122021-08-30030 August 2021 NRR E-mail Capture - Request for Additional Information Amendment Request to Adopt TSTF-471 and 517-T for Prairie Island ML21133A2502021-05-13013 May 2021 NRR E-mail Capture - Prairie Island - Acceptance Review of TSTF-471 and TSTF-571-T ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information ML20253A2782020-09-0909 September 2020 E-Mail Submitting Proposed New License Condition ML20254A1162020-09-0909 September 2020 Draft License Transmittal E-Mail ML20223A0632020-08-10010 August 2020 Email Shpo Comment Letter: Proposed License Amendment for the Prairie Island Independent Spent Fuel Storage Installation ML20192A1442020-07-0707 July 2020 NRR E-mail Capture - Request for Additional Information Prairie Island License Amendment Request to Adopt TSTF-505 ML20163A4282020-06-10010 June 2020 Email from MPCA Comment Letter - Prairie Island ISFSI ML20154K7632020-06-0202 June 2020 NRR E-mail Capture - Revision 2 to the Plan for the Audit of the Prairie Island Nuclear Generating Plant TSTF-505 License Amendment Request (Epdi: L-2019-LLA-0283) ML20135G8212020-05-14014 May 2020 NRR E-mail Capture - Revision to the Plan for the Audit of the Prairie Island Nuclear Generating Plant TSTF-505 License Amendment Request (Epdi: L-2019-LLA-0283) ML20112F4582020-04-21021 April 2020 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Low Temperature Overpressure Protection ML20083F4202020-03-20020 March 2020 NRR E-mail Capture - Plan for the Audit of the Prairie Island Nuclear Generating Plant TSTF-505 License Amendment Request (Epdi: L-2019-LLA-0283) ML20077L4632020-03-17017 March 2020 NRR E-mail Capture - Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 -Acceptance of Requested Licensing Action Request to Adopt TSTF-529 ML20052C7582020-02-21021 February 2020 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Westinghouse NSAL-09-05 and NSAL-09-05 ML20035F1552020-02-0404 February 2020 NRR E-mail Capture - Request for Additional Information Monticello and Prairie Island Alternative Requests to Adopt Code Cases N-786-3 and N-789-3 (Epids: L-2019-LLR-0078 and L-2019-LLR-0079) ML20022A1762020-01-22022 January 2020 NRR E-mail Capture - Prairie Units 1 and 2 - Acceptance of Requested Licensing Action Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements ML20021A1832020-01-21021 January 2020 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2 ML19316A0172019-11-0101 November 2019 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Integrated Leak Rate Test Extension Request ML19253B9642019-09-10010 September 2019 NRR E-mail Capture - Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Relief Request Adoption of Code Case N-786-3 ML19233A0032019-08-14014 August 2019 NRR E-mail Capture - Request for Additional Information Prairie Island Relief Requests 1-RR-10 and 2-RR-10 ML19193A0142019-07-0909 July 2019 NRR E-mail Capture - Acceptance of Prairie Island Nuclear Generating Plant, Units 1 and 2 Relief Request Nos. 1-RR-5-10 and 2-RR-5-10 Related to Reactor Vessel Inspection Intervals) ML19057A1652019-02-26026 February 2019 NRR E-mail Capture - Request for Additional Information Prairie Island 50.69 Amendment Request ML19057A4212019-02-26026 February 2019 NRR E-mail Capture - Acceptance of Prairie Island Reactor Vessel Capsule Removal Schedule Request ML19008A3562019-01-0707 January 2019 NRR E-mail Capture - Prairie Island Nuclear Generating Plant - Audit Plan Related to the License Amendment Request to Implement 10 CFR 50.69 ML18351A0142018-12-14014 December 2018 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Classification of Certain Fuel Handling Equipment ML18347A3282018-12-12012 December 2018 E-Mail from M. Krick/Sses SSES ISFSI (Conversation Held on December 12, 2018) ML18313A0832018-11-0707 November 2018 NRR E-mail Capture - Request for Additional Information Prairie Island NFPA-805 License Condition Modification Amendment Request ML18235A2982018-08-23023 August 2018 NRR E-mail Capture - Request for Additional Information Prairie Island TSTF-425 License Amendment Request ML18233A3692018-08-21021 August 2018 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Adoption of 10 CFR 50.69 ML18201A4132018-07-20020 July 2018 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt TSTF-439 ML18159A3052018-06-0808 June 2018 NRR E-mail Capture - Monticello - Acceptance of Requested Relief Request RR-012: Lnservice Inspection Impracticality in Accordance with 10 CFR 50.55a(g)(5)(iii) During the Fifth Ten-Year Interval ML18113A2252018-04-23023 April 2018 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt TSTF-425 2023-09-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23335A1152023-12-0101 December 2023 NRR E-mail Capture - Prairie Island Units 1 and 2 - Request for Additional Information LAR to Revise TS 3.7.8 Required Actions ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23214A2032023-08-0202 August 2023 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000282/2024010; 05000306/2024010 ML23199A0922023-07-18018 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000306/2023004 ML23096A3082023-04-0707 April 2023 Notification of Inspection an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23055B0562023-02-27027 February 2023 Request for Information for NRC Commercial Grade Dedication Inspection Inspection Report 05000282/2023010 and 05000306/2023010 ML23053A1432023-02-22022 February 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant ML22166A4112022-06-15015 June 2022 NRR E-mail Capture - Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-08, PIV Leakage ML22160A6022022-06-0909 June 2022 NRR E-mail Capture - Draft Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, 24-Month Operating Cycle Amendment ML22145A4152022-05-25025 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000282/2022402 05000306/2022402 ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22130A5792022-05-11011 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21321A0452021-11-10010 November 2021 Request for Additional Information: Prairie Island 24-Month Cycle Amendment Request ML21305A0102021-10-29029 October 2021 NRR E-mail Capture - Request for Additional Information Prairie Island Cooling Water Amendment ML21252A0122021-08-30030 August 2021 NRR E-mail Capture - Request for Additional Information Amendment Request to Adopt TSTF-471 and 517-T for Prairie Island ML21147A5232021-06-0303 June 2021 Prarie Island Nuclear Generating Plant, Units 1 and 2 - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21131A0752021-05-10010 May 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2021004; 05000306/2021004 ML21099A0972021-04-0909 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000282/2021012 and 05000306/2021012 ML21062A0532021-03-0202 March 2021 Information Request to Support Upcomng Problem Identification and Resolution (Pi&R) Inspection at the Prairie Island Nuclear Generating Plant ML21033A6112021-02-0101 February 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000282/2021010 and 05000306/2021010 ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information ML20192A1442020-07-0707 July 2020 NRR E-mail Capture - Request for Additional Information Prairie Island License Amendment Request to Adopt TSTF-505 ML20189A1782020-07-0606 July 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2020004; 05000306/2020004 ML20133K0692020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20077K6242020-04-13013 April 2020 License Amendment Request - Request for Additional Information ML20052F4102020-02-21021 February 2020 Notification of Nrc Design Bases Assurance Inspection (Programs) (05000282/202010; 05000306/202010) and Initial Request for Information ML20035F1552020-02-0404 February 2020 NRR E-mail Capture - Request for Additional Information Monticello and Prairie Island Alternative Requests to Adopt Code Cases N-786-3 and N-789-3 (Epids: L-2019-LLR-0078 and L-2019-LLR-0079) ML19233A0032019-08-14014 August 2019 NRR E-mail Capture - Request for Additional Information Prairie Island Relief Requests 1-RR-10 and 2-RR-10 ML19057A1652019-02-26026 February 2019 NRR E-mail Capture - Request for Additional Information Prairie Island 50.69 Amendment Request ML18313A0832018-11-0707 November 2018 NRR E-mail Capture - Request for Additional Information Prairie Island NFPA-805 License Condition Modification Amendment Request ML18264A1912018-09-19019 September 2018 NRC Information Request (9/19/2018); Part B Items (Onsite) IP 71111.08 - E-Mailed 09/19/18 (DRS-M.Holmberg) ML18235A2982018-08-23023 August 2018 NRR E-mail Capture - Request for Additional Information Prairie Island TSTF-425 License Amendment Request ML18169A4202018-06-25025 June 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Modify Renewed Facility Operating License Paragraph 2.C(4)(c) ML18025C0152018-01-24024 January 2018 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000282/2018011; 05000306/2018011 (DRS-A.Dunlop) ML17277B3332017-10-0404 October 2017 NRR E-mail Capture - Request for Additional Information Prairie Island Special Heavy Lifting Devices LAR ML17249A9232017-09-0606 September 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2017004; 05000306/2017004 (Exf) ML17235A9982017-08-23023 August 2017 NRR E-mail Capture - Request for Additional Information Prairie Island EAL Scheme Change ML17221A3892017-08-0909 August 2017 NRR E-mail Capture - Request for Additional Information for Prairie Island Nuclear Generating Plant License Amendment Request Dated February 23, 2017 Emergency Response Organization ML17219A0762017-08-0707 August 2017 NRR E-mail Capture - Request for Additional Information for Prairie Island Nuclear Generating Plant License Amendment Request Dated February 23, 2017 Emergency Response Organization ML17038A5132017-02-0707 February 2017 NRR E-mail Capture - Prairie Island NFPA 805 LAR, PRA RAI 21.01 ML17018A4272017-01-18018 January 2017 NRR E-mail Capture - Request for Additional Information: Prairie Island License Amendment Request to Revise Technical Specification 3.8.7 to Remove Non-Conservative Required Action ML16326A3532016-11-18018 November 2016 NRR E-mail Capture - Draft Request for Information Related to Prairie Island NFPA-805 License Amendment ML16265A1652016-09-20020 September 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2016004; 05000306/2016004 (Gfo) ML16189A2052016-07-0707 July 2016 Notification of NRC Inspection and Request for Information ML16113A1612016-04-21021 April 2016 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant, Units 1 and 2 ML16075A0802016-03-15015 March 2016 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 Request for Additional Information Related to License Amendment Request to Adopt TSTF-523, GL 2008-01, Managing Gas Accumulation ML16008A1092016-01-0808 January 2016 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Requests for Additional Information (Afpb) License Amendment Request to Adopt NFPA 805 ML15195A6562015-07-10010 July 2015 Prairie Island Notification of NRC Inspection and Request for Information ML15149A1662015-05-28028 May 2015 Plan - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15121A6512015-04-29029 April 2015 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection (CDBI) Inspection Report 05000282/2015007; 05000306/2015007 (Jen) 2023-09-05
[Table view] |
Text
NRR-DMPSPEm Resource From: Kuntz, Robert Sent: Thursday, August 23, 2018 5:19 AM To: 'Scott, Sara'
Subject:
Request for Additional Information RE: Prairie Island TSTF-425 license amendment request Ms. Scott, By application dated March 15, 2018 (Agencywide Documents Access and Management System Accession No. ML18074A308), Northern States Power Company, requested changes to the Technical Specification (TS) for Prairie Island Nuclear Generating Plant, Units 1 and 2. The requested change is the adoption of Nuclear Regulatory Commission-approved TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee ControlRITSTF Initiative 5b.
The NRC staff has determined that additional information is required to complete its review. The following is a request for additional information (RAI). During a call with the NRC staff for the staff to provide clarification on the RAI, it was agreed a response would be provided within 30 days of this email. If a response cannot be provided by September 24, 2019 contact me.
Robert Kuntz Senior Project Manager (Monticello and Prairie Island)
NRC/NRR/DORL/LPL3 (301)415-3733 REQUEST FOR ADDITIONAL INFORMATION RELATED TO AN AMENDMENT TO IMPLEMENT TSTF-425 REVISION 3 NORTHERN STATES POWER COMPANY PRAIRIE ISLAND NUCLEAR GENERATING PLANTS, UNITS 1 AND 2 DOCKET NO. 50-282 & 50-306
- 1. Attachment 2 to the license amendment request, Section 2.3, Applicability of Peer Review Findings and Observations (F&Os), states that a findings closure review was conducted in October 2017 in accordance with Appendix X (ADAMS Accession No. ML17086A451) to NEI 05-04. The Nuclear Regulatory Commission (NRC) has not officially endorsed the guidance in Appendix X; however, is permitting licensees to use the guidance on an interim basis subject to conditions of acceptance outlined in NRCs letter to Nuclear Energy Institute dated May 3, 2017 (ADAMS Accession No. ML17079A427). Provide the following information to confirm that the October 2017 closure review was performed consistent with the NRC accepted process, as discussed in the May 3, 2017 letter:
- a. Clarify whether a focused-scope peer review was performed concurrently with the F&O closure process. If so, provide the following:
- i. Summary of the scope of the peer review.
ii. Detailed descriptions of any new F&Os generated from the peer review and the associated dispositions for the application.
1
- b. Confirm that the closure review team was provided with a written assessment and justification of whether the resolution of each F&O, within the scope of the independent assessment, constitutes a probabilistic risk assessment (PRA) upgrade or maintenance update, as defined in American Society of Mechanical Engineers/American Nuclear Society (ASME/ANS) RA-Sa-2009, Addenda to ASME/ANS RA-S-2008, Standard for Level 1/Large Early Release Frequency Probabilistic Risk Assessment for Nuclear Power Plant Applications, as qualified by Regulatory Guide (RG) 1.200, Revision 2, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities, (ADAMS Accession No. ML090410014). If the written assessment and justification for the determination of each F&O was not performed and reviewed by the F&O closure review team, provide all the finding-level F&Os and the dispositions of these F&Os as it pertains to the impact on the TSTF-425 application. Alternatively, perform an Independent Assessment F&O closure review consistent with Appendix X, as accepted, with conditions, by the NRC letter dated May 3, 2017, and provide any additional open F&Os and associated dispositions as a result of this review.
- c. Appendix X,Section X.1.3 includes five criteria for selecting members of the closure review team.
Describe how the selection of members for the October 2017 independent assessment met the five criteria.
- d. Explain how closure of the F&Os was assessed to ensure that the capabilities of the PRA elements, or portions of the PRA within the elements, associated with the closed F&Os now meet capability category II (CC-II) for supporting requirements (SRs) from ASME/ANS RA-Sa-2009, as endorsed, with clarifications and qualifications, by RG 1.200, Revision 2.
- e. Discuss whether the F&O closure review scope included all finding-level F&Os, including those finding-level F&Os that are associated with Met SRs. If not, identify and provide detailed descriptions for any F&Os that were excluded from the F&O closure review scope, and their associated disposition for the application.
- f. For any SRs that were found to be only met at CC I by previous peer review team(s), summarize the disposition of these SRs and how it was concluded they now meet CC II. Include discussion of whether all associated F&Os described what was needed to achieve CC II and how the F&O reviewed and closed by the F&O closure team.
- 2. Section 2.3.3 of the LAR states PINGP fire PRA will be utilized in a supplementary role (as discussed further in Section 3.0) since the fire PRA model is based on the PINGP plant configuration assuming completion of all NFPA-805 design improvements. Table S-2 of NFPA 805 LAR Attachment S Modifications and Implementation Items outlines those design improvements that are scheduled for completion by second refueling outage per issuance of NFPA 805 license amendment (August 8, 2017). Responses to the following will provide additional clarification with regard to use of the Fire PRA:
- a. Provide those plant modifications listed in Table S-2 that are currently scheduled for completion beyond the second refueling outage.
- b. NEI 04-10 Step 10 Initial Assessment for Fire Events states that if the plant has a Fire PRA, then the next step of the screening process is to determine whether the SSC is evaluated in the fire PRA.
- i. Provide detailed justification that explains the basis for why PINGP opts to not follow the guidance outlined in NEI 04-10 Step 10 with regard to determining the use of Fire PRA on case by case basis.
ii. In the case that minimal number or low risk significant design improvements remain after the second refueling outage, provide an updated process for how the fire PRA will be used for TSTF-425 surveillance changes.
2
- 3. Provide the following information with regard to remaining open F&Os described in the Table 2-1:
- a. Finding CS-A10-01 states that cables routed through 16 fire compartments have not been identified nor has the methodology been specified. The resolution indicates that this supporting requirement is met at CC-1 using a conservative approach. Describe the conservative approach used in lieu of developing cable routing information for 16 fire compartments.
- b. Finding FSS-D7-01 indicates that the F&O closure review team determined to keep this finding open since the unreliability of the detection system for the deluge system is not incorporated in the PRA. In a letter dated May 24, 2016 (ADAMS Accession No. ML16152A046) to the NRC, Xcel Energy notes in Table 1, PRA RAI 01.g the following: The non-suppression probability has been calculated as sum of the unreliability and the unavailability values corresponding to each credited automatic detection and suppression system. This approach has been implemented in all the scenarios analyzed with detailed fire modeling crediting automatic suppression in the Fire PRA. This statement is inconsistent with the finding observed by the closure review team.
Provide the following information regarding characterization of suppression systems:
- i. Provide results of extent of condition analysis to determine additional detection systems that did not factor unreliability into the PRA calculation. If other detection systems, beside deluge system, are discovered to not factor unreliability, provide sensitivity analysis that shows risk impact for each system.
ii. With regard to deluge system, describe how the risk impacts of omitting unreliability in the calculation would be conservatively assessed for STI change evaluations; and provide a complete list of STI cases for which this assessment would have to be performed.
iii. Provide an approximate timeline for closure of this F&O.
- c. Finding SY-A17-01 indicates that the closure review team determined that the F&O related to Flowserve N-9000 reactor coolant pump (RCP) seals should remain open. Provide clarification that describes the current basis for modeling N-9000 RCP seals and technical justification for any PRA credit if abeyance seal modifications are employed or provide sensitivity that removes PRA credit.
3
Hearing Identifier: NRR_DMPS Email Number: 532 Mail Envelope Properties (Robert.Kuntz@nrc.gov20180823051800)
Subject:
Request for Additional Information RE: Prairie Island TSTF-425 license amendment request Sent Date: 8/23/2018 5:18:41 AM Received Date: 8/23/2018 5:18:00 AM From: Kuntz, Robert Created By: Robert.Kuntz@nrc.gov Recipients:
"'Scott, Sara'" <Sara.Scott@xenuclear.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 8470 8/23/2018 5:18:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: