ML20079P968 | 24 January 1984 | Forwards 840124 Telegram Appealing Dismissal of J E Abson Claim Against Hj Kaiser Co,Per Dept of Labor 840120 Ruling | |
ML20079K197 | 17 January 1984 | Forwards Natl Board of Boiler & Pressure Vessel Inspectors Interim Rept 18 Covering Natl Board Audit Team Activities at Facility for Dec 1983.Concurs W/Recommendations.Task NBT-4 Closed | |
ML20083D557 | 16 December 1983 | Forwards Natl Board of Boiler & Pressure Vessel Inspectors Interim Rept 17 for Nov 1983 Re Audit & Surveillance Activities at Facility.No Reportable Findings Identified | |
ML20083E511 | 16 December 1983 | Informs That Statement Re Issue of Safety at Plant, Inadvertly Taken in Wrong Context | |
ML20082T117 | 9 December 1983 | Requests Ltr of Intent Extending Expiration Date on Proposal for Independent Design Review to 840115.Award Cannot Be Made Until Util Meets W/Nrc to Discuss Results of Preliminary Review Expected to Be Completed by 831216 | |
ML20082T181 | 8 December 1983 | Requests Program Detailing How Util,Bechtel & Hjk Intend to Appoint New Constructor for Facility.Applicable ASME Code Paragraphs Should Be Identified | |
ML20082P810 | 30 November 1983 | Forwards Original Transcript of 831101 Hearing | |
ML20082F597 | 14 November 1983 | Forwards 831109 Nat Board Interim Rept 16 Re Audit & Surveillance Activities at Facility.Author Concurs W/Natl Board Audit Team Recommendations.Task NBT-4 Re Util Takeover of Partial Piping Sys Closed | |
ML20083A110 | 31 October 1983 | Forwards Rev 25 to Natl Board Tasks Rept | |
ML20078J572 | 7 October 1983 | Forwards Natl Board Interim Rept 15 Covering Audit Team Activities for Sept 1983 | |
ML20080R375 | 3 October 1983 | Forwards Rev 24 to Natl Board Tasks Rept. Rept Assembled for Tracking Progress on Concerns Raised by Natl Board Interim Repts 1 & 2,Suppls 2,3,5,7 & 13 | |
ML20078C381 | 19 September 1983 | Forwards Rev 23 to Natl Board Tasks Rept, Dtd 830916. Rept Assembled for Tracking Progress on Concerns Raised by Natl Board Interim Repts 1,2, Suppls 2,3,5,7 & 13.Executive Summary Highlights Changes Made Since Rev 22 | |
ML20078D451 | 12 September 1983 | Comments on Implementation of Recommended Independent Design Review.Design Verification Should Be Conducted in Parallel W/Verification of Const Quality | |
ML20080G367 | 30 August 1983 | Requests Clarification of Statements in Torrey Pines Technology Final Rept GA-C17173, Independent Review of Zimmer Project Mgt Re Recommendations on Independent Design Review | |
ML20078A571 | 29 August 1983 | Forwards Rev 21 to 830819 Natl Board Tasks Rept, Assembled for Tracking Progress on Concerns Raised by Suppls 2,3,5 & 7 to Natl Board Interim Repts 1 & 2. Executive Summary Attached to Highlight Changes Made Since 830805 Rev 20 Rept | |
ML20076J542 | 19 August 1983 | Forwards Aug 1983 Final Rept, Independent Review of Zimmer Project Mgt. W/O Encl | |
ML20077J482 | 11 August 1983 | Protests Cincinnati Environ Advisory Council Rejection of M Prather to Serve on Council.Prather Should Be Appointed or T Carpenter,Representing Miami Valley Power Project,Should Be Eliminated | |
ML20076A810 | 9 August 1983 | Forwards Biweekly Status Rept on Independent Review of Facility Project Mgt Covering Period 830716-29 | |
ML20076A988 | 8 August 1983 | Forwards Rev 20 to Natl Board Tasks Rept | |
ML20077H754 | 4 August 1983 | Discusses Telcon W/R Warnick of Region 3 Re Contents of Rept on Facility.Contents Will Be Discussed Following Release of Rept on 830812,per NRC Protocol Requirements | |
ML20077E336 | 22 July 1983 | Forwards Biweekly Status Rept 6 on Independent Review of Zimmer Project Mgt for 830702-15 | |
ML20076M693 | 13 July 1983 | Revises Re Bechtel Study Draft Rept on Mgt of Util.Bechtel Should Retain Rept & Arrange Meeting W/Torrey Pines Technology | |
ML20076M372 | 12 July 1983 | Forwards Biweekly Status Rept on Independent Review of Facility Project Mgt for 830618-0701 | |
ML20085B864 | 1 July 1983 | Requests Bechtel Study Draft Rept & Recent Util Proposals Developed for Consideration in Final Recommendation Re Independent Review of Facility Project Mgt,Per 830526 Meeting Agreement | |
ML20076J754 | 24 June 1983 | Forwards Biweekly Status Rept 4 on Independent Review of Project Mgt for 830604-17.Total of 7,252 Manhours Expended on Review | |
ML20072D277 | 10 June 1983 | Forwards Independent Review of Zimmer Project Mgt, Biweekly Status Rept 3,for 830521-0603 | |
ML20079R149 | 9 June 1983 | Submits 830606 Request for Documents Re Kaiser Engineers, Inc Qa/Qc Personnel | |
ML20071P125 | 31 May 1983 | Summarizes 830526 Meeting to Discuss Planned Changes to Initial Program Plan.Util Interfaces W/Reactor Control,Inc Should Be Added to Program Scope | |
ML20071P113 | 31 May 1983 | Forwards Biweekly Status Rept on Independent Review of Util Project Mgt Covering Period 830507-20 | |
ML20071L389 | 19 May 1983 | Responds to Re American Nuclear Insurers Activity at Facility.No ASME Code Work in Process Due to Stop Work Order.Hj Kaiser Continuing to Resolve Existing Nonconformances & Verification of Resolutions | |
ML20204G137 | 21 April 1983 | Forwards Advance Copy of Program Plan for Independent Review of Zimmer Project Mgt. Plan Will Be Discussed at 830425 Public Meeting in Cincinnati,Oh | |
ML20073J828 | 13 April 1983 | Forwards App a of Bechtel Corp 821108 Proposal Outlining Scope of Survey Activities in Preparation of Independent Mgt Review of Project | |
ML20073J922 | 12 April 1983 | Forwards NRC Transcript of 830328 Public Meeting in Cincinnati,Oh Re Util Selection of Torrey Pines Technology to Perform Mgt Assessment of Project.W/O Encl | |
ML20204G335 | 5 April 1983 | Responds to Questions Raised in NRC Re Contacts W/Bechtel on Zimmer Project.List of Bechtel Revenues to Ga Technologies Encl | |
ML20073A448 | 5 April 1983 | Responds to Questions Raised in Jg Keppler . Info Re Bechtel Revenues to Ga Co/Torrey Pines Technology Svcs Provided to Bechtel Encl | |
ML20073A528 | 5 April 1983 | Confirms That No Contractual Relationships Made Between Ga Co/Torrey Pines Technology & American Electric Power Co,Inc or Subsidiaries,Other than Commitment to Supply Nuclear Fuel | |
ML20073B980 | 4 April 1983 | Forwards Rev 11 to Natl Board Tasks Rept. Rept Tracks Progress on Concerns Raised by Natl Board Interim Repts 1 & 2,Suppls 2,3,5 & 7.W/o Stated Executive Summary | |
ML20073J116 | 31 March 1983 | Submits Listing of Initial Tasks Re Consulting Efforts Concerning Suspension of Facility Const.Addl Tasks & Recommendations May Be Suggested as Work Develops or New Areas Are Identified | |
ML20072P522 | 30 March 1983 | Advises That Listed Documentation Re FSAR Chapters 13,14 & 17 & Project Procedure & QA Procedure Manuals Required by Forwarded Under Separate Cover,Supplementing Util | |
ML20073B818 | 25 March 1983 | Forwards 830119 Project Organization Chart & Revs Dtd May & Dec 1978 & Apr 1981,per 830324 Telcon.Other Info Will Be Available During Site Visits.W/O Encl | |
ML20072Q096 | 23 March 1983 | Forwards Response to Inquiry Re Commitment to Supply Nuclear Fuel to American Electric Power Co.Contractual Commitments Complex & Only Indirectly Related.Commitments Have No Relationship to Project & Do Not Result in Net Revenues | |
ML20072H300 | 22 March 1983 | Forwards List of Initial Documents & Info Required in Anticipation That Torrey Pines Technology Will Be Confirmed as Independent Reviewer of Project Mgt.Nrc Advised of Request Via 830322 Telcon | |
ML20072Q247 | 22 March 1983 | Forwards Initial List of Documents/Info for Independent Review of Facility Project Mgt & QA Program | |
ML20072Q223 | 18 March 1983 | Forwards Response to NRC Request for Addl Info Re Proposal for Independent Review of Util Project Mgt.Scope of Work on Completed Independent Design & Const Reviews of San Onofre, Palo Verde,Shoreham & Waterford Encl | |
ML20081B765 | 29 December 1982 | Suppls in Response to Jg Keppler 821228 Request, Directed to Util,Re Bechtel Mgt Role.Soderholm Involvement Discussed | |
ML20081B760 | 23 November 1982 | Submits Revised Proposal for Providing Completion Svcs for Facility.Rev to Proposal,Originally Submitted on 821108, Responds to Commission 821122 Order to Show Cause.List of Independent Review Team Members Encl | |
ML20081B768 | 8 November 1982 | Forwards Description of Steps to Be Taken to Identify Necessary Organizational & Procedural Action,Resumes of Phase I Team Members,Summarizes of Bechtel Nuclear Experience & Contract Forms.Info Deleted | |
ML20050C086 | 1 August 1981 | FOIA Request for All Records Re Zimmer Nuclear Power Plant | |
ML20064E311 | 14 May 1981 | Confirms Info Received Re Investigation of Rejected Radiographs Supplied to Util at 810430 Meeting at Region 3 Ofc.Synopsis of Problem Discussed.Meeting W/Nrc Scheduled for 810518 Postponed.Related Info Encl | |
ML19346A184 | 28 April 1981 | Requests That Thorough Investigation Be Conducted Into Facility Const |