 Issue dateTitleTopic
ML18068A34529 April 1998Rev 9 to EI-9, Offsite Radiological Monitoring.
ML18068A34428 April 1998Rev 3 to EI-6.6, Gamma E Determination.
ML18065B22721 April 1998Reactor Vessel Neutron Fluence Methodology.
ML18065B20210 March 1998Rev 7 to Relocated TS Per GL 89-09.Grab sample
Offsite Dose Calculation Manual
Annual Radiological Environmental Operating Report
Process Control Program
Power change
ML20197G38517 December 1997Rev 17 to Palisades Nuclear Plant Suitability,Training & Qualification PlanContraband
ML18065B23224 October 1997Rev 5 to Procedure HP 10.10, Palisades Radiological Environ Program Sample Collection & Shipment.Grab sample
Annual Radiological Environmental Operating Report
ML18067A51511 February 1997Rev 5 to Health Physics Procedure HP 10.10, Palisades Radiological Environ Program Sample Collection & Shipment.Grab sample
Annual Radiological Environmental Operating Report
ML18065B20124 December 1996Rev 11 to Offsite Dose Calculation Manual.Grab sample
Offsite Dose Calculation Manual
ML18065B08627 November 1996Corrected Pages 14 & 15 to Rev 18 to EM-09-02, Inservice Testing Program Relief Request Valve Relief Request 20.Stroke time
ML20134P40719 November 1996Suitability,Training & Qualification Plan, Rev 16
ML20137G38729 October 1996Rev 6 to Relocated TS Per NRC GL 89-09Grab sample
Offsite Dose Calculation Manual
Annual Radiological Environmental Operating Report
Process Control Program
Power change
ML18065A76610 June 1996Expired Temporary Change O-96-044 to Rev 17 to SOP-17A, Clean Radwaste Sys.
ML18065A76510 June 1996Cancelled Tcn O-96-045 to Rev 17 to SOP-17B, Dirty Radwaste Sys.
ML18065A80221 February 1996Rev 2 to EM-09-13, ISI Pressure Testing Program.Boric Acid
Hydrostatic
VT-2
Zebra Mussel
Biofouling
Liquid penetrant
Through-Wall Leak
Scaffolding
ML20137G36316 February 1996Rev 10 to Offsite Dose Calculation ManualGrab sample
Offsite Dose Calculation Manual
ML20137G35815 February 1996Rev 6 to CPC Pnp Process Control ProgramBoric Acid
Offsite Dose Calculation Manual
Process Control Program
ML18064A81429 June 1995Procedure EOF App B, INPO Emergency Response Assistance Agreement, Dtd 950426
ML20100H26218 June 1995Rev 2 to Reactor Vessel Exam Program Plan Interval 2,Period 3 & Interval 3,Period 1
ML18064A88816 March 1995Rev 0 to Palisades Nuclear Power Plant Third Interval ISI Program for Class 1,2 & 3 Components & Supports, Vols I & II
ML18064A6303 March 1995Rev 7 to App H, Emergency Planning EOF Training Matrix.
ML18064A63427 February 1995Project Plan,Alloy 600,Palisades Nuclear Plant, Rev 1,dtd 950227
ML20072K77415 July 1994Rev 0 to Palisades Performance Enhancement PlanStroke time
Temporary Modification
Systematic Assessment of Licensee Performance
Grace period
ML20072K7646 July 1994Rev 1 to Palisades Plant Restart Plan from 1994 Forced OutageTemporary Modification
ML18059B0483 June 1994Attachment 4 to Procedure EM-09-13,Rev 1, ISI Pressure Testing Program Procedure.Hydrostatic
ML20069D30824 May 1994Suitability,Training & Qualification Plan
ML20069G25120 May 1994Rev 30 to Procedure MO-7A-2, Emergency Diesel Generator 1-2 (K-6B)Power change
ML20069G23920 May 1994Rev 30 to Procedure MO-7A-1, Emergency Diesel Generator 1-1 (K-6A)Power change
ML20064E4836 March 1994ASME Section XI Repair Program, 0054-00101-001-100,rev 0Weld Overlay
Nondestructive Examination
ML20064E5014 March 1994Procedure for Application & Exam of Weld Overlay Repairs to Austenitic Stainless Steel Piping Systems, 0054-00101-001-101,rev 0Weld Overlay
Nondestructive Examination
Liquid penetrant
Scaffolding
ML18059A69823 February 1994Reactor Vessel Integrity Project Plan.
ML18059A68815 February 1994Editorial Changes to Rev 6 to Emergency Implementing Procedure EI-6.13, Protective Action Recommendations for Offsite Populations.
ML18059B02031 December 1993Methods of Alleviating Adverse Consequences of Fluctuating Water Levels in Great Lakes - St Lawrence River Basin, Rept to Govts of Canada & Us,Dtd 931231
ML18059A55419 November 1993Rev 4 to Attachment 3 to Procedure REC-1, Recovery Plan Format.
ML18059A47827 October 1993Rev 5 to Administrative Procedure 9.11, Engineering Analysis.Boric Acid
Hydrostatic
Nondestructive Examination
VT-2
Foreign Material Exclusion
Code Reconciliation
Liquid penetrant
Pressure boundary leak
Scaffolding
ML18059A4237 October 1993Rev 0 to Palisades Plant Pressurizer Safe End Crack Repair Action Plan.Nondestructive Examination
ML20059A51830 September 1993Public Version of Rev 36 to General Ofc Emergency Planning Procedure,App G, Emergency Telephone Numbers. W/931019 Release Memo
ML18058B78715 December 1992Rev 3 to HP 10.10, Palisades Radiological Environ Program Sample Collection & Shipment.Grab sample
Annual Radiological Environmental Operating Report
ML18058B03411 May 1992Rev 6 to Odcm.Grab sample
Offsite Dose Calculation Manual
ML18058A4337 May 1992Rev 5 to General Ofc Emergency Planning Procedure EOF-4, Communication Support Team, Page 3,reflecting Editorial Changes
ML20090A34027 February 1992Rev 5 to ODCM
ML18058A14627 January 1992Rev 45 to General Office Emergency Planning Gort/Eof Procedures Index
ML18058A1479 December 1991Rev 5 to General Ofc Emergency Planning Procedure EOF-3, Emergency Operations Facility Administrator. Approval Summary EnclFitness for Duty
ML18058A1449 December 1991Rev 5 to General Ofc Emergency Planning Procedure EOF-4, Communication Support Team. Approval Summary Encl
ML18058A1459 December 1991Rev 6 to General Ofc Emergency Planning Procedure EOF-2, Emergency Operations Facility Director. Approval Summary Encl
ML20091S2369 December 1991Rev 8 to General Ofc Emergency Planning Procedure GEN-3, On-Shift Sys Power Controller. Approval Summary Encl
ML18058A1429 December 1991Rev 7 General Office Emergency Planning Procedure GORT-1, General Office Response Team (Gort). Approval Summary Encl
ML18058A1439 December 1991Rev 10 to General Ofc Emergency Planning Procedure GEN-1, Overview. Approval Summary EnclFitness for Duty
ML18057B32817 October 1991Rev 2 to Procedure EI-15.2, Quarterly Communications Test Telephone Number,Verifications.
ML20086T28116 September 1991Rev 0 to Functional Description FC-888,covering Replacement of All Four Channels of Reactor Protection Sys Power Supply Assemblies,Trip Unit Assemblies,Interconnection Modules, Bistable Trip Units & Auxiliary Trip Units
ML18057B02210 May 1991Rev 15 to EM-09-04, Inservice Testing of Selected Safety- Related Pumps, Reflecting Complete Rewrite of Procedure to Omit Vertical Lines