Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML20207M92312 March 1999Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results
ML18066A27713 August 1998Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency
LD-97-033, Part 21 Rept Re Defect in Potter & Brumfield Mdr Relays, Models 170-1 & 7032.Extended Problem to Include All Mdr Relay Models W/Date Codes 93XX-95XX.Root Cause Analysis, Written Rept & Recommended Corrective Actions Due by 97120120 November 1997Part 21 Rept Re Defect in Potter & Brumfield Mdr Relays, Models 170-1 & 7032.Extended Problem to Include All Mdr Relay Models W/Date Codes 93XX-95XX.Root Cause Analysis, Written Rept & Recommended Corrective Actions Due by 971201
LD-97-028, Part 21 Rept Re Contamination of Lubricant Which Has Led to Hardening of Lubricant in Certain Potter & Brumfield Mdr Relay Models 170-1 & 7032.Will Distribute Copy of Rept to Utils Having ABB-CE Designed Nuclear Steam Supply Sys13 October 1997Part 21 Rept Re Contamination of Lubricant Which Has Led to Hardening of Lubricant in Certain Potter & Brumfield Mdr Relay Models 170-1 & 7032.Will Distribute Copy of Rept to Utils Having ABB-CE Designed Nuclear Steam Supply Sys
LD-97-024, Part 21 Rept Re Error in Energy Redistribution Factor Used in LOCA Analysis for Listed Plants for Which ABB-CE Performed Analysis.Issued Recommendations Info Bulletin 97-00414 August 1997Part 21 Rept Re Error in Energy Redistribution Factor Used in LOCA Analysis for Listed Plants for Which ABB-CE Performed Analysis.Issued Recommendations Info Bulletin 97-004
ML20140A96629 May 1997Part 21 Rept Re Ksv Emergency Diesel Generator Power Piston Failure.Caused by Jacket Water in Combustion Chamber. Recommends That Users Verify That Crown Thickness at Valve Cutout Be 100 MinimumFinite Element Analysis
ML20210E35927 March 1997Part 21 Rept Re Sorrento Electronics Inc Has Determined Operation & Maint Manual May Not Adequately Define Requirements for Performing Periodic Surveillance of SR Applications.Caused by Hardware Failures.Revised RM-23A
ML20137G62625 March 1997Svcs Part 21 Rept Re Emergency Generators Installed at Zion Station Which Developed Significant Drop in Crankcase Lube Oil Level.Caused by Crack in Liner Wall,Allowing Jacket Water to Enter ChamberFinite Element Analysis
ML18065B01118 October 1996Part 21 Rept Re Application of Certain Aspects of ABB-CE Safety Analysis Methodology
ML20117G46414 May 1996Part 21 Rept Re Cooper Bessemer Reciprocating Products,Div of Cooper Cameron Corp,Issued Ltr to Define Utils/Plants Containing Similar Equipment as Supplied on Cooper Bessemer Ksv & Enterprise Dsr EDGs
LD-96-009, Part 21 Rept Re Potential Instrumentation Decalibr at Low Power.Affected Utils Should Ensure That Log Power Channels Properly Calibr & cross-correlated to Linear Power Channels at 100% Reactor Power15 April 1996Part 21 Rept Re Potential Instrumentation Decalibr at Low Power.Affected Utils Should Ensure That Log Power Channels Properly Calibr & cross-correlated to Linear Power Channels at 100% Reactor Power
ML20077D34329 November 1994Part 21 Rept Re Suspect Master Connecting Rods & Contains Info Location in Engine for Rods
ML20078G3059 November 1994Rev to Part 21 Rept Re Potential Problem W/Master Power Connecting Rods.Vendor Recommends Listed Utils Perform Visual Insp of Master Rods to Determine Applicability of Rept
ML20078C25919 October 1994Part 21 Rept Re Valtek Valves Addressed in NRC Part 21 Log Number 93-325,installed at South Texas Project.Valtek re-designed Trim to Meet All Requirements & Built Parts to Retrofit in Valves
LD-93-003, Part 21 Rept Re Defect in Potter & Brumfield Model 170-1 Relay.One of Two Rotor Return Springs Broke & Portion of Spring Lodged Between Rotor & Stator.Rotor Springs Supplied by Lewis Spring Co.Info Bulletin Being Prepared13 January 1993Part 21 Rept Re Defect in Potter & Brumfield Model 170-1 Relay.One of Two Rotor Return Springs Broke & Portion of Spring Lodged Between Rotor & Stator.Rotor Springs Supplied by Lewis Spring Co.Info Bulletin Being Prepared
ML20126J59631 December 1992Part 21 Rept Re Potential Loss of RHR Cooling During Nozzle Dam Removal.Nozzle Dams May Create Trapped Air Column Behind Cold Leg Nozzle Dam.Mod to Nozzle Dams Currently Underway. Ltrs to Affected Utils EnclHydrostatic
ML20125C7167 December 1992Part 21 Rept Re Possibility for Malfunction of Declutching Mechanisms in SMB/SB-000 & SMB/SB/SBD-00 Actuators. Malfunction Only Occurs During Seismic Event.Balanced Levers May Be Purchased from Vendor.List of Affected Utils EnclStroke time
Anchor Darling
ML20127P58623 November 1992Followup to 921005 Part 21 Rept Re Potential Defect in SB/SBD-1 Housing Cover Screws.Procedure Re Replacement of SBD-1 Spring Cover Bolts Encl.All Fasteners Should Be Loosened & Removed.List of Affected Utils Encl
ML20106E1952 November 1992Part 21 Rept Re Cracked Fuel Nozzle Tips Purchased from Bendic.Initially Reported on 910405.Addl Testing of Tips Performed Completed,Reviewed & Recommendation to Prevent Failures Made
ML17306B0588 October 1992Part 21 Rept Advising That Preliminary Evaluation of Rosemount Part 21 Notification Determined That Change in Systematic Static Pressure Span for Pressure Differential Transmitters May Result in Increase in Indicated Power
ML17306A33413 December 1991Followup Part 21 Rept Re Potential for Certain Westinghouse Products,Utilizing Dc Coil Assemblies,To Malfunction.Caused by Epoxy Compound Becoming semi-fluid During Svc.Initially Reported on 910624.Epoxy Check Will Be IncorporatedOvertravel
ST-HL-AE-3903, Suppl to Special Rept:On 901126,fuel Oil Leak Noted at Injection Pump 1L of Standby Diesel 23.Caused by Crack on Threaded Portion of Delivery Valve Holder.Injection Pump Delivery Valve & Valve Holder Replaced on 9011274 November 1991Suppl to Special Rept:On 901126,fuel Oil Leak Noted at Injection Pump 1L of Standby Diesel 23.Caused by Crack on Threaded Portion of Delivery Valve Holder.Injection Pump Delivery Valve & Valve Holder Replaced on 901127
ML20086P15931 October 1991Part 21 Rept Re Microscopic Cracks in Fuel Nozzle Tip from Mfg Lot D87001.Cracks Perpendicular to Axis of Nozzle & Extend Through Case Hardening & Stop at Core.Interim/Final Report Will Be Forwarded as Further Development Occurs
ML20083D77120 September 1991Interim Part 21 Rept Re Failure of Fuel Injector Nozzle Tips.Initially Reported on 910723.Each Util Will Continue to Monitor Exhaust Gas Temps During Monthly Runs & Will Sample Lube Oil on Quarterly Basis for Contamination
ML17305B61824 June 1991Part 21 Rept Re Potential for Certain Westinghouse-supplied Products,Utilizing Dc Coil Assemblies,To Malfunction. Initially Reported on 910620.Recommends That All Suspect Devices Be Replaced & Epoxy Compound Probed
ML20072S9505 April 1991Interim Part 21 Rept Re Failure of Standby Diesel Generator Fuel Nozzle Tips Mfg by Bendix.Initially Reported on 910327. on 910327 Memo Issued Requesting Recall of Affected Parts. Technical Evaluation Underway by Util
ML20072T3084 April 1991Advises That Ongoing Investigation Into Emergency Diesel Generator Failure Raised Questions Re Fuel Nozzle Tips Furnished by Cooper Energy Svc.Records Indicate Tips Supplied to Company
ST-HL-AE-3655, Deficiency Rept & Part 21 Rept Re Change in Commitment to Procure Class 1E Battery Cables from Gould Nuclear Batteries Inc.Gould Discontinued Implementation of QA Program & Removed from Util Approved Vendor List3 January 1991Deficiency Rept & Part 21 Rept Re Change in Commitment to Procure Class 1E Battery Cables from Gould Nuclear Batteries Inc.Gould Discontinued Implementation of QA Program & Removed from Util Approved Vendor ListCommercial Grade Dedication
ST-HL-AE-3568, Revised Part 21 Rept Re Failure of Feedwater Isolation Valve Due to Thermal Incompatibility of Hydraulic Fluid15 October 1990Revised Part 21 Rept Re Failure of Feedwater Isolation Valve Due to Thermal Incompatibility of Hydraulic Fluid
ML17348A16227 March 1990Part 21 Rept Re Matls W/Programmatic Defects Supplied by Dubose Steel,Inc.Customers,Purchase Order,Items & Affected Heat Numbers Listed
ML20012C1358 March 1990Part 21 Rept Re Failure of Connecting Rod in Standby Diesel Generator 22.Initially Reported on 891208.On 891128,master Connecting Rod Failed.Caused by over-drilling of Oil Holes. Final Rept, Finite Element Analysis of KSV-4-2A... EnclFinite Element Analysis
ML17223A74526 January 1990Part 21 Rept Re Backup Rings Furnished in Spare Parts Seal Kits & in 25 Gpm 4 Way Valves as Part of Actuators Made of Incorrect Matl.Rings Should Be Viton & Have Been Identified as Buna N
ML20011D1978 December 1989Part 21 Rept Re 891128 Failure of Master Connecting Rod 4 & Ejection of Rod & Broken Pieces Through Right Ctr Door Frame Opening.Caused by High Cycle Fatigue to Transverse Oil Passage.Repairs to Crankshaft & Engine Underway
ML19325E08616 October 1989Followup Part 21 Rept Re Class 1E Battery Chargers W/ Transformers Running at Temps Exceeding Those Used in Qualification Rept When Operating at or Near Full Load Rating of Equipment.Listed Corrective Actions Underway
ML17304B12820 April 1989Part 21 Rept Re Multiple Control Element Assembly Slip or Drop Events at Unit 1 on 881210.Caused by Intermittent T Grounding of Control Element Drive.Initially Reported on 890419.Stack Assemblies Will Be Replaced
ML20247P7994 April 1989Part 21 Rept Re Atmospheric Dump Valves.Cause of Failure Speculative But Result of Piston Ring That Failed to Seal. Resolution to Problem Requires Increasing Pilot Valve Capacity & Reworking of Plug to Enlarge Pilot Flow Area
ML17304B1692 February 1989Part 21 Rept Re Ruskin Div Supplied Dampers W/Itt Actuators. Div Currently Evaluating Loctite Compound Which May Be Applied,Following Verification of Proper Damper Adjustment, to Threads of Extension Shaft in PlaceLoctite
ML17304A97118 January 1989Part 21 Rept Re Ksv Standby Diesel Generator Rocker Arm Failure.On 890104,exhaust Valve Rocker Arm Installed in KSV-20-T Engine Broke at Plant.Investigation Revealed That Castings Cracked During Mfg.Review Underway
ST-HL-AE-2868, Part 21 & Final Deficiency Rept Re ESF Diesel Generator Galling Damage.Initially Reported on 881026.Damaged Parts on Diesel Generator 21 Replaced.Deficiency Is Solely Attributable to Cooper-Bessemer Maint Activities23 November 1988Part 21 & Final Deficiency Rept Re ESF Diesel Generator Galling Damage.Initially Reported on 881026.Damaged Parts on Diesel Generator 21 Replaced.Deficiency Is Solely Attributable to Cooper-Bessemer Maint Activities
ST-HL-AE-2843, First Interim Part 21 & Deficiency Rept Re Elastomer Diaphragms Contained in Comsip Delphi Containment Hydrogen Analyzers.Initially Reported on 881012.Unit 1 Regulator Replaced.Next Rept Will Be Submitted by 88121614 November 1988First Interim Part 21 & Deficiency Rept Re Elastomer Diaphragms Contained in Comsip Delphi Containment Hydrogen Analyzers.Initially Reported on 881012.Unit 1 Regulator Replaced.Next Rept Will Be Submitted by 881216
ST-HL-AE-2840, First Interim Deficiency & Part 21 Rept Re Class 1E Battery Cables.Initially Reported on 881012.Jumper Cables Will Be Replaced W/Qualified Cables Prior to Fuel Load.Next Rept Will Be Submitted by 8812309 November 1988First Interim Deficiency & Part 21 Rept Re Class 1E Battery Cables.Initially Reported on 881012.Jumper Cables Will Be Replaced W/Qualified Cables Prior to Fuel Load.Next Rept Will Be Submitted by 881230
ML20207P0154 October 1988Part 21 Rept Re Fuel Nozzle Tips in Standby Diesel Generator KSV-20-T W/Cracks Permitting Diesel Fuel to Be Sprayed Into Cylinders.Heavy Vapors Observed Emitting from Breathers on Some Cylinder Heads
ST-HL-AE-2767, Final Deficiency Rept Re Cracking of ESF Diesel Generator Heads.Initially Reported on 880801.Precautions Added to ESF Diesel Generator Instruction Manual to Ensure Engine Timing Checked Out Prior to Operation Following Maint30 August 1988Final Deficiency Rept Re Cracking of ESF Diesel Generator Heads.Initially Reported on 880801.Precautions Added to ESF Diesel Generator Instruction Manual to Ensure Engine Timing Checked Out Prior to Operation Following Maint
ST-HL-AE-2698, Final Deficiency Rept Re Veritrak Transmitters.Initially Reported on 860801.Reactor Protection Setpoints Currently in Use Considered Conservative & No Hardware Changes Required29 June 1988Final Deficiency Rept Re Veritrak Transmitters.Initially Reported on 860801.Reactor Protection Setpoints Currently in Use Considered Conservative & No Hardware Changes RequiredPost Accident Monitoring
ST-HL-AE-2696, Part 21 & Deficiency Rept Re Defects in Westinghouse Circuit Breakers.Initially Reported on 880520.Item Reportable Under 10CFR50.55(e) for Unit 2 & 10CFR21 for Units 1 & 2.Remaining Unit 2 Insps Will Be Completed Prior to Fuel Load15 June 1988Part 21 & Deficiency Rept Re Defects in Westinghouse Circuit Breakers.Initially Reported on 880520.Item Reportable Under 10CFR50.55(e) for Unit 2 & 10CFR21 for Units 1 & 2.Remaining Unit 2 Insps Will Be Completed Prior to Fuel Load
ST-HL-AE-2688, Final Deficiency Rept Re Leakage of aluminum-bronze Essential Cooling Water Sys.Initially Reported on 880512. No Safety Concerns Exist If Left Uncorrected Based Upon Detailed Technical Evaluations Previously Submitted9 June 1988Final Deficiency Rept Re Leakage of aluminum-bronze Essential Cooling Water Sys.Initially Reported on 880512. No Safety Concerns Exist If Left Uncorrected Based Upon Detailed Technical Evaluations Previously Submitted
ML20154M60618 April 1988Provides Further Info Re Seal Matl Incompatibility Issue at Plant,Per 880415 Discussion.Recommends Enhanced Surveillance Program for Suspected Operators to Monitor for Excessive Leakage.Part 21 Related
ST-HL-AE-2559, Seventh Interim Deficiency Rept Re Veritrak Transmitters. Initially Reported on 860801.Westinghouse Presently Compiling Data from Tests on Transmitter Capsules & Amplifiers.Next Rept Will Be Submitted by 88063025 March 1988Seventh Interim Deficiency Rept Re Veritrak Transmitters. Initially Reported on 860801.Westinghouse Presently Compiling Data from Tests on Transmitter Capsules & Amplifiers.Next Rept Will Be Submitted by 880630
ST-HL-AE-2538, Supplemental Deficiency Rept on Electrical Splices Using Raychem Heat Shrink Insulation Matl.Initially Reported on 870219.Review of Cables & Terminations Listed as Not Having Splice Performed to Assure Proper Transmission of Info1 March 1988Supplemental Deficiency Rept on Electrical Splices Using Raychem Heat Shrink Insulation Matl.Initially Reported on 870219.Review of Cables & Terminations Listed as Not Having Splice Performed to Assure Proper Transmission of Info
ML20153B28122 February 1988Part 21 Rept Re Defect in Operation of Gas Monitors Using Fixed Filters.Initially Reported on 880212.Caused by Error in Software for Monitors.Vendor Testing Mod to Software & in Interim Recommends Changing Filters Every 48 H