ML20059N31228 September 1990Advises That 881021 Amend 20 to Facility Security Plan Consistent w/10CFR50.54(p) & Acceptable
ML20059N30327 September 1990Ack Receipt of Util Transmitting Rev 8 to Security Training & Qualification Plan.Plan Withheld (Ref 10CFR2.790(d))
ML20058L21926 July 1990Ack Receipt of 880808 & s Forwarding Amends 19 & 25 to Security Plan.Amends Consistent w/10CFR50.54(p) & Acceptable
IR 05000528/19900255 July 1990Forwards Insp Repts 50-528/90-25,50-529/90-25 & 50-530/90-25 on 900516-18 & 0614-15.Violations Noted.Enforcement Conference Scheduled for 900710 to Discuss Results of Insp. Unreliable Performance of Emergency Lighting Sys NotedEmergency Lighting
ML20059M83013 June 1990Forwards NRC Performance Indicators for First Quarter 1990. W/O Encl
ML20055C39226 February 1990Approves Util 900214 Request for Use of B&W Steam Generator Plugs W/Alloy 690 as Alternative to Alloy 600.Alternate Matl Is nickel-base Alloy (ASME Designation SB-166)
IR 05000528/198903229 September 1989Forwards Security Insp Repts 50-528/89-32,50-529/89-32 & 50-530/89-32 on 890807-11 & Notices of Violation & Deviation.Program Weaknesses Re Security Officer Overtime & Behavioral Observation Program Noted.Encls Withheld
ML20248G88020 September 1989Forwards Insp Repts 50-528/89-12,50-529/89-12 & 50-530/89-12 on 890130-0811.Deficiencies Noted
ML20248G87120 September 1989Forwards Insp Repts 50-528/89-37,50-529/89-37 & 50-530/89-37 on 890807-25.No Violations or Deviations Noted
ML20248G97320 September 1989Forwards Unexecuted Amend 13 to Indemnity Agreement B-69, Reflecting Increase in Primary Layer of Nuclear Energy Liability Insurance Provided by ANI & Maelu
ML20247H64112 September 1989Advises That 890816 Revisions to ATWS Mitigation Sys Acceptable W/Requirements of 10CFR50.62(c)(1)
ML20247K22311 September 1989Forwards Amends 123 & 41 to Licenses DPR-61 & NPF-49, Respectively & Safety Evaluation.Amends Change Tech Specs 4.10.1.D.1.h & 4.4.5.4.a.8 to Allow Insp of Steam Generator Tubes by Insertion of Ultrasonic Test Probe
ML20247E3377 September 1989Forwards Amends 122,34,143 & 40 to Licenses DPR-61,DPR-21, DPR-65 & NPF-49,respectively & Safety Evaluation.Amends Change Tech Spec Sections 6.10.2.m & 6.10.3 Re Records Retention for Radiological Effluent Monitoring & ODCMOffsite Dose Calculation Manual
Process Control Program
ML20246Q01231 August 1989Forwards Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations Noted
IR 05000029/198901431 August 1989Forwards Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations Noted
ML20246C39415 August 1989Forwards Safeguards Insp Repts 50-272/89-19,50-311/89-17 & 50-354/89-15 on 890710-14.No Violations Noted
ML20246C82111 August 1989Confirms 890808 Telcon Re Util Participation in NRC Regulatory Impact Survey on 891023 in Berlin,Ct.Schedule & General Discussion Groups Shown in Encl
ML20248D6924 August 1989Advises That Rev 6b to Generating Stations Emergency Plan Transmitted by Util 890710 Form Acceptable & Does Not Decrease Effectiveness of PlanNuclear Accident Reporting System
ML20248C0563 August 1989Forwards Sser Accepting 880601,0909 & 890602 Changes to ATWS Mitigation Sys Actuation Circuitry for Plants.Nrc Requested to Be Notified Upon Completion of Human Factors Review
ML20245H5332 August 1989Advises That 890519 Changes to QA Program Described in CPC-2A Acceptable.Issues Addressed Listed
ML20247H68925 July 1989Requests Proposed Design Change to Containment Hydrogen Monitoring Sys,W/Schedule for Implementing Change or Justification for Existing Configuration
ML20246A29529 June 1989Forwards Request for Addl Info Re NRC Bulletin 88-008, Thermal Stresses in Piping Connected to Rcs
ML20246L22126 June 1989Forwards Amends 118,33,142 & 36 to Licenses DPR-61,DPR-21, DPR-65 & NPF-49,respectively & Safety Evaluation.Amends Revise Tech Specs by Removing Tech Spec Figures 6.2-1 & 6.2-2 Re Organizations Functional Requirements
ML20245J22423 June 1989Corrected Ltr Forwarding Amend 18 to License NPF-74 & Safety Evaluation.Amend Incorporates Cycle 2 Changes in Tech SpecsSafe Shutdown
Shutdown Margin
Anticipated operational occurrence
Fuel cladding
ML20245J33022 June 1989Provides Background Info on Regulatory Analysis Supplementing NRC Proposed Backfit,Per 890413 Request.Util Expected to Provide Schedule for Implementation of Required ImprovementsBackfit
IR 05000528/198902020 June 1989Forwards Security Insp Repts 50-528/89-20,50-529/89-20 & 50-530/89-20 on 890518-0613.No Violations Noted.Major Areas Inspected:Activities Re Physical Protection.Rept Withheld (Ref 10CFR2.790(d))
ML20245F26916 June 1989Forwards SER Accepting Licensee 850612 Response to Generic Ltr 83-28,Item 4.5.3 Re Trip Reliability & on-line Functional Testing of Trip Sys
ML20245H14915 June 1989Submits Correction/Clarificaton to Util 890508 Response to Generic Ltr 88-14, Instrument Air Supply Sys Problems Affecting Safety-Related Equipment. Program on Critical Air Demand Equipment Is in Addition to Investigations Performed
ML20245B17315 June 1989Ack Receipt of Rev 55 to QA Topical Rept CE-1-A.Program Satisfies Requirements of 10CFR50,App B & Acceptable
ML20245A21012 June 1989Ack Receipt of 890519 & 23 Ltrs Informing NRC of Steps Taken to Correct Violations Noted in 890424 Insp.Corrective Actions Will Be Reviewed During Future Physical Security Insp
ML20244C2949 June 1989Advises Tht Util 890329 Request for Approval to Use Fuses for Electrical Isolation of non-Class 1E Dc Power Sys Acceptable Provided That Circuit Breaker in Parallel to Two Fuses Locked Open
ML20244C5091 June 1989Advises That Bunker Ramo Penetration Assemblies Environmentally Qualified to Perform Intended Functions for Plants,Per 890224 Rept & .Concerns Expressed in Re Byron Unit 2 Satisfied
ML20248C26731 May 1989Forwards Insp Repts 50-321/88-37,50-366/88-37 & 50-424/88-53 on 881102-890106 & Notice of Violation.Notice of Violation Withheld (Ref 10CFR2.790(d) & 73.21)
ML20247M77326 May 1989Forwards Director'S Decision Re Ohio Citizens for Responsible Energy 10CFR2.206 Petition Re 880309 Power Oscillation Event at Lasalle,Unit 2
ML20247H40822 May 1989Advises That 880315,0829 & 890517,Revs 6,7 & 7A,respectively to Security Training & Qualification Plan Acceptable
ML20247H35119 May 1989Advises That Licensee Response to Generic Ltr 82-33 Re post-accident Monitoring Instrumentation,Per Rev 3 to Reg Guide 1.97,acceptable,except for Four Items Listed in Technical Evaluation Rept
ML20247J78019 May 1989Informs of Implementation Schedule for Item 1.b of NRC Bulletin 88-011, Pressurizer Surge Line Thermal Stratification, Mutually Agreed Upon Between NRC & Westinghouse During 890411 Meeting
ML20247C15218 May 1989Informs of Implementation Schedule for Item 1.b of NRC Bulletin 88-011, Pressurizer Surge Line Thermal Stratification. Understands That Westinghouse Will Provide Util W/Generic Bounding Analysis Re Seismic Loadings
ML20247G52418 May 1989Responds to Re Util Position on Dealing W/Dc Grounds After Discussion W/Nrc in 890301 Meeting.Continued Plant Operation Will Be Allowed Only So Long as Applicable Limiting Conditions/Or Action Statements Met
ML20247B24117 May 1989Comments on Expeditious Actions & Notice of Audit on Generic Ltr 88-17 Re Potential Loss of Dhr.Requests Addl Info Re Training Packages,Administrative Controls for Containment Closure & RCS Level Indications
ML20246Q15116 May 1989Informs of Implementation Schedule for Item 1.b of NRC Bulletin 88-011, Pressurizer Surge Line Thermal Stratification, Per 890411 Meeting W/Westinghouse Owners Group.Proposed Schedule for Analysis Must Be Accelerated
ML20246P81415 May 1989Requests Addl Info Re 881130 Application for Amends to Licenses Per Generic Ltr 87-09.Affirmation Should Be Provided That Procedures,Mgt Directives & Onsite Reviews Limit Use of Spec 3.0.4 Exceptions
ML20246L27411 May 1989Forwards Anl Draft Rept Re Main Steam Line Breaks in Plants Ice Condenser,Per Util 880613,0907 & 1012 Ltrs & WCAP-10988 & WCAP-10986P,for Review & Comments within 60 Days.W/O Encl
ML20247G82810 May 1989Advises That 890206 Amend 18,Rev 1 to Security Plan Consistent W/Provisions of 10CFR50.54(p) & Acceptable
ML20246Q0738 May 1989Forwards Revised Tech Spec Page B 3/4 4-2,clarifying Operability Requirements for PORVs in Manual or Automatic Mode,In Response to Util 881212 Request
ML20247A7783 May 1989Extends Invitation to Power Reactor Operator Licensing Seminar on 890531 in King of Prussia,Pa.Meeting Agenda Encl
ML20247A5943 May 1989Extends Invitation to Power Reactor Operator Licensing Seminar on 890531 in King of Prussia,Pa.Meeting Agenda Encl
ML20246Q3713 May 1989Extends Invitation to Attend Power Reactor Operator Licensing Seminar on 890531 in King of Prussia,Pa.Agenda & Info Re Lodging Arrangements Encl
ML20245L32228 April 1989Ack Receipt of 881223 Submittal of Rev 8 of QA Topical Rept CPC-2A Re Transfer of QA Assigned Functions to Other Plant Organizations & Continuing QA Organizations Program Control. Topical Rept Acceptable & Meets 10CFR50,App B
ML20245J06225 April 1989Forwards Amends 114,30,141 & 33 to Licenses DPR-61,DPR-21, DPR-65 & NPF-49,respectively & Safety Evaluation.Amends Modify Tech Specs of Four Units to Be Consistent W/Plant Restart Provision in 10CFR50.36 If Safety Limit Exceeded