License Amendment Request OL-1217 for Callaway Plant Union Electric Company Response to Request for Additional Information Deletion of Operating License Section
ML052000083
Person / Time
Site: Callaway Ameren icon.png
Issue date: 06/17/2005
From: Keith Young
AmerenUE
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
OL-1217, ULNRC-05162
Download: ML052000083 (6)


Text

AmerenUE PO Box 620 Callaway Plant Fulton, MO 65251 June 17, 2005 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop P1-137 Washington, DC 20555-0001 Ladies and Gentlemen: ULNRC-05162 DOCKET NUMBER 50-483 CALLANNWAY PLANT WAmeren UNION ELECTRIC COMPANY UE LICENSE AMENDMENT REQUEST OL-1217 RESPONSES TO REQUESTS FOR ADDITIONAL INFORMATION DELETION OF OPERATING LICENSE SECTION 2.F, DELETION OR REVISION OF LICENSE CONDITIONS, AND REVISION TO TECHNICAL SPECIFICATION TABLES 5.5.9-2 AND 5.5.9-3

Reference:

ULNRC-05070, dated October 27, 2004 The referenced letter transmitted to the NRC AmerenUE's subject proposed license amendment request. During its review, the NRC staff made requests for additional information and clarifications via e-mail and telephone conference.

AmerenUE has responded via e-mail and telephone conference. This letter provides for AmerenUE's formal transmittal of the information that was previously responded to electronically. The Attachment to this letter provides a composite of all NRC staff requests for additional information and AmerenUE's responses to those requests.

If you should have any questions on the above or attached, please contact Dave Shafer at (314) 554-3104 or Dwyla Walker at (314) 554-2126.

Sincerely, jp OA'1 Keith D. Young Manager, Regulatory Affairs DJW"/jdg Attachment 00 (

a subsidiary of Ameren Corporation

ULNRC-05162 June 17, 2005 Page 2 cc: U.S. Nuclear Regulatory Commission (Original and 1 copy)

Attn: Document Control Desk Mail Stop P1-137 Washington, DC 20555-0001 Mr. Bruce S. Mallett Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Jack N. Donohew (2 copies)

Licensing Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 7E1 Washington, DC 20555-2738 Missouri Public Service Commission Governor Office Building 200 Madison Street PO Box 360 Jefferson City, MO 65102-0360 Deputy Director Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102

ULNRC-05 162 June 17, 2005 Page 4 STATE OF MISSOURI

} Ss CALLAWAY COUNTY Keith D. Young of lawful age, being first duly sworn upon oath says that he is Manager - Regulatory Affairs, for Union Electric Company; that he has read the foregoing document and knows the content thereof; that he has executed the same for and on behalf of said company with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.

By 4 (4T

'-' KeithO/YounVJ Manager, Regulatory Affairs SUBSCRIBED and sworn to before me this 1l ' day of Ju. e 2005

-CO(ctA-c1 pab1 t

,S-jz,4-c I Al cM(Ai 1 '-) - ott

Attachment to ULNRC-05162 RESPONSES TO NRC REQUESTS FOR ADDITIONAL INFORMATION MADE DURING TELEPHONE CONFERENCE ON MAY 2,2005 AND TRANSMITTED TO AMERENUE VIA E-MAIL DATED MAY 5,2005 Request 1:

Provide implementation date for License Condition 2.C.(l), Attachment I (A)

AmerenUE Response:

License Condition 2.C.(1), Attachment 1 (A): The Callaway Commitment Tracking System indicates that the training was implemented on November 27, 1984. This date satisfied the condition and it is closed.

Request 2:

Provide installation date for License Condition 2.C.(1), Attachment 1 (B)

AmerenUE Response:

License Condition 2.C.(1), Attachment 1 (B): The Callaway Commitment Tracking System indicates that the modification package for the installation of a permanent area monitor on the manipulator crane was completed March 31, 1986.

This satisfied the condition and it is closed.

Request 3:

Additional information is needed on License Condition 2.C.(6).(b). Part of the condition requires there be an advisor to the plant manager during start-up and for one year following full power operation. Then application does not state that Mr.

Daniel C. Poole (Callaway advisor to plant manager) fulfilled this role for one year following the start of full power operation (i.e., when did this role begin with respect to plant startup and when did it end with respect to full power operation).

We need to know this so that we know this part of condition was met. This would be additional information needed to be submitted in a letter.

AmercnUE Response:

License Condition 2.C.(6).(b): Letter to the NRC, ULNRC-01 231 dated January 3, 1986, submitted a license amendment request to revise the Technical Specification organization and to remove the position of Advisor to the Plant Manager. Justification for the revision was based on the fact that License Condition 2.C.(6).(b) was satisfied as of December 19, 1985. Amendment 16 was approved September 8, 1986.

1 of3

Attachment to ULNRC-05162 Request 4:

Review other License Conditions for any that may require additional documentation.

AmerenUE Response:

License Condition 2.C.(8): Letter to the NRC, ULNRC-01062 dated March 19, 1985, provided documentation of completion of the Initial Test Program.

11. RESPONSES TO NRC REQUESTS FOR ADDITIONAL INFORMATION TRANSMITTED TO AMERENUE VIA E-MAIL DATED MAY 25,2005 Request 1:

What was the date that Callaway entered its 1st "Mode 6 (refueling mode)"

[This question is in regard to Condition 2.C.(1) Attachment 1, part b]

AmerenUE Response:

Callaway's first refueling outage started on February 28, 1986 and ended April 18, 1986. As indicated on the control room Shift Supervisor Daily log, the area radiation monitor, SD-RE-41, on the manipulator crane was OPERABLE on March 7, 1986. Also indicated on the control room Shift Supervisor Daily log is that the plant was in Mode 5 on March 8, 1986 and in Mode 6 on March 9, 1986.

The completion of the monitor installation modification package (completion of all associated activities and paper work) was on March 31, 1986. The dates are consistent with the information provided to the NRC in ULNRC-1254, dated February 7, 1986 and in regard to Condition 2.C.(1) Attachment 1, part b.

Request 2:

What was the restart date of Callaways 1st refueling outage?

[This date is needed for time requirement of Condition 2.C.7 part b & c]

AmerenUE Response:

As stated in response to question 1, restart from the first refueling outage occurred April 18, 1986.

2of3

Attachment to ULNRC-05162 Request 3:

Why is there a discrepancy in the SER (page 14) of Amendment No. 15 (April 8, 1986) stating License Condition 14 as LOCA Reanalysis and your license stating License Condition 13 as LOCA Reanalysis? As Jack mentioned in the phone conversation on May 25, any information would be helpful, but the content of the SER relates to Callaway's LOCA Reanalysis License Condition 13.

ArnerenUE Response:

Callaway does not know why there is a discrepancy in the SER. In our communications to NRC (both ULNRC-1207, dated November 15, 1985 and ULNRC-1247, dated January 28, 1986) Callaway refers to License Condition 2.C.13.