Letter Sequence Other |
---|
|
|
MONTHYEARML20216J4881997-09-0909 September 1997 Forwards Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Condition. in Order to Complete Review,Detroit Edison Requested to Respond by 971017 Project stage: RAI NRC-97-0111, Forwards Response to 970909 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions,1997-10-17017 October 1997 Forwards Response to 970909 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions, Project stage: Other NRC-98-0058, Provides Update to Licensee Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions,1998-03-27027 March 1998 Provides Update to Licensee Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, Project stage: Other ML20216C1561998-04-0606 April 1998 Forwards Request for Addl Info Related to Fermi-2 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions Project stage: RAI ML20206N7351999-05-14014 May 1999 Forwards RAI Re Plant Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During DBA Conditions Project stage: RAI 1998-03-27
[Table View] |
Similar Documents at Fermi |
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217N4261999-10-25025 October 1999 Forwards Amend 17 to License DPR-9 & Safety Evaluation. Amend Revises TS by Deleting SR D.3.c,which Required Weekly Observation of Nitrogen Cover Gas Pressure within Sodium Storage Tanks Located in Sodium Building NRC-99-0085, Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl1999-10-22022 October 1999 Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl NRC-99-0094, Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed1999-10-22022 October 1999 Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed ML20217P1661999-10-21021 October 1999 Forwards Insp Rept 50-341/99-17 on 990927-1005.No Violations Noted ML20217M0771999-10-19019 October 1999 Confirms Discussion Between GL Shear,M Mitchell,E Kosky, D Williams,B Rumins,D Harmon & W Rutenberg in Public Meeting on 990923.Purpose of Meeting Was to Discuss Current Status RP Program at Enrico Fermi 2 ML20217N9231999-10-15015 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 40 ML20217E5671999-10-14014 October 1999 First Partial Response to FOIA Request for Documents.Records in App a Already Available in Pdr.App B Records Encl & Being Released in Entirety NRC-99-0087, Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons1999-10-12012 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons NRC-99-0083, Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-10-0707 October 1999 Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal ML20217D5331999-10-0707 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 39 ML20217F5931999-10-0707 October 1999 Forwards Insp Rept 50-341/99-11 on 990724-0908.Two Violations Re Failure to Follow Procedures While Sampling Standby Liquid Control Tank & Wear Dosimetry Properly Being Treated as Noncited Violations ML20217B8261999-10-0404 October 1999 Forwards Summary of Decommissioning Insp Plan for Fy 2000. Plan Will Be Updated Annually & May Be Revised at Any Time Based Upon Future Insp Findings,Events & Resource Availability ML20212J8121999-10-0101 October 1999 Discusses Plant,Unit 2 Completion of Licensing Action for GL 98-01 & Suppl 1, Y2K Readiness of Computer Sys at Npps. Ack Efforts That Licensee Have Completed to Date in Preparing Plant for Y2K Transition ML20212K8881999-09-30030 September 1999 Refers to 990928 Meeting Conducted at Fermi Unit 2 to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PSA Staff ML20217A3261999-09-30030 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 38 NRC-99-0091, Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations1999-09-27027 September 1999 Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations ML20212J8331999-09-27027 September 1999 Responds to Licensee 990924 Request That NRC Exercise Discretion Not to Enforce Compliance with Actions Required in TS 3/4.6.1.8.Ltr Documents 990923 Telcon with Util in Which NRC Orally Issued NOED ML20216G9791999-09-24024 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 37 NRC-99-0092, Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys1999-09-24024 September 1999 Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys ML20216H3561999-09-23023 September 1999 Informs That During 990914 Telcon,L Sanders & M Bielby Made Arrangements with NRC to Inspect Licensed Operator Requalification Program at Fermi Nuclear Station for Week of 991129 Which Coincides with Util Regularly Scheduled Exam ML20216H4541999-09-23023 September 1999 Informs That During 990914 Telcon L Sanders & M Bielby Made Arrangements for Administration of Licensing Exams at Fermi Nuclear Station for Week of Jan 31,2000.NRC Will Make Exam Validation Visit to Facility During Week of Jan 10,2000 ML20212F3241999-09-20020 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 36 NRC-99-0081, Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public1999-09-17017 September 1999 Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public ML20217A9421999-09-0909 September 1999 Informs That NRC Plan to Conduct Addl Resident Insps Beyond Core Insp Program Over Next 6 Months to Assess Improvements in Areas of Procedural Compliance & Quality of Work. Historical Listing of Plant Issues Encl NRC-99-0079, Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-09-0808 September 1999 Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20211Q0991999-09-0303 September 1999 Forwards Rev 35 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0090, Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld1999-09-0303 September 1999 Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld NRC-99-0066, Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d)1999-08-30030 August 1999 Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d) ML20211G4951999-08-24024 August 1999 Forwards Rev 34 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0055, Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval1999-08-19019 August 1999 Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval IR 05000341/19990131999-08-19019 August 1999 Discusses Insp Rept 50-341/99-13 & OI Rept 3-98-039 Conducted Into Potential Misconduct of Operator Formerly Employed by De.Nrc Determined That Violation of NRC Regulations Occurred.Synopsis of IO Rept Encl NRC-99-0056, Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation1999-08-19019 August 1999 Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation ML20211C0521999-08-17017 August 1999 Forwards Tables for Sections 3.6 & 3.7 of Draft Safety Evaluation of Proposed Conversion of Current TS to Improved Standard TS NRC-99-0089, Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-08-17017 August 1999 Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20217E6181999-08-13013 August 1999 FOIA Request for Documents Re Implementing Regulations in 10CFR & Requesting That Region III Task Interface Agreement (TIA) Related to Fermi 2 Plant Be Made Available IR 05000341/19990011999-08-10010 August 1999 Forwards Insp Rept 50-341/99-01 on 990619-0723 & Nov. Violation of Concern Because Operators Did Not Understand License Requirements & Placed Plant in Configuration Where EDG 11 Was Removed from Service IR 05000341/19990121999-08-0606 August 1999 Forwards Insp Rept 50-341/99-12 on 990712-0716.No Violations Noted.Insp Focused on Implementation of Plant Chemistry & Radiological Environ Monitoring Programs & Operation of post-accident Sampling Sys ML20211C4761999-08-0606 August 1999 Forwards Draft Safety Evaluation Re Proposed Conversion of Current TS to Improved Standard TS NRC-99-0057, Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS1999-08-0404 August 1999 Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS ML20210N5451999-08-0303 August 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 33 NRC-99-0077, Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS1999-07-26026 July 1999 Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS ML20210J2121999-07-23023 July 1999 Discusses NRC OI Investigation Rept 3-98-039 Completed on 990524 & Forwards Notice of Violation NRC-99-0053, Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl1999-07-15015 July 1999 Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl ML20209H7211999-07-14014 July 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 32 NRC-99-0054, Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal1999-07-13013 July 1999 Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal ML20209F6571999-07-12012 July 1999 Forwards Insp Rept 50-341/99-09 on 990516-0618.No Violations Noted.Weak Procedural Guidance,Communications Issues & Configuration Control Weaknessess Were Evident NRC-99-0052, Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions1999-07-0707 July 1999 Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions ML20196J5511999-07-0202 July 1999 Discusses GL 92-01,Rev 1,Supp 1, Rv Integrity, Issued by NRC on 950519 & DE Responses & 980729 for Fermi 2.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 as Result of Review of Responses ML20209C6141999-07-0101 July 1999 Rev 31 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0076, Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included1999-06-30030 June 1999 Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARNRC-99-0094, Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed1999-10-22022 October 1999 Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed NRC-99-0085, Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl1999-10-22022 October 1999 Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl ML20217N9231999-10-15015 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 40 NRC-99-0087, Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons1999-10-12012 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons NRC-99-0083, Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-10-0707 October 1999 Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal ML20217D5331999-10-0707 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 39 ML20217A3261999-09-30030 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 38 NRC-99-0091, Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations1999-09-27027 September 1999 Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations ML20216G9791999-09-24024 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 37 NRC-99-0092, Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys1999-09-24024 September 1999 Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys ML20212F3241999-09-20020 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 36 NRC-99-0081, Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public1999-09-17017 September 1999 Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public NRC-99-0079, Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-09-0808 September 1999 Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev NRC-99-0090, Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld1999-09-0303 September 1999 Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld ML20211Q0991999-09-0303 September 1999 Forwards Rev 35 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0066, Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d)1999-08-30030 August 1999 Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d) ML20211G4951999-08-24024 August 1999 Forwards Rev 34 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0056, Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation1999-08-19019 August 1999 Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation NRC-99-0055, Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval1999-08-19019 August 1999 Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval NRC-99-0089, Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-08-17017 August 1999 Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20217E6181999-08-13013 August 1999 FOIA Request for Documents Re Implementing Regulations in 10CFR & Requesting That Region III Task Interface Agreement (TIA) Related to Fermi 2 Plant Be Made Available NRC-99-0057, Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS1999-08-0404 August 1999 Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS ML20210N5451999-08-0303 August 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 33 NRC-99-0077, Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS1999-07-26026 July 1999 Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS NRC-99-0053, Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl1999-07-15015 July 1999 Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl ML20209H7211999-07-14014 July 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 32 NRC-99-0054, Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal1999-07-13013 July 1999 Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal NRC-99-0052, Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions1999-07-0707 July 1999 Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions ML20209C6141999-07-0101 July 1999 Rev 31 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0049, Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Disclosure Encl1999-06-30030 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Disclosure Encl NRC-99-0076, Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included1999-06-30030 June 1999 Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included ML20209C1081999-06-29029 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 30 NRC-99-0050, Forwards Rev 7 to ITS Submittal of 980403,to Provide Remaining Responses to NRC RAIs Re ITS Sections 3.5 & 3.8. Revision Instructions Included1999-06-24024 June 1999 Forwards Rev 7 to ITS Submittal of 980403,to Provide Remaining Responses to NRC RAIs Re ITS Sections 3.5 & 3.8. Revision Instructions Included NRC-99-0075, Forwards Operator License Renewal Application,Nrc Forms 398 & 396 for CR Effan,License SOP-30186-3.Encl Withheld1999-06-22022 June 1999 Forwards Operator License Renewal Application,Nrc Forms 398 & 396 for CR Effan,License SOP-30186-3.Encl Withheld ML20212J3861999-06-18018 June 1999 Forwards Rev 29 to Approved UFSAR LCR That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0047, Responds to NRC 990513 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Revised Design Calculation DC-5957, GL 96-06 Calculations, Encl1999-06-0909 June 1999 Responds to NRC 990513 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Revised Design Calculation DC-5957, GL 96-06 Calculations, Encl ML20195G2001999-06-0808 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 28 ML20195E7391999-06-0303 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 27 NRC-99-0046, Forwards Rev 6 to Fermi 2 ITS Submittal ,to Provide Remaining Responses to NRC RAI Re ITS Section 3.3, & Update ITS Submittal to Reflect Responses.Brief Abstract of Changes Contained in Attachment 11999-06-0202 June 1999 Forwards Rev 6 to Fermi 2 ITS Submittal ,to Provide Remaining Responses to NRC RAI Re ITS Section 3.3, & Update ITS Submittal to Reflect Responses.Brief Abstract of Changes Contained in Attachment 1 ML20207D9631999-05-26026 May 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section) ML20195B3381999-05-19019 May 1999 Forwards Rev 25 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section) NRC-99-0040, Requests NRC Approval of Revs to Weld Tables of Encl Relief Requests RR-A21,rev 1 & RR-A22,rev 1.Revs Do Not Impact Basis for Original Requests for Relief Because There Is No Change to Technical Basis or Proposed Alternative1999-05-14014 May 1999 Requests NRC Approval of Revs to Weld Tables of Encl Relief Requests RR-A21,rev 1 & RR-A22,rev 1.Revs Do Not Impact Basis for Original Requests for Relief Because There Is No Change to Technical Basis or Proposed Alternative NRC-99-0039, Requests Relief from ASME Section XI Requirement to Examine Essentially 100% of Selected Category B-J Pipe Welds,Per 10CFR50.55a(g)(5)(iii).Relief Request RR-A23,encl1999-05-14014 May 1999 Requests Relief from ASME Section XI Requirement to Examine Essentially 100% of Selected Category B-J Pipe Welds,Per 10CFR50.55a(g)(5)(iii).Relief Request RR-A23,encl NRC-99-0041, Requests Relief from ASME Section XI Requirements to Examine Essentially 100% of Accessible Category B-D Nozzle Welds,Per 10CFR50.55a(g)(5)(iii).Rev 1 to Relief Request RR-A6,encl1999-05-14014 May 1999 Requests Relief from ASME Section XI Requirements to Examine Essentially 100% of Accessible Category B-D Nozzle Welds,Per 10CFR50.55a(g)(5)(iii).Rev 1 to Relief Request RR-A6,encl NRC-99-0038, Requests Relief from ASME Section XI 1980 Requirement to Examine Essentially 100% If Category B-A RPV Shell Weld Lengths,Per 10CFR50.55a(g)(5)(iii)1999-05-14014 May 1999 Requests Relief from ASME Section XI 1980 Requirement to Examine Essentially 100% If Category B-A RPV Shell Weld Lengths,Per 10CFR50.55a(g)(5)(iii) NRC-99-0045, Forwards Rev 5a to Fermi 980403 Submittal,Converting TS to Its.Encl Rev Provides Remaining Responses to NRC RAIs Re ITS Section 3.6 Contained in NRC 990211 Rai.Brief Abstract of Changes & Responses to Rai,Encl1999-05-0707 May 1999 Forwards Rev 5a to Fermi 980403 Submittal,Converting TS to Its.Encl Rev Provides Remaining Responses to NRC RAIs Re ITS Section 3.6 Contained in NRC 990211 Rai.Brief Abstract of Changes & Responses to Rai,Encl NRC-99-0044, Forwards Rev 5 to ITS to Provide Responses to RAI Re ITS Section 3.6 (Except ITS Section 3.6.1.3) Contained in & Update in ITS Submittal to Reflect Responses1999-04-30030 April 1999 Forwards Rev 5 to ITS to Provide Responses to RAI Re ITS Section 3.6 (Except ITS Section 3.6.1.3) Contained in & Update in ITS Submittal to Reflect Responses NRC-99-0059, Provides Notification Required by 10CFR50.82(a)(7) of Changes to Fermi 1 Decommissioning Cost Estimate1999-04-29029 April 1999 Provides Notification Required by 10CFR50.82(a)(7) of Changes to Fermi 1 Decommissioning Cost Estimate ML20206E2941999-04-28028 April 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 24 NRC-99-0037, Forwards Rev 9 to Fermi 2 Ufsar,Per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of Changes to QA Program & Vol 1 of Technical Requirements Manual,Encl1999-04-26026 April 1999 Forwards Rev 9 to Fermi 2 Ufsar,Per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of Changes to QA Program & Vol 1 of Technical Requirements Manual,Encl 1999-09-08
[Table view] |
Text
,
0:ugte n etstn Senio, Vre Prescent
~-,0......,-
Detroit. -
. .-u Ec ison =~=,,e,.s,....;-
October 17,1997 l
NRC-97-0111
! IJ.S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, D. C. 20555
References:
- 1) Fenn12 NRC Docket No. 50-341 NRC License No. NPF-43
- 2) NRC Generic letter 96-06: Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions, dated September 30,1996
- 3) Detroit Edison Letter to NRC," Detroit Edison 30-Day Response to NRC Generic Letter 96-06," NRC 96-0118, dated October 30,1996
- 4) Detroit Edison Letter to NRC," Detroit Edison 120 Day Response to NRC Generic Letter 96-06," NRC 97-0003, dated January 28,1997
- 5) NRC Letter to Detroit Edison," Request for Additional Information Related to the Fermi-2 Response to Generic Letter 96-06," dated September 9,1997 (TAC No M96811)
Subject:
Additional Infonnation Related to Detroit Edison Response to NRC Generic I etter 96-06 In Reference 5, the NRC requested Detroit Edison to provide additional 7
ir. formation regarding the 120 day Response (Reference 4) to Generic Letter 96-06.
s
--4 e 9710210124 971017 /L'O /l PDR ADOCK 05000341 ['\
P PDR s g
, USNRC NRC 97 Oll!
Page 2 Detroit Edison was requested to provide summaries of the evaluations performed for the pipes in the six affected penetrations which are susceptible to thermally induced overpressurization. These summaries were to include: (1) fabrication drawings of piping sections evaluated; (2) a description of the analysis, including assumptions used in the analysis and; (3) the results of the analysis. Additionally, the response was to explain how the criteria used for the evaluations met the licensing basis criteria for Fermi 2 and to provide the schedule for the completion of any modifications that may be required. The enclosure to this letter provides the requested additional information as stated above, in Reference 4 Detroit Edison committed to completing necessary modifications by the next refueling outage. Detroit Edison is participating in EPRI analysis and l iesticg c.:'ivities intended to establish a technical basis that can be used to l demc 1 strate aceptability of these penetrations without modification. Because l
compc: tion of t'tese activities may not allow adequate time to properly design and install .nou 5:ations during the next refueling outage, the commitment from l Reference 4 is revised, as follows:
1 Detroit Edison will design and install any modifications which inay be necessary based on the results of these activities. Detroit Edison will provide an update to the NRC by March 31,1998 regarding the progress of this effort, including any proposed modifications identified to date.
if you have any questions, please contact Mr. Norman K. Peterson, Director, Nuclear Licensing at (313) 586-4258.
Sincerely, ,
Enclosure cc: A. B. Beach G. A. Harris M. J. Jordan A. J. Kugler
i i
1
[ USNRC l NRC 97 0111-Page 3 t
I, DOUGLAS R. GIPSON, do hereby afrirm that the foregoing statements are based on facts and circumstances which are true and accurate to the best ofiny knowledge and belief.
b i
DOUGLAS R.%1PSON _.
Senior Vice President On this /7 M day of .O _.are me personally appeared Douglas R. Gipson, being first duly sworn and says that he executed the foregoing as his free act and deed, i
Notary Public
- SHARON K BUCKLEY-g aMonroe cound.Mt WoossiedonhpkesSept 22,20@ q l *
. . . . . , . ~ - . - . - . - . - - . - . - . . . - . . _ - - - , - . , _ - . - - . . . , .
, Enclosure to NRC 97 0111 Page1 Detroit Edison Response to the NRC Reuucst for Addinonalinformallo_ 1 (RAI) Related to Detroit Edison Response to Generie Letter 96-06.
(TAC No. M96811)
The following is the Detroit Edison response to the items requested by the NRC in the enelosure of the NRC letter dated September 9,1997:
e NRC RAI Item Number 1: "The NRC requests that DECO provide summaries of the evaluaties performed for the pipes in the six affected penetrations. The summaries should include fabrication drawings of the piping sections evaluated and describe the method of analysis, including the assumptions used in the analyse,s, and the results "
Detroit Edison Response:
As discussed in Detroit Edison's 120 day response to Generic Letter 96 06 (Reference 4), Fermi 2 has six drywell penetrations that are susceptible to thennally induced overpressurization due to increase in the drywell ambient temperature after a LOCA. As requested in the NRC RAI, enclosed are six l figures describing the piping sections and valves for these six penetrations.
l The figures summarize .he infomiation from the many fabrication drawings that are used to describe the installation. Additionally, three supporting figures are provided describing details of the containment penetrations.
These penetrations are:
- 1. Penetration X 8: Main Steam Drain Line
- 2. Penetration X 18: Drywell Floor Drain Sump Discharge Line
- 3. Penetration X-19: Drywell Equipment Drain Sump Discharge Line
- 4. Penetration X 29Aa: Reactor Recirculation Water Sample Line
- 5. Penetration X Sla: Reactor Recirculation Pump A Seal Purge Line
- 6. Penetration X-49a: Reactor Recirculation Pump B Seal Purge Line None of these susceptible penetrations are required to operate after a LOCA.
Five of the six penetration lines, the Main Steam Drain line (Figure 1); Drywell Floor Drain and Equipment Drain Sump Discharge lines (Figures 2 & 3); and Recirculation Pump Seals A and B Purge lines (Figures 5 & 6) are connected to non-safety related piping immediately outside the containment isolation valve.
These systems are not required to operate after accidents. The Recirculation Water Sample line penetration (Figure 4) att*.ched to non-safety related tubing near the sample cooler and would also noi ne used after an accident.
. Enclosure to NRC 97 0111 Page 2 For the isolated drywell penetrations susceptible to thermal overpressurization, operability means that containment integrity is maintained considering the single failure criteria. As discussed in Reference 4, the Fermi 2 operability evaluation for these penetrations relies on engineering judgmentt no detailed stress analysis was performed. The evaluation concluded that operability of containment penetrations was not adversely alTected by the aforementioned phenomeno t This approach is considered satisfactory since there is reasonable assurance that the penetrations will maintain containment integrity.
As discussed in Reference 4, penetration voiding may exist that would prevent overpressurization; or valve seat, bonnet, or packing leakage would be expected to limit any pressure rise to less than the failure pressure. A review of Fermi 2 Local Leak Rate Test data confirmed that all six penetrations exhibit some leakage. Leakage rates of air at 56 psig are not easily correlated to water leakage rates at several thousand psig. Ilowever, for the worst penetration, which is the drywell equipment drain sump discharge line, less than one half gallon is required to leak to completely depressurize the piping.
The main steam drains drywell penetration is isolated aller reaching full reactor pressure and temperature, when drain flow is minimum and the drains are no longer needed. At this condition the penetration piping is expected to be illied with steam, instead of completely full with water. Also, the piping would be above ambient temperature due to interfacing high temperature systems on each side of the isolation valves. Therefore, it is highly unlikely that this piping will be water solid to the extent that it can be subjected to thermal overpressurization.
The containment sump lines would not be expected to be completely full since the penetration is located at the high point of the system. The inboard isolation valves are normally open which allows the piping to leak through the pump discharge check valves. The piping outside containment also includes a vacuum breaker approximately at the same elevation as the penetration piping.
These penetrations are isolated with solid wedge gate valves which would also leak through the packing, bonnet boltface or across the seat before piping failure would be expected.
The Recirculation Pump Seal Purge lines and the Recirculation Sample line are likely to be filled solid with water. However, the containment isolation valves are air-operated spring to-close angle globe valves, and at least one of the isolation valves in each of these penetrations is oriented so that flow is under seat and their expanding volume of water is very small. This type of valve is not leak tight, and would be expected to leak to limit thermal overpressurization before the 3/4" and 1" Schedule 80 or 160 stainless steel
. Enclosure to NRC-97-0111 Page 3 piping would fail. The excess pressure would be expected to lif1 the spring before overpressurizing the piping to failure.
The thermal overpressurization loading is not expected to cause the piping system to fail because the pressure will cause strains in the piping and provide increase in the volume for fluid to expand before causing overpressurization.
The load is self limiting for the temperature increases during postulated LOCA. Self limiting loads are typically not included in emergency or faulted condition stress evaluations since a single occurrence of the load will not cause failure.
In the unlikely event of mechanical failure, containment integrity is expected to be maintained. llecause the penetration assemblies have greater wall thickness, the piping and components inside and outside the containment are more susceptible to overpressure failure than the common piping in the penetration assembly. Simultaneous failures would be required both inside and outside the containment before containment integrity could be affected.
- NRC RAlltem Number _21"The response from DECO should also explain how the criteria used for the evaluations meet the licensing basis criteria for Fenni 2..."
Detroit Edison Response:
The licensing basis of the primary containment is to provide the capabili:y of limiting the release of fission products within the values specified in 10 CFR 100, in the event of a postuimed LOCA. The licensing basis for the piping systems penetrating primary containment is to maintain the integrity of the containment with double barrier protection, such that no single active failure will result in the loss of containment integrity. To maintain the containment integrity, containment penetrations have the following design characteristics: (a) capability to withstand peak transient pressures expected during a LOCA: (b) capability to withstand without failure the forces caused by impingement of the fluid from the rupture of the largest local pipe or connection;(c) capability to accommodate without failure the thermal and mechanical stresses that may be encountered during all modes of operation.
The UFSAR Sections 3.1,3.2,3.8,3.9, and 6.2 describe Fermi 2's compliance with the above mentioned licensing basis of containment penetrations, isolation valves and piping between the isolation valves.
Enclosure to NRC 97 0111 Page 4 Generic Letter 96-06 identifies conditions where thermal expansion of fluid trapped in isolated piping could lead to overpressurization of the piping syste:s The Generic Letter also states that piping systems u hich have the potential to experience pressurization due to trapped fluid expansion shall either be designed to withstand the increased pressure or shall have provisions for relieving the excess pressure. This requirement is contained in AShiE Section Ill. NC 3621.2 " Fluid Expansion Effect". Ilowever, per AShiE Code Interpretations N197 008 and N197 011, this requirement is only related to nonnal design and operating conditions, and is not applicable to cases where i
thennal expansion of fluid trapped in isolated piping occurs only during one-l time accident conditions. The stress caused by the volume expansion of the l trapped fluid due to temperature increase after LOCA exhibits the self limiting characteristics of a secondary stress as defined in AShiE Section 111, Nis-3213.9 " Secondary Stress", and failure from such stress is not expected.
For Fenni 2, the design basis for the components subjected to thermal overpressurization loads is AShiE Section 111 (1971), and the components are classified as Class I or Class 2. As these components are not subject to thermal overpressure during their normal operating conditions, their design basis does not include the thermal overpressure load case and the loading is not defined in the AShiE Design Specifications for these components. Also, the component stress analysis reports do not include an evaluation of the thermal overpressure load case. The practice of not including the thermal overpressure load case is based upon Detroit Edison's conclusion that evaluation of this load case is not required by AShiE Section 111, as supported by Code Interpretations N197-008 and N197 011.
Nevertheless, during the period ofinitial licensing of Fermi 2, Detroit Edison has addressed thermal expansion of fluid trapped in isolated piping where it wa:: required by the operating conditions of the piping system. In response to an NRC question (FSAR Question 212.169) specific to the RilR suction line between isolation valves El150F008 and El150F009, which is used for shu*down cooling (penetration X-12), provisions were made to accommodate post-LOCA thennal expansion of water trapped between these valves.
Although other penetrations were also reviewed by the NRC, the context of this request did not provide a discussion or reason for being specific to this penetration. As described in Fermi 2 UFSAR Section 6.3.2.16, a 3/4 inch thennal reliefline was added which allowed the heated water trapped between the isolation valves to be relieved back to the reactor. This provision was found acceptable by the NRC in Section 5.4.2 of the Fermi 2 Safety Evaluation Report (NUREG-0798). This 4 unique case related to a specific penetration where the operat: g conditions may have warranted consideration 1
. Enclosure to NRC 97 0111 Page 5 4
of thermal expansion of fluid trapped in isolated piping during accident conditions.
In summary, Detroit Edison concludes that the Fermi 2 licensing basis does not generally contain requirements to design for pressurization due to thermal expansion of trapped fluid during a one time accident occurrence. The licensing basis requires that containment iritegrity be maintained following an accident. Detroit Edison's evaluation criteria provides reasonable assurance that containment integrity would be maintained following postulated accidents.
- NRC RAI Item Number 3: "The response from DECO should also... provide the schedule for the completion of any modifications that may be required."
Detroit Edison Response:
Detroit Edison is participating in the EPRI GL 96 06 Utility Group to perform testing and analysis to establish a technical basis that can be used to demonstrate acceptability of these penetrations without modification. Detroit Edison will design and install any modifications which are necessary based on the results of these activities. Detroit Edison will provide an update to the NRC by March 31,1998 regarding the progress of this effort, including any proposed modifica' ions identified to date.
FERMI'2 ' ~
DRYVELL PENETRATION X-8 ,
6 ,,o, -
p cif ' >
pf f DESIGN PRESSURD 1250 PSI'
. DESIGN T- MPERATURD 575 F 3' ELL, SCH 160 B2103F016 (A234 VPB DR A105) POVELL 900#
~' A2 G VCB h' .SDLID VEDGE GATE INSIDE CONTAINMENT
-3, I?' gj 1 i CR 3,6- I Y BUTT VELD (TYP.)
Q.
l B2103FC19
POVELL 900#
I(
E
{
Sg R6 160 *
% 19023 VE A 16 GR VCB SDLID VEDGE GATE k~IP 1-47 Or, a.
Er
'10 DI
/.4 D
DUTSIDE lh R
& \ CONTAINMENT -
1%
It REF: M-3526-1 FIGURE 1
- MAIN STEAM - DRAINS - ASME CLASS I F
FERMI 2 . ,
DRYWELL PENETRATION X-18 Gil54F600 . DESIGN PRESSURE 150 PSI -
POVELL 300# DESIGN TEMPERATURE 140*F FIG 3023 VE SOLID VEDGE GATE R ELBOVS ARE A234 GR VPB DR A105 A 16 M VCB 3
k (V7 _ 13'-5 3/8* PIPING IS UNINSULATED
- TYPE II' CONTAINMENT PENETRATIDN O SEE FIGURE 8 ;
INSIDE _
I
., , 90* LR. M CDNTAINMENT ' g gfg, g
o 90* LR. o 3* SCH 40 3* SCH 160 . .
in DUTSIDE
,G CDNTAINMENT VACUUM A
,,, [ ASME ANSI BREAKER 4 CLAS_S 3, B31.1 _
. l ,
EL 578'-31/2* LM __
~~
, , EL. 577'-11'
, Vsm 90* L.R. FE RU
~
11 1 / 8 "
G1100r003 VEI " "
ASME CLASS 2 $So3 E CLTSS2 CL S 3
' SDLID VEDGE GATE 26*-11 1/16 =
A216 GR VCB (SPRING TD CLOSE) .
REF M-3050-1 M-3'59-1 FIGURE 2 DRYVELL FLOOR DRAIN SUMP PUMP DISCHARGE LINE
i l
l FERMI 2 . .
DRYVELL PENETRATION X-19 .
, s DESIGN PRESStEE: 150 PSI l DESIGN TEMPERATURE: 140*F I
ELBOVS APE A234 GR VPB DR AIDS i
AND ARE ALL 90*'
t PIPING IS UNINSULATED VACUUM PREAKER 160 pI O gB 0* L.R. -
f F0 0
. , gc 1 3g 'gfF o -,
3 ,11P fl p, y 5 DUTSIDE CONTAltoiENT
- 90* 5.R. f V- 90 LR \
e- ' I V* -3'-300# POVELL BUTT VELD (TYP.) %, 1 ID VEDG GATE g7,,7' A216 GR VCB
, <> (SPRING TD CLDSE)
INSIDE g' CDNTAINMENT 90* L A gM, f g]B
b 3*-300# POVELL FIG 3023 VE I!!E"GR 005 ^ ASME CLASS 2 Yy REF M-3658-1 M-3049-1 FIGURE 3 DRYWELL EQUIPMENT DRAIN SUMP PUMP DISHCHARGE LINE .
NMSO
4 FERMI 2 . .
DRYVELL PENETRATION X-29Ao INSIDE g,).
CONTAINMENT s
'tyE l'I't DESIGN PRESSURD 1500 PSI DESIGN TEMPERATURD 575*F t I/2
' I g( ALL FITTINGS SDCKET VELDED 6000#
g.
I ltgk kg qI gg . PIPING IS UNINSULATED
E(4 3 p ' -
, MATERIAL (EXCEPT CONTAINMENT PENET.)
y I g j PIPING A312 TP 316L N g FITTINGS A182 F316L 1* 3 DUTSIDE 6 El 2 Tp5 CONTAINMENT cs ,
, B3100F021 3/4*-1500# MANC4L GLGEE Ngc4 gO' KERDTEST 21506X04-1 4,e l* z a '/ /
sv%I w
6 og / . # 6*<+]A# e-e N 0,,,, ge s t 3/
B3100F014' ROCXVELL EDVARDS e, *'5 ASME CLASS I f 6 'M #- REF: 6DI-B31-7255-1 AIR OPERATED Y
'// . 3VI-B31-7397 ;
GLOBE,1500#
3/4" A182F316 (FLOV UNDER SEAT B3100F020 TO RELIEVE PENETRATION
- 'y %g_
ROCKVELL EDVARDS DVERPRESSURE TO REACTOR) UNIVALVE, MODEL l 3624F316 MMT AIR DPERATED Y -!
GLOBE.1500#
3/4" 4182F316 FIGURE 4 ,
RECIRCULATION SAMPLE LINE
s....--.. . _ _ _ _ . _ ._ _
FERM1 2 DESIGM PRESSURE < 1750 PSI DRYVELL' PENETRATION X-Sla DESIGN 1rEMPERATURE: ISOT '
- PIPING 15 UNINSULATE.D PIPE IS A312 TP 304 6
%" FITTINGS ARE 3000#, A182 F- 304 h,SCH80' SOCKET-VELD 3/4* S
.TWE II g-
-n Qr O' A5kS
+\ /
DUTSIDE N
CONTAINME*lT I B3100F016A .
M%1'z3/4, PED. CD'8L ROCKVELL EDVARDS
\ UNIVALVE, MODEL
- I INSIDE val 3626316 MMT S k VED CDNTAINMENT *g1 v DS AIR t.?'ERATED Y-E GLOBE, 3/4' 1500#
g 4T m (FLOV UNDER SEAT 3/4' y) LI 3/ ,,- 5003 CDUPLING .A.
TD RELIEVE PENETRATION
}I 7& 3/4' C#g
-:: -C DVERPRESSURD j SEE 'A' $- * - Y#
THIS SHT." \ c3-b g g4 -10 1/2' 4
s ,
\k , 'N
+
n 8
,4' ASME CLASS 2 satocrot4A RDCKVELL EDVARDS REF: 6VM-B31-5065-1 UNIVALVE, MODEL 3624r316 usT FIGURE 5
"^ ~
G[oBS"'3f4$5 ann RECIRCULATION PUMP A SEAL PUR_G1
FERMI 2 DESIGN PRESSURE: 1750 FSI. - . 4 DRYVELL PENETRATION X-490 DESIGN TEMPERATUREr 150*F f
t 6 .DUTSIDE 3/4* SEH PIPING IS UNINSULATED 1
EONTAINMENT ALL FITTINGS ARE 3000#,. A182 F304 5 1jg. PIPE IS A312 TP304, SOCKET-VELDED "b 4M*%g. 4 If
'PE gjg, D PE IN SCH 80
,, , SEE FIGURE '
+-P D
h #
2*
3.-5 l'x3/4-CHECK VALVF EDUPLING/
w
,i M B3100F016B INTERNALS REMOVED .
ROCKVELL EDVARDS RDCKVELL EDVARDS 5 UNIVALVE, MODEL LIFT CHECK 3624T
- 3624F316 MMT ')**A* 3/4*-1500#
AIR OPERATED Y <,
GLOBE,1500#
--
3/4* SV, A182FS16 7 CONTAINMENT (FLOV UNDER SEAT
,o ASME CLASS 2
, 45* ELL Yh '
REri 6VM-B31-5239-1 6VM-B31-5064-1
~-
- N K LL EDVARDS
~
UNIVALVE, t*0 DEL 3624F316 MMT W =-
i S,
"^
2'"oe"'iS 5" '
3/4* SV A182F316 FIGURE 6 RECIRCUL ATION PUMP SEAL ' PURGE B -.
m FERMI 2 . .
6 .
~
Y :
CCw1AmstENT SHCll _
'or
_Nf1Z ZLE. 6tttovs-7
{
- as,uneo enrs se aomo b5 x [
h'
'l .. r sega wet. B _cwcri turc Jer emacion- FA_ocrcAt rantto ;.,j ,
4 s.% , . *i.*3 ,
M $
'f, ;
_8@ yetmtmmn Osw ao @ ' *** -
^^9 fa t a vs t D _ g 4 stccvc ]
~ ,.
m1 my-,, ,, _
3 y .
puumummsmmummm mJ [ -
l.,, '
_. on i monnn JfIlidif111111 f f 11111I fp E :-sIII11 M JJ s' _
WlOW&( -YtEW TL e
/. G.9G i/.' tre o a n n IMsII - -
n uut.- %
~ / l [ ] I1 I} I J f f f III f fI J f f f f / fill J/ J J J J g. .
^) ~ ,
I?TT'777.' ,9^75??Tf~r???"T ut stuum M Yr,F;u ,:uu sia;;rMEl7.'*"N u uusuuuu I usu uuum, r
y kj l n i s s u ut u u s mu u uu m s m .sts.wova S ,e j VIEW "I._ [ , . --
/ V---* -
( 7, _
. _ __jj .,
+- 7 u.,mr,-
(sTAsttrzte m,, p.,,g 1 -a.
Moctes W . .
4 g .
1 I g
- LONGITUDAL SECTION.0F PENET. ASSEMBLY FIGURE 7 TYPE I CONTAINMENT PENETRATION ~
RLtn H-2501
uw, 4 O
L
! 1 a,
9 O . gg3 ,
ti S o!!
s c! O c a i
- - -1 -
c a >
W
( i
. g'l Is, 1
3 153 E
3
,,hf
// sie*
w in -
E-4V~S) ,
E N
+
~ v '
p II -
11
-s E5, !s !
!gjM9 i r
- 4 u I! .
O \ @
m
.. g D -
cu vi ; 'P m H
+ II I' g
- E il *4 %% E_ k g w ia ii l 8 %i t h E- - is = 3 S E
. n , u. -
s s ! > G Z
g se 4
k C t '-
.I* x u i ,
~ *
. < .c &
q -
r e ,
t
.s ..\ %
I
]J 'ky
' s .
i
- i. i y , o *
(
Z.a
%h
. es e 4 -
O h er
(l 1ll e
)
6Y 8 S 1T
( 5 E H C C4 &
A L
P X
S03 SP P T O e 6 5
I N2 0 1
w 5 S 3 -
/\
>G
- 'l A I P C &
Y B (T _
C O) j F
(
E
) G O R r '
N O
I
_ _ T o A
= R T
E
_ N
, E P
L 2 E _
9 T
_ 0E _
N I . 8T S
M H E E R CN R M SO E eR B
_ , U N F T 0 A
, G I
I A
N 1C E F T M
N LL N I
AE TH NS c/ _
. O C
G I C .
I
' I o E r 4 .
' *
. Y 1
4 T 4
X ll #
O R
P _
P A
6 7
_ _ /
T N
E E
( O j CRE M N EP N I T
N fVIP A P
E AO T M EC D N N L NO I C EN A C E
D A T LEE D D I
S N LVT D I NO ATA S
- IC MEL N SBPI g
,