ML14127A20731 December 2013Columbia Generating Station Annual Radioactive Effluent Release Report: January Through December 2013Offsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
Feedwater Heater
Annual Radiological Environmental Operating Report
Process Control Program
Annual Radiological Effluent Release Report
Tritium
GO2-14-069, Offsite Dose Calculation Manual31 December 2013Offsite Dose Calculation ManualGrab sample
Offsite Dose Calculation Manual
Met Tower
Annual Radiological Environmental Operating Report
Process Control Program
Power change
ML14010A29330 December 2013Final Safety Analysis Report, Amendment 62, Chapter 1 - Introduction and General Description of PlantSafe Shutdown
High winds
Reactor Vessel Water Level
High Radiation Area
Ultimate heat sink
Grab sample
Offsite Dose Calculation Manual
Anticipated operational occurrence
Safe Shutdown Earthquake
Coatings
Operating Basis Earthquake
Nondestructive Examination
Emergency Lighting
Incorporated by reference
High Energy Line Break
Aging Management
Abnormal operational transient
Design basis earthquake
Flow Accelerated Corrosion
Feedwater Heater
Scram Discharge Volume
Intergranular Stress Corrosion Cracking
Stress corrosion cracking
Excess Flow Check Valve
Earthquake
Control of Heavy Loads
Chernobyl
Turbine Missile
Fuel cladding
Accidental discharge
Fire Protection Program
Unidentified leakage
Unidentified leak
Power Uprate
Overspeed trip
Water rod
Control Room Habitability
ML14010A30930 December 2013Final Safety Analysis Report, Amendment 62, Chapter 13 - Conduct of OperationsSafe Shutdown
Offsite Dose Calculation Manual
Hydrostatic
Local Leak Rate Testing
Fire Protection Program
Power change
Operability Assessment
Thermography
ML14010A30230 December 2013Final Safety Analysis Report, Amendment 62, Chapter 7 - Instrumentation and Control SystemsHot Short
Safe Shutdown
Shutdown Margin
Reactor Vessel Water Level
Grab sample
Fire Barrier
Anticipated operational occurrence
Safe Shutdown Earthquake
Internal Flooding
Squib
High Energy Line Break
Abnormal operational transient
Scram Discharge Volume
Overtravel
Earthquake
Turbine Missile
Fuel cladding
Power change
Unidentified leakage
Overspeed trip
Water hammer
ML14010A30830 December 2013Final Safety Analysis Report, Amendment 62, Chapter 12 - Radiation Protection, Figure 12.3-19 Through Page 12.5-21Loop seal
High Radiation Area
Grab sample
Feedwater Heater
Deep Dose Equivalent
ML14010A29230 December 2013Final Safety Analysis Report, Amendment 62, List of Effective Pages
ML14010A30330 December 2013Final Safety Analysis Report, Amendment 62, Chapter 8 - Electric PowerHot Short
Safe Shutdown
Shutdown Margin
Loop seal
Ultimate heat sink
Fire Barrier
Coatings
Emergency Lighting
Earthquake
Fuel cladding
Overspeed trip
ML14010A31030 December 2013Final Safety Analysis Report, Amendment 62, Chapter 14 - Initial Test ProgramShutdown Margin
High Radiation Area
Stroke time
Hydrostatic
Emergency Lighting
Feedwater Heater
Power change
Overspeed trip
ML14010A30130 December 2013Final Safety Analysis Report, Amendment 62, Chapter 6 - Engineered Safety FeaturesReactor Vessel Water Level
Loop seal
Fire Barrier
Stroke time
Safe Shutdown Earthquake
Hydrostatic
Coatings
Squib
Emergency Lighting
Tornado Generated Missile
Local Leak Rate Testing
Stress corrosion cracking
Integrated leak rate test
Earthquake
Power-Operated Valves
Fuel cladding
Coast down
GOTHIC
Power Uprate
Potassium iodide
ML14010A31130 December 2013Final Safety Analysis Report, Amendment 62, Chapter 15 - Accident AnalysesSafe Shutdown
Shutdown Margin
Reactor Vessel Water Level
Stroke time
Anticipated operational occurrence
Abnormal operational transient
Feedwater Heater
Feedwater Controller Failure
Rod Drop Event
Fuel cladding
Power change
GOTHIC
Power Uprate
Failure to Scram
Overspeed trip
Loss of condenser vacuum
ML14010A31330 December 2013Final Safety Analysis Report, Amendment 62, Chapter 17 - Quality AssuranceNondestructive Examination
Process Control Program
GO2-13-174, Final Safety Analysis Report, Amendment 62, Appendix J - Shielding Evaluation Report30 December 2013Final Safety Analysis Report, Amendment 62, Appendix J - Shielding Evaluation ReportSafe Shutdown
Power Uprate
ML14010A30030 December 2013Final Safety Analysis Report, Amendment 62, Chapter 5 - Reactor Coolant System and Connected SystemsSafe Shutdown
Reactor Vessel Water Level
Grab sample
Anticipated operational occurrence
Safe Shutdown Earthquake
Weld Overlay
Hydrostatic
Operating Basis Earthquake
Nondestructive Examination
Abnormal operational transient
Intergranular Stress Corrosion Cracking
Stress corrosion cracking
Earthquake
Pressure Boundary Leakage
Scaffolding
Coast down
Unidentified leakage
Power Uprate
Overspeed trip
Thermal fatigue
Water hammer
ML14010A29630 December 2013Final Safety Analysis Report, Amendment 62, Chapter 3 - Design Criteria - Structures, Components, Equipment, and Systems, Page 3.6-1 Through Page 3.6-101Safe Shutdown
High Energy Line Break
Tornado Generated Missile
Earthquake
Power Uprate
ML14010A29730 December 2013Final Safety Analysis Report, Amendment 62, Chapter 3 - Design Criteria - Structures, Components, Equipment, and Systems, - Figure 3.6-21 Through Figure 3.12-4Safe Shutdown
Ultimate heat sink
Stroke time
Anticipated operational occurrence
Safe Shutdown Earthquake
Hydrostatic
Coatings
Operating Basis Earthquake
Finite Element Analysis
Tornado Generated Missile
Abnormal operational transient
Local Leak Rate Testing
Design basis earthquake
Feedwater Heater
Scram Discharge Volume
Earthquake
Liquid penetrant
Power Uprate
ML14010A31630 December 2013Final Safety Analysis Report, Amendment 62, Appendix F - Fire Protection EvaluationHot Short
Safe Shutdown
Reactor Vessel Water Level
High Radiation Area
Ultimate heat sink
Fire Barrier
Anticipated operational occurrence
Safe Shutdown Earthquake
Hydrostatic
Coatings
Operating Basis Earthquake
Operator Manual Action
Emergency Lighting
High Energy Line Break
Feedwater Heater
Intergranular Stress Corrosion Cracking
Excess Flow Check Valve
Earthquake
Fire Protection Program
Fire Watch
Early Warning Fire Detection
Scaffolding
Overspeed trip
Manual Operator Action
Water hammer
ML14010A29930 December 2013Final Safety Analysis Report, Amendment 62, Chapter 4 - ReactorShutdown Margin
Anticipated operational occurrence
Safe Shutdown Earthquake
Hydrostatic
Nondestructive Examination
Finite Element Analysis
Scram Discharge Volume
Stress corrosion cracking
Fuel cladding
Power change
Power Uprate
Water rod
ML14010A30630 December 2013Final Safety Analysis Report, Amendment 62, Chapter 11 - Radioactive Waste ManagementLoop seal
Mission time
Grab sample
Offsite Dose Calculation Manual
Anticipated operational occurrence
Safe Shutdown Earthquake
Hydrostatic
Annual Radioactive Effluent Release Report
Feedwater Heater
Process Control Program
Earthquake
Fuel cladding
Loss of condenser vacuum
ML14010A31530 December 2013Final Safety Analysis Report, Amendment 62, Appendix B - Response to Regulatory Issues Resulting from TMI-2Reactor Vessel Water Level
Grab sample
Anticipated operational occurrence
Temporary Modification
Fuel cladding
Loss of condenser vacuum
ML14010A29430 December 2013Final Safety Analysis Report, Amendment 62, Chapter 2 - Site CharacteristicsSafe Shutdown
High winds
Ultimate heat sink
Offsite Dose Calculation Manual
Hydrostatic
Met Tower
Incorporated by reference
Design basis earthquake
Intergranular Stress Corrosion Cracking
ML14010A31430 December 2013Final Safety Analysis Report, Amendment 62, Appendix a - Supplement Aging Management Programs and Activities Credited for Columbia License RenewalFire Barrier
Safe Shutdown Earthquake
Hydrostatic
Coatings
Operating Basis Earthquake
High Energy Line Break
Aging Management
Flow Accelerated Corrosion
Intergranular Stress Corrosion Cracking
Stress corrosion cracking
License Renewal
Earthquake
Fire Protection Program
Flow Induced Vibration
Power Uprate
Thermography
ML14010A29030 December 2013Columbia, 10 CFR 50.71 Maintenance of Records Licensing Basis Document Update
ML14010A29130 December 2013Final Safety Analysis Report, Amendment 62, General Table of ContentsSafe Shutdown
Incorporated by reference
Aging Management
License Renewal
ML14010A29830 December 2013Final Safety Analysis Report, Amendment 62, Appendix 3A - Plant Design Assessment Report for Safety/Relief Valves and Loss-of-Coolant Accident LoadsSafe Shutdown
Safe Shutdown Earthquake
Hydrostatic
Operating Basis Earthquake
Earthquake
Power Uprate
Subsequent actuation
ML14010A29530 December 2013Final Safety Analysis Report, Amendment 62, Chapter 3 - Design Criteria - Structures, Components, Equipment, and Systems, Table of Contents Through 3.5-46Safe Shutdown
High winds
Ultimate heat sink
Anticipated operational occurrence
Safe Shutdown Earthquake
Internal Flooding
Hydrostatic
Coatings
Operating Basis Earthquake
Tornado Generated Missile
Abnormal operational transient
Tornado Missile Protection
Scram Discharge Volume
Stress corrosion cracking
Integrated leak rate test
Earthquake
Turbine Missile
Fuel cladding
Liquid penetrant
Through-Wall Leak
Power change
Unidentified leakage
Overspeed trip
ML14010A30530 December 2013Final Safety Analysis Report, Amendment 62, Chapter 10 - Steam and Power Conversion SystemSafe Shutdown
High Radiation Area
Ultimate heat sink
Grab sample
Stroke time
Tornado Missile
Hydrostatic
Feedwater Heater
Stress corrosion cracking
Earthquake
Turbine Missile
Overspeed trip
Loss of condenser vacuum
Control Room Habitability
ML14010A31730 December 2013Final Safety Analysis Report, Amendment 62, Appendix I - Licensing Review Group IssuesSafe Shutdown
Fire Barrier
Safe Shutdown Earthquake
Operating Basis Earthquake
Feedwater Heater
Scram Discharge Volume
Stress corrosion cracking
Exemption Request
Earthquake
Fuel cladding
Water rod
ML14010A31230 December 2013Final Safety Analysis Report, Amendment 62, Chapter 16 - Technical Specifications
ML14010A30730 December 2013Final Safety Analysis Report, Amendment 62, Chapter 12 - Radiation Protection, Table of Contents Through 12.3-27Loop seal
High Radiation Area
Grab sample
Anticipated operational occurrence
Feedwater Heater
ML14010A30430 December 2013Final Safety Analysis Report, Amendment 62, Chapter 9 - Auxiliary SystemsSafe Shutdown
Shutdown Margin
Reactor Vessel Water Level
Loop seal
High Radiation Area
Ultimate heat sink
Non-Destructive Examination
Grab sample
Tornado Missile
Safe Shutdown Earthquake
Hydrostatic
Squib
Emergency Lighting
Tornado-Generated Missile
Double blade guide
Design basis earthquake
Feedwater Heater
Earthquake
Control of Heavy Loads
Liquid penetrant
Recently irradiated fuel
Unidentified leakage
Overexposure
Water rod
IR 05000397/201301024 December 2013IR 05000397-13-010; on 07/22/13 - 11/21/13; Columbia Generating Station; Special Inspection Into the Discovery of Multiple Degraded Conditions on the Division 1 Critical Switchgear Air Handling UnitTime of Discovery
Past operability
Probabilistic Risk Assessment
Functionality Assessment
Condition Adverse to Quality
Missed surveillance
Significance Determination Process
Operability Determination
Maintenance Rule Program
IR 07200035/201340123 December 2013IR 07200035-13-401, 11/21/2013, Columbia Generating Station - Cover Letter
ML13325A89123 December 2013Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Flooding WalkdownsUnanalyzed Condition
ML13357A32221 December 2013Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Columbia Generating Station, TAC No.: MF0796Safe Shutdown
High winds
Reactor Vessel Water Level
Ultimate heat sink
Safe Shutdown Earthquake
Internal Flooding
Operating Basis Earthquake
Emergency Lighting
Incorporated by reference
FLEX
Tornado Generated Missile
Fukushima Dai-Ichi
Containment Hardened Vent
Frazil ice
Battery sizing
B.5.b Mitigating Strategies
Earthquake
Commercial Grade
Hardened vent
GOTHIC
Water hammer
IR 05000397/201340419 December 2013IR 05000397-13-404, 11/21/2013, Columbia Generating Station - Cover LetterAffidavit
ML13353A71419 December 2013IR 05000397-13-404, 11/21/2013, Columbia Generating Station - Cover LetterAffidavit
GO2-13-171, Guarantee of Payment of Deferred Premium17 December 2013Guarantee of Payment of Deferred Premium
ML13351A10217 December 2013Notification of Generic Fundamentals Examinations for 2014Generic Fundamentals Examination
ML14087A16412 December 2013Cooling Water Intake Screen NMFS Consultation No. (I/NWR/2011/05286)
ML14091A21812 December 2013Cooling Water Intake Screen NMFS Consultation No. (I/NWR/2011/05286)
ML13345A20511 December 2013NRR E-mail Capture - Letter Dated 10/31/13, Seismic Hazards at Columbia Generating Station
ML13309A08011 December 2013Memorandum to File: Transcript for 10 CFR 2.206 Petition from Beyond Nuclear (Et Al) Regarding General Electric Mark I and Mark II Boiling-Water Reactors
TAC:MF117611 December 2013
ML13345A00210 December 2013Closure of Investigation (OI 4-2012-025)
IR 05000397/20134059 December 2013NRC Material Control and Accounting Program Inspection Report 05000397/2013405 (Cover Letter Only)Affidavit
ML13340A3825 December 2013Part 21 Reportable Condition Notification: Failure of Relay Logic Card Modules in 2 Out of 4 VotersAffidavit
ML13339B1455 December 2013Meeting Summary for Public Meeting with Energy Northwest Regarding Columbia Generating Station
TAC:MF010927 November 2013
GO2-13-157, Response to Request for Additional Information Regarding Seismic Walkdown Summary27 November 2013Response to Request for Additional Information Regarding Seismic Walkdown SummaryFukushima Dai-Ichi
Seismic Walkdown Report