Issue date | Title | Topic | |
---|---|---|---|
ML20217A797 | 6 October 1999 | Forwards NRC Approved Operator Licensing Exam (Facility Outline & Initial Exam Submittal & as-given Operating Exam) for Tests Administered During Week of 990607 | Job Performance Measure |
ML20210G971 | 16 June 1999 | Informs That on June 9,two Occurrences of Hydrogen Burns Took Place at Palisades During VSC-24 Loading Activities | Boric Acid |
ML20210G961 | 14 June 1999 | Informs That Sfpo Not Sure of Having Lead for Palisades Events Being Handled by Region III Insp | |
ML20210G941 | 11 June 1999 | Informs That on 990610 Palisades 1 Notfied NRC That on 990609,minor Hydrogen Burns Occurred During Welding of Structural Lid on Sf Storage Cask | |
ML20210G936 | 10 June 1999 | Informs That Attachment Has Been Reviewed & Approved in DNMS Re Palisades Pn | Boric Acid |
ML20210G887 | 10 June 1999 | Forwards Draft Pn Region Iii,Concerning Latest Hydrogen Burn at Palisades | |
ML20210G909 | 10 June 1999 | Requests That Cio Make Copy of Pn to Be Sent to M Sinclair in Midland,Mi | Boric Acid |
ML20196F528 | 25 November 1998 | Notification of 981207 Meeting with Util in Rockville,Md to Discuss Licensees Efforts to Ensure Continued Compliance with 10CFR50.61,pressurized Thermal Shock Rule | |
ML20236N521 | 20 April 1998 | Informs That Weld Team Will Be at Palisades Conducting Insp of VSC-24 Owners Group UT Effort During Wk of 980420 | |
ML20236K930 | 26 March 1998 | Forwards Status on VSC-24 Weld Issues for Info Purposes. Future Events & Dates Subject to Change.Provides Outline of Internal Plan to Complete CAL Items.Requests Maintaining Guide as Internal Planning Guide | |
ML20236M192 | 23 February 1998 | Informs That VSC-24 Owners Group Wants to Postpone Insp of UT Exam Procedure for VSC-24 Closure Welds by 2 Weeks to Week of 980316 Due to Unsuccessful Paint Job on mock-up | |
ML20236N420 | 30 January 1998 | Forwards NMSS Items of Interest for Wk Ending 980130.Items Include Meeting W/Ge on 980121,insp at Amersham on 980122-23,US EPA Meeting on 980122 to Discuss Groundwater C/A Program at Church Rock & Visit to Flawtech on 980122 | Nondestructive Examination Exemption Request |
ML20236N482 | 28 January 1998 | Informs That Flawtech Has Been Inserting Flaws in Palisades VSC-24 Mockup & That Palisades (R Humphrey) Will Perform UT Exam & Receipt Insp at Flawtech on 980202.Flawtech Will Ship Mockup to ANO on 980203 | |
ML20236N503 | 26 January 1998 | Forwards Item of Interest Re Flawtech Methods for Inserting Flaws Into Metallic Component Specimens.Flawtech Currently Under Contract to Consumers Energy to Implant Flaws Into Palisades VSC-24 Dry Fuel Storage mock-up | |
ML20138J767 | 5 February 1997 | Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licenseing Exam on 970409. Ltr W/Copy to Chief,Operator Licensing Branch Must Be Submitted to Listed Address in Order to Register Personnel | Generic Fundamentals Examination |
ML20133P421 | 21 January 1997 | Notification of 970129 Meeting W/State of Mi & FEMA in Rockville,Md to Discuss Potential Alternative Approaches to Management of Dose Assessment for Protective Action Decision Making W/Respect to Emergency Planning | |
ML20132F496 | 20 December 1996 | Notification of 970109 Meeting W/Listed Attendess in Rockville,Md to Discuss Potential Alternative Approaches to Mgt of Dose Assessment for Protective Action Decision Making W/Respect to Emergency Planning | |
ML20138G365 | 5 November 1996 | Requests That Listed Info Be Forwarded to Licensee in Connection W/Unescorted Access Visits to Plant by Listed NRC Contractor Employees During 961118-970110 for Purpose of Assisting NRC in Conduct of Design Insp.Partially Deleted | |
ML20128G575 | 3 October 1996 | Forwards Ltr to Be Sent to Licensees of Six Pressurized Water Reactor Plants That Have Used Fuel Mfg by Siemens Power Corp Since 1986.Licensees Requested to Verify Compliance of 10CFR50.46 W/Regulations | Backfit |
ML20134B792 | 24 June 1996 | Discusses Results of Audit Review of Changes to Siemens Large Break ECCS Evaluation Model | |
ML20058N481 | 15 December 1993 | Informs of Decision to Expand Senior Mgt Oversight of Selected Plants,Per Recent Meeting W/J Martin & H Miller. Lists Assignment of Managers,Effective Immediately | |
ML20056E457 | 5 August 1993 | Forwards Technical Review Rept Re, Tardy Licensee Actions Initiated Because of Delayed Replacement of Batteries in Uninterruptible Power Supplies at Plant | |
ML20127N564 | 25 January 1993 | Notification of 930127-28 Meeting W/Util in Rockville,Md to Discuss I&C TS Amend & Proposed analog-to-digital Conversion at Plant | |
ML20248E548 | 29 September 1989 | Forwards AEOD/T919, Failure of Overcurrent Protective Device at Palisades Unit 1. Expresses Desire to Investigate All Future Class IE Devices Failures in-depth | |
ML20128C633 | 13 December 1988 | Discusses Licensee 10CFR21 Rept Re Substitution of Geuine Parts in Masoneilan Valves Supplied by S-C Controls to Various Nuclear Power Plants | |
ML20127L502 | 9 November 1988 | Summary of 881028 Meeting by Util at Plant Re Nonconforming Parts Received from Sample-Webtrol for Masoneilan Valve. Meeting Brought Together Parties Involved & Discussed Possible Causes of Problem | |
IA-92-253, Informs of 880408 Fitness for Duty Program Allegation Re Individual Being Hired at Plant W/Prior Drug Use Problem | 12 August 1988 | Informs of 880408 Fitness for Duty Program Allegation Re Individual Being Hired at Plant W/Prior Drug Use Problem | Fitness for Duty |
ML20125B785 | 12 August 1988 | Informs of 880408 Fitness for Duty Program Allegation Re Individual Being Hired at Plant W/Prior Drug Use Problem | Fitness for Duty |
ML20125B781 | 9 August 1988 | Provides Listed Info as Required by Section 3.2 of RP 0517A Re Allegation AMS RIII-88-A-0105 Concerning Use of Drugs by Employees Working Midnight Shift at Plant | Fitness for Duty |
IA-92-271, Provides Listed Info as Required by Section 3.2 of RP 0517A Re Allegation AMS RIII-88-A-0105 Concerning Use of Drugs by Employees Working Midnight Shift at Plant | 9 August 1988 | Provides Listed Info as Required by Section 3.2 of RP 0517A Re Allegation AMS RIII-88-A-0105 Concerning Use of Drugs by Employees Working Midnight Shift at Plant | Fitness for Duty |
ML20125B746 | 3 August 1988 | Discusses Allegation Re Drug Use by Night Shift Employees at Plant.Informs That Allegation Will Continue to Be Carried as Open in Allegation Mgt Sys Pending Final Resolution/ Closeout by Division | |
ML20125B743 | 1 August 1988 | Discusses Allegation Received on 880729 Re Drug Use at Plant | |
ML20155G743 | 7 June 1988 | Forwards F Miraglia 880527 Memo for Review & Requests Proposed Priorities for Actions on Project Manager Rept by C.O.B. 880609 | |
ML20154Q166 | 27 May 1988 | Discusses Updating Project Managers Rept (Pmr) in Accordance W/New Priority Ranking Sys.Mods Have Been Made So That Pmr Will Now Accept New Priority Data.Old Priority Data Will Be Deleted During Wk of 880530.Sample Data Format Encl | |
ML20148A757 | 14 March 1988 | Forwards Project Directorate III-1 Slides for 880317 Briefing of Executive Team.Slides Marked P Primary Slides Directorate Plans to Show.Other Slides Backup for Possible Ref | |
IA-88-165, Discusses Topics for Senior Mgt Meeting & Submits Partial Listing of Facilities Where Vendor Support Has Been Problem,Vendor Involved & Component/Issue of Interest. W/Copyrighted Matl | 9 March 1988 | Discusses Topics for Senior Mgt Meeting & Submits Partial Listing of Facilities Where Vendor Support Has Been Problem,Vendor Involved & Component/Issue of Interest. W/Copyrighted Matl | Stroke time |
ML20155K200 | 9 March 1988 | Discusses Topics for Senior Mgt Meeting & Submits Partial Listing of Facilities Where Vendor Support Has Been Problem,Vendor Involved & Component/Issue of Interest. W/Copyrighted Matl | Stroke time |
ML20236L666 | 9 November 1987 | Forwards Rev 1 to NUS-1721, App I Analysis,Crystal River Nuclear Unit & NUS-1729, App I Analysis,Palisades Plant, for Placement in Document Control Sys.Record Copy | |
ML20151C762 | 15 October 1987 | Forwards FBI Communication to Be Disseminated Only to NRC Employees W/Need to Know.W/O FBI Communication.Records of 860610,0926,1212,870404 & 0929 Telcons & Region III Repts of 860610,870318 & 0929 Events Encl | |
ML20147F504 | 25 February 1987 | Forwards Comments on Licensee Training Performance During Period of INPO Accreditation Effort.Certification of Licensed Operator Training Program Encl | |
ML20154A283 | 13 December 1986 | Forwards Assessments by Enforcement Staff of Regional Performance in Enforcement Area from Jul-Nov 1985 | Liquid penetrant |
ML20214K602 | 24 November 1986 | Forwards Tentative Itinerary for 861201 Visit to Facility by Commissioner Carr | |
ML20214C475 | 17 November 1986 | Notifies of Rescheduling of SALP 7 Assessment Period.Period Extended Until 870131 Due to Extended Outage.Author 861106 Memo,Requesting SALP 7 Inputs,Should Be Disregarded | |
ML20214C686 | 17 November 1986 | Forwards List of Missing SALP Evaluation Forms (0516B). Requests Review of Files to Locate Missing Forms.Recognizing That RP 0516B Issued in Mar 1986,request Applies Only to Repts Issued After Mar 1986 | |
ML20207A077 | 15 October 1986 | Forwards Request for Addl Info Re ATWS Rule,To Be Transmitted to Licensee.Response Requested by 861201 in Order to Meet Target Completion Date for SER Input of 861231 | |
ML20215G136 | 14 October 1986 | Summary of 861006 Operating Reactor Events Meeting 86-35 Re Events Since Last Meeting on 860929.Assignees Should Review Identified Responsibilities & Completion Dates & Advise If Dates Cannot Be Met.Attendance List & Viewgraphs Encl | Safe Shutdown Ultimate heat sink Fire Watch |
ML20209H027 | 10 September 1986 | Requests That Electrical Insp Be Performed at Facility to Review 860826 Failure of Power Supply Breaker to Vital Bus 1-E to Close Upon Demand.Response to Listed Questions Also Requested | |
ML20203H274 | 28 July 1986 | Forwards,For Review,Latest Update of SALP Ratings | |
ML20236X673 | 16 June 1986 | Forwards NRC plant-specific Backfit Regulatory Analysis,Per NRC Manual Chapter 0514,covering Actions in Encl 860521 Confirmatory Action Ltr Re 860519 Reactor Trip.Info from 860508 Backfitting Workshop in King of Prussia,Pa Encl | Anticipated operational occurrence Backfit |
ML20199C641 | 13 June 1986 | Forwards Itinerary for Commissioner Zech 860623 & 24 Visit to Facilities |