Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML18152B357 | 22 October 1999 | Requests Relief from Temporary Repair of Through Wall Leak Discovered on 30 Inch Component Cooling Heat Exchanger Discharge Pipe Associated with Service Water Sys Common to Surry Units 1 & 2 | Design basis earthquake Through Wall Leak |
ML20217H581 | 15 October 1999 | Forwards 1999 Update to FSAR, for McGuire Nuclear Station.With Instructions,List of Effective Pages for Tables & List of Effective Pages for Figures | Safe Shutdown Tornado Missile Safe Shutdown Earthquake Coatings Tornado Generated Missile Design basis earthquake Battery sizing Earthquake Turbine Missile Fuel cladding Overspeed trip |
ML18152B358 | 14 October 1999 | Submits Response to Violations Noted in Insp Repts 50-280/98-201 & 50-281/98-201.Corrective Actions:Visual Insps Were Completed on Accessible Coatings Inside Containment for Both Units 1 & 2 | Coatings |
ML20217K283 | 14 October 1999 | Submits Response to NRC Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates, for Fiscal Yrs 2000 & 2001 | |
ML20217G786 | 13 October 1999 | Forwards MOR for Sept 1999 & Revised MOR for Aug 1999 for McGuire Nuclear Station,Unit 1 & 2 | |
ML20217F359 | 13 October 1999 | Forwards Info Copy of Cycle 14 COLR for McGuire Nuclear Station,Unit 1 | |
ML20217F326 | 13 October 1999 | Submits Quantity of Tubes Insp from Either Side of SGs A-D & Lists Tubes with Imperfections,Locations & Size.No Tubes Removed from Svc by Plugging.Total of Eleven Tubing Wear Indications Identified at Secondary Side Supports in SGs | |
ML18152B354 | 12 October 1999 | Requests Use of Code Case N-532 & N-619,per Provisions of 10CFR50.55a(a)(3).Detailed Info Supporting Request,Encl. Attachment 2 Includes Technical White Paper That Provides Further Technical Info | VT-2 |
ML20217H321 | 8 October 1999 | Forwards Changed Pages for Issue 5,rev 1 of Nine Mile Point Station Physical Security & Safeguards Contingency Plan,Iaw 10CFR50.54(p).Without Encls | |
ML20217J509 | 6 October 1999 | Forwards Revs to Section 16.15-4.8.1.1.2.g of McGuire Selected Licensee Commitments Manual.Section Has Been Revised to Allow Testing of Portions of DG Fuel Oil Sys Every 10 Yrs | VT-2 |
ML20217C835 | 5 October 1999 | Communicates Correction to Info Provided During 990917 Meeting with Duke Energy & NRC Region Ii.Occupational Radiation Safety Performance Indicator Values Should Have Been Presented as 1 Instead of 0 | |
ML18040A370 | 30 September 1999 | Provides Changes to Application for Amend Re Volumes 1-11 of 981016 Submittal & Discard & Insertion Instructions Re Integration of Proposed Changes,In Response to NRC RAIs | Post Accident Monitoring Scram Discharge Volume Fuel cladding |
ML20216J931 | 30 September 1999 | Forwards Response to NRC 981119 Suppl RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions | Hydrostatic |
ML18152B340 | 27 September 1999 | Requests That Ma Walker Be Removed from List of Individuals Scheduled to Take Exam IAW Guidance Provided in NUREG-1021, Operator Licensing Exam Stds for Power Reactors | Generic Fundamentals Examination |
ML18152B339 | 27 September 1999 | Forwards Revised Relief Request IWE-3,which Now Includes Addl Visual Exam Requirement After post-repair or Mod Pressure Testing Is Completed,Per Telcon with NRC | Nondestructive Examination VT-2 |
ML20212E980 | 23 September 1999 | Submits Info in Response to Request for Estimated Initial Operator Licensing Exam Needs,Per Administrative Ltr 99-03 | Generic Fundamentals Examination |
ML18152B338 | 21 September 1999 | Forwards in Triplicate,Applications for Renewal of License for Bf Jurewicz & JW Heide.Without Encls | |
ML18152B667 | 17 September 1999 | Forwards Two NRC Forms 536,containing Info on Proposed Site Specific Operator Licensing Exam Schedules & Estimated Number of Applicants Planning to Take Exams And/Or Gfes,In Response to NRC Administrative Ltr 99-03 | Generic Fundamentals Examination |
ML18152B333 | 17 September 1999 | Forwards Revised 180-day Response to NRC GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves. | Grace period |
ML20216F710 | 17 September 1999 | Forwards Response to NRC 990806 RAI Re USI A-46,verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors.Nrc Is Informed That Actions Required for Resolution of USI A-46 Have Been Completed | |
ML18152B334 | 16 September 1999 | Requests Relief from Specific Requirements of Subsection IWE of 1992 Edition with 1992 Addenda of ASME Section XI Re Containment Liner Examination Requirements,For North Anna & Surry Power Stations | Nondestructive Examination VT-2 |
ML20212D532 | 15 September 1999 | Informs That Duke Energy Corp Agrees to Restrict Max Fuel Rod Average Burnup to 60,000 Mwd/Mtu,In Order to Support NRC Final Approval & Issuance of Requested Amend | |
ML20216E879 | 14 September 1999 | Forwards Monthly Operating Repts for Aug 1999 & Revised Monthly Operating Rept for July 1999 for McGuire Nuclear Station | |
ML18152B452 | 14 September 1999 | Forwards Comments on Review of Preliminary Accident Sequence Precursor Analysis of Operational Event That Occurred at Plant,On 980508,as Reported in LER 98-009 | |
ML20212D898 | 14 September 1999 | Forwards ISI Summary Rept for Refueling Outage 15 & Flaw Indication Repts.Supporting Info Repts & Calculations, Encl | |
ML20212B258 | 10 September 1999 | Requests That Name of Bm Bordenick Be Removed from Nine Mile Point,Units 1 & 2 Service List | |
ML20211P577 | 10 September 1999 | Forwards Application for Amends to Licenses DPR-63 & NPF-69, to Transfer Licenses to Amergen Energy Co,Llc.Ts Pages & Proprietary Addendum,Included.Proprietary Encl Withheld | |
ML20212A263 | 9 September 1999 | Forwards Rev 25 to McGuire Nuclear Station,Units 1 & 2 Pump & Valve Inservice Testing Program, IAW 10CFR50.55a. Section 8.0 Contains Summary of Changes & Detailed Description of Changes Associated with Rev 25 | |
ML20212A519 | 8 September 1999 | Requests NRC Approval for Relief from Requirements of ASME Boiler & Pressure Vessel Code,Section XI,1989 Edition,App VI,VI-2430(c) & 2440(b).Approval of 99-GO-002 Is Requested by 000301 | |
ML18152B450 | 8 September 1999 | Submits in Triplicate,Application for Renewal of License for Rd Scherer,Iaw 10CFR55.57.Requests That Certification of Medical Exam by Facility Licensee,Nrc Form 396,be Withheld from Public Disclosure,Per 10CFR2.790(a)(6) | |
ML20212A134 | 7 September 1999 | Forwards Summary Rept Secondary Containment Leakage Testing, Dtd June 1999 for Nine Mile Point,Unit 1,IAW TS 6.9.3.f | |
ML18152B447 | 1 September 1999 | Requests That NRC Remove Listed Labels from Distribution | |
ML20211K814 | 1 September 1999 | Forwards Reactor Containment Bldg Ilrt,Iaw Plant TS 6.9.3.e.Testing Confirmed That TS 3.3.3/4.3.3 & 6.16 Primary Containment Leakage Requirements Were Satisfactorily Met | |
ML20211L922 | 1 September 1999 | Confirms That Licensee Will Retain Weld 32-WD-050 as IGSCC Category F Until Completion of Reinspection Program,In Response to NRC | |
ML20211J646 | 30 August 1999 | Forwards Response to NRC 990625 RAI Re NMPC Responses to GL 92-01,rev 1,supplement 1, Reactor Vessel Structural Integrity | |
ML20211K300 | 30 August 1999 | Forwards Semi-Annual Radioactive Effluent Release Rept for 990101-990630 & Revised ODCM, for Nine Mile Point,Unit 1. Format Used for Effluent Data Is Outlined in App B of Regulatory Guide 1.21,rev 1 | Offsite Dose Calculation Manual Process Control Program |
ML20211H174 | 30 August 1999 | Forwards Comments on Catawba Nuclear Station Units 1 & 2 & McGuire Nuclear Station,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid.Ltr Dtd 990107,rept ATI-98-012-T005 & Partial marked-up Rept WCAP-14995 Encl | |
ML20211M445 | 30 August 1999 | Forwards Summary of Util Conclusions Re Outstanding Compliance Issue Re Staff Interpretation of TS SR 3.0.1,per Insp Repts 50-369/99-03 & 50-370/99-03,as Discussed with NRC During 990618 Meeting | Enforcement Discretion Temporary Modification Operability Determination Backfit |
ML18152B371 | 27 August 1999 | Forwards LER 99-005-00,per Plant TS Table 3.7.6.Rept Has Been Reviewed by Station Nuclear Safety & Operating Committee.Commitment Made by Util,Listed | |
ML20211H192 | 26 August 1999 | Forwards Application for Amend to License DPR-63,supporting Implementation of Noble Metal Chemical Addition by Raising Reactor Water Conductivity Limits in TSs 3.2.3.a,3.2.3.c.1 & 3.2.3.b | |
ML18152B385 | 23 August 1999 | Forwards Revised TS Basis Pages for TS 3.1.B,deleting Reactor Vessel Toughness Data Duplicated in Ufsar.Ref to Applicable UFSAR Section Included in TS Basis | |
ML18152B368 | 20 August 1999 | Submits 30-day Rept Re Two Instances in Which Conditions of Approval in Coc Were Not Observed in Making Shipment.Two Type B Shipments Using Model CNS 8-120B Package Were Made After Expiration of QA Program Approval Between 990531-0628 | |
ML18152B366 | 20 August 1999 | Provides Medical Status Rept for E Washington,As Required by License Conditions.Summary of E Washington Current Physical Exam & Pertinent Lab Data Attached.Encl Withheld,Per 10CFR2.790(a)(6) | |
ML18152B365 | 20 August 1999 | Requests Removal of License Condition from Sh Wightman Operator License SOP-21538.Updated NRC Form 396 Is Encl.Form NRC 396 Withheld,Per 10CFR2.790(a)(6) | |
ML20211D773 | 20 August 1999 | Forwards Semiannual FFD Program Performance Data Rept Covering Period 990101 Through 990630 | Fitness for Duty |
ML18152B380 | 18 August 1999 | Forwards Technical Rept NE-1206,Rev 0, Surry Unit 2,Cycle 16 Startup Physics Tests Rept, Summarizing Results of Physics Testing Program Performed After Initial Criticality on 990525 | |
ML20211B937 | 18 August 1999 | Provides Addl Info Re Application of Method a at Nmp,Unit 1 as Described in Generic Implementation Procedure,Rev 2 (GIP-2),NRC Supplemental SER 2 & Documents Ref in GIP-2 Upon Which GIP-2 Is Based | Safe Shutdown Safe Shutdown Earthquake Earthquake Backfit |
ML20211F297 | 17 August 1999 | Forwards non-proprietary & Proprietary Updated Pages for DPC-NE-2009,submitted 980722.Pages Modify Fuel Design & thermal-hydraulic Analysis Sections of DPC-NE-2009. Proprietary Page 2-4 Withheld,Per 10CFR2.790 | Affidavit |
ML20211B112 | 16 August 1999 | Forwards Topical Rept DPC-NE-2012, Dynamic Rod Worth Measurement Using Casmo/Simulate, Describing Results of Six Drwm Benchmark Cycles at Catawba & McGuire & Discusses Qualification to Use Drwm at Catawba & McGuire | |
ML18040A369 | 16 August 1999 | Forwards Response to NRC 990510 RAI Pertaining to NMP Application for Amend Re Conversion of NMPNS Unit 2 Current TS to Its.Nrc Requested Info Re Several Sections,Including Section 3.6, Containment Sys. | High Radiation Area Post Accident Monitoring Hydrostatic |