ULNRC-06772, 10 CFR 50.59 and 10 CFR 72.48 Summary Report

From kanterella
Jump to navigation Jump to search
10 CFR 50.59 and 10 CFR 72.48 Summary Report
ML22327A223
Person / Time
Site: Callaway  Ameren icon.png
Issue date: 11/23/2022
From: Witt T
Ameren Missouri, Union Electric Co
To:
Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation, Document Control Desk
Shared Package
ML22327A222 List:
References
ULNRC-06772
Download: ML22327A223 (1)


Text

Aiiier MISSOURI en Callaway Plant November 23, 2022 ULNRC-06772 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 10 CFR 50.59 10 CFR 72.48 Ladies and Gentlemen:

DOCKET NUMBERS 50-483 AND 72-1045 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO.

RENEWED FACILITY OPERATING LICENSE NPF-30 10 CFR 50.59 AND 10 CFR 72.4$

SUMMARY

REPORT In accordance with 1 0 CFR 50.59(d)(2) and 1 0 CFR 72.48(d)(2), this letter transmits a report that summarizes the 10 CFR 50.59 and 10 CFR 72.48 evaluations for changes, tests, and experiments approved and implemented within the reporting period for activities at Callaway Plant. Specifically, this enclosed report covers all evaluations that were implemented from June 1 6, 202 1 to November 23, 2022. In addition to those, a 1 0 CFR 50.59 evaluation that was omitted in the previous 10 CFR 50.59 and 1 0 CFR 72.48 summary report (submitted via Ameren Missouri letter ULNRC-06677 dated June 22, 2021) and is now included in this summary report. The omission has been addressed in the Callaway corrective action program.

This letter does not contain new commitments.

If there are any questions, please contact Mr. Tom Elwood at (3 1 4) 225-1905.

Sincerely, Todd Witt, Manager, Regulatory Affairs Enclosure 83 15 County Road 459 Steedman, MO 65077 AmerenMissouri.com

ULNRC-06772 November 23, 2022 Page 2 of 3 cc: Mr. Scott A. Morris Regional Administrator U. S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U. S Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. M. Chawla Project Manager, Callaway Plant Office ofNuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop O8B1A Washington, DC 20555-0001 Director Division of Spent Fuel Management Office ofNuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission Washington, DC 20555-0001

ULNRC-06772 November 23, 2022 Page 3 of 3 Index and send hardcopy to QA File A160.0761 Hardcopy:

Certrec Corporation 6500 West Freeway, Suite 400 FortWorth,TX 76116

( Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)

Electronic distribution for the following can be made via Responses and Reports ULNRC Distribution:

F. M. Diya B. L. Cox F. J. Bianco D. E. Farnsworth B.L. Jungmann T.A.Witt T.B.Elwood S. A. Gaydos G. N. Klein NSRB Secretary STARS Regulatory Affairs Mr. Jay Silberg (Pillsbury Winthrop Shaw Pittman LLP)