DD-99-12, Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 991028 | 28 October 1999 | Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 991028 | |
ML20217N390 | 25 October 1999 | Advises That Info Provided in & Affidavit Re Holtec Position Paper WS-115,rev 1,repts HI-87113, Rev 0,HI-87114,rev 0,HI-87102 Rev 0 & HI-87112,rev 0,marked Proprietary,Will Be Withheld from Public Disclosure | |
ML20217L859 | 21 October 1999 | Discusses 990921 Request for Approval to Perform Alternative Testing as Part of Vermont Yankee Nuclear Power Station IST Program.Informs That Submittal Reviewed Against ASME Code Section XI Requirements & Forwards Safety Evaluation | |
ML20217M118 | 19 October 1999 | Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates | |
ML20217K316 | 19 October 1999 | Forwards Amend 195 to License DPR-61 & Safety Evaluation. Amend Deletes Certain TSs Either No Longer Applicable to Permanently Shutdown & Defueled State of Reactor or Duplicate Regulatory Requirements | |
ML20217G949 | 14 October 1999 | Forwards Exemption from Requirements of 1-CFR50,App E, Section IV.F.2.c,re Conduct of full-participation Exercise in Sept 1999,at Plant,Units 1,2 & 3 | Exemption Request |
ML20217D395 | 13 October 1999 | Forwards Request for Addl Info Re Util 990806 Submittal on USI A-46, Implementation Methodology Used at Pilgrim Nuclear Power Station, Per GL 87-02 | Safe Shutdown Safe Shutdown Earthquake |
ML20217D971 | 13 October 1999 | Responds to Request That Information Titled Addl Info Re Cycle Specific SLMCPR for Vermont Yankee Cycle 21 Be Withheld from Public Disclosure.Determined Info to Be Proprietary & Will Be Withheld from Public Disclosure | |
ML20217D967 | 12 October 1999 | Forwards Copy of Transcript of Public Meeting Held by NRC Staff & NNECO on 990825 at Waterford,Connecticut on Decommissioning Program for Millstone,Unit 1.Without Encl | |
ML20217E158 | 8 October 1999 | Forwards Insp Rept 50-293/99-05 on 990726-0905.Three Violations Noted & Being Treated as Ncvs.Violations Include Failure to Assure That Design Bases Correctly Translated Into Specifications | High Radiation Area |
DD-99-11, Informs That Time Provided by NRC Regulation within Which Commission May Act to Review Director'S Decision (DD-99-11) Expired & That Commission Declined Any Review.Decision Became Final Action on 991004 | 8 October 1999 | Informs That Time Provided by NRC Regulation within Which Commission May Act to Review Director'S Decision (DD-99-11) Expired & That Commission Declined Any Review.Decision Became Final Action on 991004 | |
ML20217C105 | 8 October 1999 | Forwards Amend 153 to License DPR-3 & Safety Evaluation. Amend Revises TS Section 6.0,Administrative Controls,By Deleting TS Sections 6.2.2.f Which Contains Limits on Working Hours of Plant Staff | |
ML20217D301 | 7 October 1999 | Forwards Request for Addl Info Re Util 990118 Request for Amend to License NPF-49 to Allow full-core Offloads to Spent Fuel Pool During Core Offloads to Spent Fuel Pool During Core Offload Events | |
ML20217C150 | 7 October 1999 | Forwards Insp Rept 50-271/99-11 on 990809-27.No Violations Noted.Insp Focused on Effectiveness of Engineering Functions in Providing for Safe Operation of Plant | Operability Determination |
ML20212J789 | 4 October 1999 | Informs That Licensee 980804,0628,29 & 990921 Responses to GL 98-01, Y2K Readiness of Computer Sys at NPPs Acceptable.Nrc Consider Subj GL to Be Closed for Plant | |
ML20217B471 | 4 October 1999 | Informs That Staff Did Not Identify Any Safety Concerns Re Licensee Proposals to Modify Commitments Made for Action Items 4.2.1,4.2.2,4.5.1 & 4.5.2 of GL 83-28 by Providing Addl Justifications or Safety Bases for Changes | |
ML20212L126 | 4 October 1999 | Forwards Viewgraphs Presented by Licensee at 990923 Meeting with Nrc,In Response to Request | |
ML20212J223 | 1 October 1999 | Forwards Copy of Environ Assessment & Fonsi Re 990317 Application for Amend to Revise TS Section 6.0 by Deleting TS Section 6.2.2.f Which Contains Limits on Working Hours of Plant Staff | |
ML20212J245 | 1 October 1999 | Informs That Util 980807 & 990629 Responses to GL 98-01, Y2K Readiness of Computer Sys at NPPs Acceptable.Nrc Considers Subj GL to Be Closed for Units 2 &3 | |
ML20212J305 | 1 October 1999 | Discusses GL 97-06 Re Degradation of SG Internals,Dtd 971230.GL Requested Each PWR Licensee to Submit Info That Will Enable NRC Staff to Verify Whether PWR SG Internals Comply & Conform to Current Licensing Basis for Facilities | |
ML20212J999 | 1 October 1999 | Responds to Recent Ltr to President Clinton,H Clinton, Chairman Jackson &/Or Wd Travers Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performance of Plant to Ensure That Public Health & Safety Adequately Protected | |
ML20212K124 | 1 October 1999 | Responds to Recent Ltrs to Chairman Jackson,Commissioners & Wd Travers,Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performace of Millstone to Ensure That Public Health & Safety,Adequately Protected | |
ML20212L183 | 1 October 1999 | Responds to Recent Ltr to Wd Travers Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Performance of Millstone to Ensure Adequate Protection to Public Health | |
ML20212L197 | 1 October 1999 | Responds to Recent Ltr to Chairman Jackson & Commissioners Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance to Ensure Public Health & Safety | |
ML20212L208 | 1 October 1999 | Responds to Recent Ltrs to President Wj Clinton,Chairman Jackson & Commissioners & Wd Travers,Expressing Concerns Re Millstone NPPs & Continued Lack of Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance | |
ML20212L217 | 1 October 1999 | Responds to Recent Ltr to President Wj Clinton,Chairman Jackson & Commissioners,Wd Travers & Ferc,Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island | |
ML20212J662 | 30 September 1999 | Informs of Completion of mid-cycle PPR of Units 2 & 3 on 990916.Identified Several Recent Instances in Which Condition Repts Were Not Initiated,Resulting in Untimely or Inadequate C/As.Historical Listing of Plant Issues Encl | |
ML20212J650 | 30 September 1999 | Informs of Completion of mid-cycle PPR of VYNPS on 990913. No New Areas Identified in Which Licensee Performance Warranted Addl Insp Beyond Core Insp Program.Historical Listing of Plant Issues & Insp Plan Through Mar 2000 Encl | |
ML20217A927 | 30 September 1999 | Discusses Investigation Conducted at Millstone Nuclear Power Station by NRC OI Region I on 980319 to Determine If Contract Training Instructor Was Terminated for Raising Concerns About Quality of Training Matls | |
ML20217B322 | 30 September 1999 | Refers to Investigation Rept 1-1997-035 Conducted at Millstone Nuclear Power Station by NRC Ofc of Investigation Field Ofc,Region I on 970915 to Determine Whether Former Health Physics Technician Discriminated Against | |
ML20212J830 | 30 September 1999 | Informs of Completion of mid-cycle PPR of Pilgrim Nuclear Power Station.Staff Conducts Reviews for All Operating NPPs to Integrate Performance Info & to Plan Insp Activities at Facility Over Next Six Months | Main transformer failure |
ML20216J134 | 28 September 1999 | Ltr Contract:Task Order 49, Millstone Units 2 & 3 Employee Concerns Program Insp, Under Contract NRC-03-98-021 | |
ML20212F787 | 24 September 1999 | Advises That Util 990121 Application for Amend Being Treated as Withdrawn.Proposed Changes Would Have Modified Facility UFSAR Pertaining to Values for post-accident Containment Pressure Credited in Pilgrim Net Positive Head Analyses | |
ML20212F432 | 24 September 1999 | Responds to 990921 e-mail to E Poteat,Requesting Waiver of Late Charges of Listed Amount for Annual Fee Invoice AR0431-99.Request Denied Because 10CFR15.37 Does Not Provide for Waiver Based on Info Provided in e-mail | |
ML20212D034 | 20 September 1999 | Expresses Appreciation for Accepting NRC Request for Tour of Haddam Neck Facility During on 991014.Invites R Mellor to Participate in NRC 1999 Decommissioninng Power Reactor Work- Shop:Nrc Insp Program at Decommissioning Power Reactors | |
ML20212F252 | 20 September 1999 | Confirms That NMSS Has Received 990916 Submittal & Will Be Included as Attachment to Commission Paper Along with State of Maine Submittal | |
ML20212F136 | 20 September 1999 | Confirms That NMSS Has Received 990916 Submittal & Will Be Included as Attachment to Commission Paper Along with State of Maine Submittal | |
ML20212E461 | 20 September 1999 | Responds to Concerning Possible Involvement in Weekly Telephone Calls NRC Staff Has with Maine Yankee Staff | |
ML20212F496 | 20 September 1999 | Forwards Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations of NRC Requirements Occurred & Being Treated as Ncvs,Consistent with App C of Enforcement Policy | |
ML20212C162 | 17 September 1999 | Forwards Amend 175 to License DPR-28 & Safety Evaluation. Amend Revises TSs to Enhance Limiting Conditions for Operation & Surveillance Requirements Relating to Standby Liquid Control System | |
ML20212C286 | 16 September 1999 | Forwards SER Accepting Licensee 981123 Request for Relief RR-E1,RR-E5,RR-E6 Pursuant to 10CFR50.55a(a)(3)(i) & Request for Relief RR-E2,RR-E3 & RR-E4 Pursuant to 10CFR50.55a(a)(3)(ii) | |
ML20216F317 | 13 September 1999 | Forwards Insp Rept 50-271/99-06 on 990621-0801.One Violation Identified & Being Treated as Noncited Violation | |
ML20212A901 | 10 September 1999 | Forwards Environ Assessment & Finding of No Significant Impact Re Application for Exemption,Dtd 990803.Proposed Exemption Would Provide Relief from Requirement of 10CFR50 | Exemption Request |
ML20212A317 | 10 September 1999 | Discusses Investigation Rept 1-1998-045 Conducted on 981112 to Determine If Former Senior Health Physics Technician Being Denied Employment at Millstone in Retaliation for Having Raised Safety Concerns in Past.Synopsis Encl | |
ML20212A750 | 10 September 1999 | Forwards Staff Requirements Memo Response,Dtd 990525,which Provides Actions NRC Plans for Continued Oversight of safety-conscious Work Environ & Employee Concerns Program | |
ML20212A591 | 8 September 1999 | Responds to 990816 e-mail & 990901 Telcon with Respect to Comments Re Decommissioning of Maine Yankee Site.Concerns Raised with Respect to Status of Fuel at Maine Yankee Have Been Raised in Previous Ltrs to Us NRC | |
ML20211K517 | 2 September 1999 | Expresses Appreciation for Support Provided for NRC Public Meeting on 990825 | |
ML20211H074 | 30 August 1999 | Discusses GL 92-01,Rev 1, Rv Structural Integrity, Issued by NRC on 950519 & NNECO Responses for Millstone Unit 2 & 980715.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 Based on Response Review | |
ML20211M937 | 30 August 1999 | Addresses Two Issues Raised in s to Senator Collins & Governor a King That Relate to Construction of ISFSI at Maine Yankee | |
ML20212B218 | 30 August 1999 | Responds to Re 990707 Message from N Allen Re Transportation Incident Involving Shipment from Maine Yankee Nuclear Power Plant |