ML18039A90215 October 1999Forwards LER 99-010-00 Re Occurrence of Plant Reactor Scram Due to Main Turbine Trip Which Resulted in Main Steam Moisture Separator.All Plant Safety Systems Operated as Designed in Response to Event
ML18039A89614 October 1999Forwards LER 99-009-00,re Manual Reactor Scram on Unit 2 from 54% Power,Iaw 10CFR50.73(a)(2)(iv).All Plant Safety Sys Operated as Designed in Response to Event
ML20217G74014 October 1999Forwards MOR for Sept 1999 for Cooper Nuclear Station. Rept Includes Documentation of Challenges to Safety/Relief Valves,Iaw TS 5.6.4
ML18039A8888 October 1999Provides Licensee Supplemental Response to NRC 980713 RAI Re GL 87-02,Suppl 1, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors.Safe Shutdown
Safe Shutdown Earthquake
Earthquake
ML18039A8938 October 1999Forwards LER 99-008-00,concerning HPCI Sys Being Declared Inoperable,Iaw 10CFR50.73(a)(2)(v).There Are No Commitments Contained in Ltr
ML20217B5481 October 1999Requests Exception to 10CFR50.4(c) Requirement to Provide Total of Twelve Paper Copies When Submitting Revs to BFN UFSAR
ML20212F77522 September 1999Requests Operator & Senior Operator License Renewals for Listed Individuals and Licenses
ML20216J80620 September 1999Forwards Rev 37 to Safeguards Plan,Iaw Provisions of 10CFR50.(p).Rev Withheld,Per 10CFR73.21
ML20212C49215 September 1999Forwards Monthly Operating Rept for Aug 1999 for Cooper Nuclear Station.Rept Includes Operating Data Rept,Unit SD Rept & Documentation of Challenges to Safety/Relief Valves
ML18039A87210 September 1999Informs of Licensee Decision to Withdraw Proposed Plant risk-informed Inservice Insp Program,Originally Transmitted in Util 981023 Ltr.Licensee Expects to Resubmit Revised Program within Approx 6 Wks
ML20211Q5739 September 1999Submits Response to Administrative Ltr 99-03 Re Preparation & Scheduling of Operator Licensing Exams.Completed NRC Form 536,operator Licensing Exam Data,Which Provides Plant Current Schedules for Specific Info Requested EnclGeneric Fundamentals Examination
ML20211N5272 September 1999Responds to NRC 990823 RAI Re Y2K Readiness at Cooper Nuclear Station,Per GL 98-01,Suppl 1
05000298/LER-1999-006, Forwards LER 99-006-00 for Cns.Commitments Made by Util Encl26 August 1999Forwards LER 99-006-00 for Cns.Commitments Made by Util Encl
ML20211F13124 August 1999Forwards Rev 1 to Calculation Nedc 97-044, NPSH Margins for RHR & CS Pumps, in Support of 990615 Proposed Amend to DPR-46 Re Containment Overpressure Contribution to ECCS Pumps NPSH Requirements
05000298/LER-1999-003, Informs That Commitment Re Insp Rept 50-298/98-15 & LER 99-003,to Bound Extent of Condition & Take Appropriate C/As Is Now Complete.Addl Time Is Required to Accommodate Training of Engineering Support Personnel23 August 1999Informs That Commitment Re Insp Rept 50-298/98-15 & LER 99-003,to Bound Extent of Condition & Take Appropriate C/As Is Now Complete.Addl Time Is Required to Accommodate Training of Engineering Support PersonnelStroke time
Enforcement Discretion
ML20210R03012 August 1999Forwards Monthly Operating Rept for July 1999 for Cooper Nuclear Station,Iaw Guidance Provided by GL 97-02.Rept Also Includes Documentation of Challenges to Srvs,Per TS 5.6.4
ML20210P67610 August 1999Requests That Following Changes Be Made to Distribution on NRC Correspondence
ML20210Q6939 August 1999Forwards Updated Changes to Distribution Lists for Browns Ferry & Bellefonte Nuclear Plants
ML18039A8376 August 1999Forwards BFN Unit 2 Cycle 10 ASME Section XI NIS-1 & NIS-2 Data Repts, for NRC Review.Corrected Inservice Insp Summary Rept for Unit 3 Cycle 8 Operation,Included in ReptGrab sample
Hydrostatic
ML20210K6072 August 1999Submits Withdrawal of Proposed License Amend Re Secondary Containment Isolation Description & Refueling Accident Analysis Results
ML20210K3812 August 1999Forwards Listed Info,Which NPPD Believes Demonstrates Ability to Obtain Funds in Amount of $10 Million for Payment of Such Premiums within Specified Three Month Period,Iaw 10CFR140.21Incorporated by reference
Decommissioning Funding Plan
Power change
ML20210G51028 July 1999Forwards fitness-for-duty Program semi-annual Performance Rept for Period of 990101-0630,per Provisions of 10CFR26.71(d)Fitness for Duty
ML18039A81826 July 1999Forwards LER 99-004-00 Re Inoperability of Two Divisions of Plant CSS Due to Personnel Error During Surveillance Testing.Event Reported Per 10CFR50.73(a)(2)(i)(B)
ML20210F30322 July 1999Submits Rept Re Impact of Changes or Errors in Methodology Used to Demonstrate Compliance with ECCS Requirements of 10CFR50.46.One Reportable non-significant Error Was Found During Time Period of 980601-990630
ML20209B7851 July 1999Forwards Corrected Occupational Radiation Exposure Repts, for Cys 1996 & 1997.Util Stated That Repts Did Not Properly Tabulate Number of Personnel Receiving Exposures Less than 100 Mrem by Work & Job Functions in CY96 & CY97
05000298/LER-1999-005, Forwards LER 99-005-00 for Cns.Commitments Made by Util Encl1 July 1999Forwards LER 99-005-00 for Cns.Commitments Made by Util Encl
ML20209B54528 June 1999Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Disclosure Encl
05000298/LER-1999-004, Forwards LER 99-004-01.Commitments Made by Util Are Encl28 June 1999Forwards LER 99-004-01.Commitments Made by Util Are EnclCorrosion bonding
ML18039A80828 June 1999Forwards LER 99-004-00 Re Esfas That Occurred When RPS Motor Generator Tripped.Rept Is Submitted IAW Provisions of 10CFR50.73(a)(2)(iv) as Event of Condition That Resulted in Automatic Actuation of ESF
ML18039A81125 June 1999Requests Permanent Relief from Inservice Insp Requirements of 10CFR50.55a(g) for Volumetric Exam of Bfn,Unit 3 Circumferential RPV Welds,Per GL 98-05
ML20196H03324 June 1999Informs NRC of Deletion of 1991 Commitment Contained in Ltr Re Feedwater Nozzle Bypass Leakage Monitoring at Plant
ML20209A72223 June 1999Submits Revised Pages to Proposed Change to Plant TS Previously Submitted in ,Per 990615 Telcon with NRC
ML20196F53322 June 1999Forwards Examination Summary Rept for FW Nozzle Examinations Performed During 1998 Fall Refueling Outage at Cooper Nuclear Station.Rept Covers Past Examinations Up to & Including 1998 Fall Refueling Outage
ML18039A80522 June 1999Forwards LER 99-003-00,re Automatic Reactor Scram Due to Turbine Trip.Rept Numbered 99-001 Should Be Deleted & Replaced with Encl Rept as Result of Error Noted in 990614 Rept
ML20196F81322 June 1999Forwards Rev 24 to Security Personnel Training & Qualification Plan,Per 10CFR50.54(p).Rev Withheld
ML18039A80318 June 1999Responds to NRC Staff Verbal Request Re TS Change TS-376, Originally Submitted on 970312, & Proposed Changes to TS to Extend Current 7-day AOT for EDGs to 14 Days
ML20196B46817 June 1999Forwards TS Bases Changes Made at Plant Subsequent to Receipt of License Amend 178,dtd 980731,for Conversion to Its,Through 990610.List of Effective Pages for TS Bases, Encl
ML20195H88914 June 1999Forwards Response to NRC 990315 RAI Re GL 95-07, Pressure Locking & Thermal-Binding of SR Power-Operated Gate Valves, 180-day Response Submitted by District on 960213
ML20195E2358 June 1999Forwards Response to NRC 990517 RAI Re Util Proposed Change to TS Re Calibr Frequency of Reactor Recirculation Flow Transmitters Associated with APRM
ML18039A7931 June 1999Provides Summary of Major Activities Performed at BFN During Scheduled Unit 2 Cycle 10 Refueling Outage
ML20195D3321 June 1999Informs That Cb Fisher,License OP-5525-4,can No Longer Maintain License at Plant Because of Physical Condition That Causes Licensee to Fail to Meet Requirements of 10CFR55.21
ML18039A78924 May 1999Informs That Oscillation Power Range Monitor Module Has Been Enabled for Current Cycle of Operation Following Unit 2 Cycle 10 Refueling Outage Which Was Completed on 990509
ML18039A79124 May 1999Informs That by Meeting Test Criteria Established by Test Based on Ansi/Ans 3.5-1985 (License Amends 254 & 214) power- Uprate Simulation Acceptable for Operator Training
ML20195B93624 May 1999Informs That Do Elkins,License SOP-3392-6,no Longer Needs to Maintain License as Position Does Not Require License
ML20207A07019 May 1999Forwards Rev 3 to CNS Strategy for Achieving Engineering Excellence, Which Provides Effective Tool for Overall Engineering Work Mgt.Commitments Made by Util,Encl
ML20206R76017 May 1999Forwards Annual Radiological Environ Rept,Radiological Environ Monitoring Program,Jan-Dec 1998,per TS 5.6.2Annual Radiological Environmental Operating Report
ML20206U65514 May 1999Informs That ML Meek & Wd Dawson Will No Longer Need to Maintain SRO Licenses at Plant,Due to Termination of Employment,Effective 990521
ML20206P96813 May 1999Forwards Monthly Operating Rept for Apr 1999 for Cooper Nuclear Station.Rept Includes Documentation of Challenges to Safety/Relief Valves
ML20206Q84210 May 1999Forwards Medical Info on DM Olive,License SOP-20540-2,in Response to NRC 990428 Telcon.Encl Withheld from Public Disclosure IAW 10CFR2.790(a)(6)
ML18039A7776 May 1999Forwards LER 99-003-00,providing Details Re Plant HPCI Sys Being Declared Inoperable Due to Loose Electrical Connection.Ltr Contains No Commitments