MONTHYEARML25058A3462025-02-28028 February 2025 Project Manager Assignment IR 05000261/20254042025-02-28028 February 2025 Material Control and Accounting Program Inspection Report 05000261 2025404 - Public ML25045A1622025-02-24024 February 2025 SLR Environmental Pre-Application Meeting Summary ML25006A0602025-01-0707 January 2025 2025 Requalification Program Inspection H.B. Robinson Nuclear Plant ML24353A3462025-01-0202 January 2025 Letter - U.S. Nuclear Regulatory Commission Feedback on White Papers Related to the Determination of T0 for H.B. Robinson Unit 2, Heat Number W5214 ML24323A2382024-12-0505 December 2024 Regarding Relief Request RA-23-0300 for the Fifth 10-Year Inservice Inspection Interval ML24320A0032024-12-0404 December 2024 Request for Withholding Information from Public Disclosure, H. B. Robinson Steam Electric Plant, Unit No. 2 IR 05000261/20240032024-10-30030 October 2024 Integrated Inspection Report 05000261/2024003 ML24297A2182024-10-28028 October 2024 – NRC Operator License IR 05000261/20244022024-10-16016 October 2024 – Security Target Set Baseline Inspection Report 05000261/2024402 IR 05000261/20244012024-09-11011 September 2024 Security Baseline Inspection Report 05000261/2024401 ML24242A2612024-08-29029 August 2024 Operator Licensing Examination Approval 05000261/2024301 IR 05000261/20240052024-08-22022 August 2024 Updated Inspection Plan for H.B. Robinson Steam Electric Plant - Report 05000261/2024005 ML24169A2712024-08-14014 August 2024 – Issuance of Amendment No. 280 to Adopt TSTF-258-A, Revision 4, Regarding Changes to Technical Specification 5.7, High Radiation Area IR 05000261/20240022024-08-0101 August 2024 Integrated Inspection Report 05000261/2024002 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000261/20240112024-06-0303 June 2024 Focused Engineering Inspection- Commercial Grade Dedication Report 05000261/2024011 ML24114A0152024-06-0303 June 2024 Unit 2 – Issuance of Amendment No. 279 Regarding Application of Leak-Before-Break Methodology for Auxiliary Reactor Coolant System Piping IR 05000261/20240012024-05-0909 May 2024 Integrated Inspection Report 05000261/2024001 IR 05000261/20240102024-04-30030 April 2024 Biennial Problem Identification and Resolution Inspection Report 05000261/2024010 IR 05000261/20230062024-02-28028 February 2024 Annual Assessment Letter for H.B. Robinson Steam Electric Plant Unit 2 - Report 05000261-2023006 ML24072A2942024-02-0606 February 2024 – Notification of Licensed Operator Initial Examination 05000261/2024301 IR 05000261/20243012024-02-0606 February 2024 – Notification of Licensed Operator Initial Examination 05000261/2024301 ML24033A0592024-02-0202 February 2024 Response to Request for Additional Information License Amendment Request to Exclude the Dynamic Effects of Specific Postulated Pipe Ruptures from the Design and Licensing Basis Based on Leak-Before-Break Methodology IR 05000261/20230042024-01-31031 January 2024 Integrated Inspection Report 05000261/2023004 ML24009A2432024-01-25025 January 2024 Unit, No. 2 - Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0047 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24009A2712024-01-24024 January 2024 Revision to Reactor Vessel Material Surveillance Capsule Withdrawal Schedule ML23354A0052024-01-0808 January 2024 Request for Withholding Information from Public Disclosure, H. B. Robinson Steam Electric Plant, Unit No. 2 ML23342A0902023-12-0808 December 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000261/20234202023-11-30030 November 2023 Security Baseline Inspection Report 05000261/2023420 (Cover Letter with Report) IR 05000261/20230102023-11-28028 November 2023 Fire Protection Team Inspection Report 05000261/2023010 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000261/20230032023-11-0707 November 2023 – Integrated Inspection Report 05000261 2023003 and 07200060 2023001 ML23226A0862023-10-12012 October 2023 Issuance of Amendment No. 277 Regarding Revision of TSs to Add High-High Steam Generator Level Function to Table 3.3.2-1 and Remove Obsolete Content from TSs 2.1.1.1 and 5.6.5.b ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 ML23235A0552023-08-23023 August 2023 – Notification of an Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000261/2023010) and Request for Information (RFI) IR 05000261/20230052023-08-21021 August 2023 Updated Inspection Plan for H.B. Robinson Steam Electric Plant (Report 05000261/2023005) 05000261/LER-2023-002, Plant Trip During Reactor Protection System Testing2023-08-17017 August 2023 Plant Trip During Reactor Protection System Testing 05000261/LER-2023-001, Condition Prohibited by Technical Specification Due to Missed Entry Into Limiting Condition for Operation2023-08-10010 August 2023 Condition Prohibited by Technical Specification Due to Missed Entry Into Limiting Condition for Operation IR 05000261/20230022023-08-0707 August 2023 – Integrated Inspection Report 05000261/2023002 IR 05000261/20234022023-05-30030 May 2023 – Cyber Security Inspection Report 05000261/2023402 ML23145A1602023-05-25025 May 2023 Submittal of Updated Final Safety Analysis Report (Revision No. 30), Independent Spent Fuel Storage Installation Safety Analysis Report (Revision No. 28), Technical Specifications Bases Revisions, Quality IR 05000261/20230012023-05-0202 May 2023 Integrated Inspection Report 05000261/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000261/20220062023-03-0101 March 2023 Annual Assessment Letter for H.B. Robinson Steam Electric Plant, Unit 2 (Report 05000261/2022006) ML23047A4512023-02-21021 February 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000261/2023402 ML23041A2272023-02-13013 February 2023 2022 Q4 Robinson_Workflow Final 2025-02-28
[Table view] Category:Proprietary Information Review
MONTHYEARML24320A0032024-12-0404 December 2024 Request for Withholding Information from Public Disclosure, H. B. Robinson Steam Electric Plant, Unit No. 2 ML22213A0682022-08-0505 August 2022 Request for Withholding Information from Public Disclosure for H. B. Robinson Steam Electric Plant, Unit 2 ML22125A1942022-05-12012 May 2022 Request for Withholding Information from Public Disclosure for H.B. Robinson Steam Electric Plant, Unit 2 ML18166A3222018-09-28028 September 2018 Request for Withholding of Proprietary Information from Public Disclosure for Shearon Harris Nuclear Power Plant, Unit 1, and H. B. Robinson Steam Electric Plant Unit No. 2 ML17332A4642017-12-21021 December 2017 Request for Withholding of Proprietary Information from Public Disclosure for Shearon Harris Nuclear Power Plant, Unit 1, and H. B. Robinson Steam Electric Plant Unit No. 2 ML17079A5372017-03-24024 March 2017 Request for Withholding of Proprietary Information from Public Disclosure ML16336A1212017-02-14014 February 2017 Request for Withholding of Proprietary Information from Public Disclosure ML16292A5222016-10-27027 October 2016 Request for Withholding Information from Public Disclosure H.B. Robinson Steam Electric Plant, Unit No. 2 and Shearon Harris Nuclear Power Plant ML16145A1652016-06-24024 June 2016 Request for Withholding of Proprietary Information from Public Disclosure for Shearon Harris Nuclear Power Plant, Unit 1, and H. B. Robinson Steam Electric Plant Unit No. 2 ML16124A9962016-05-27027 May 2016 Request for Withholding of Proprietary Information from Public Disclosure for Shearon Harris Nuclear Power Plant, Unit 1, and H. B. Robinson Steam Electric Plant Unit No. 2 ML16040A2312016-02-29029 February 2016 Request for Withholding Information from Public Disclosure for Shearon Harris Nuclear Power Plant, Unit 1, and H.B. Robinson Steam Electric Plant, Unit 2 ML16012A1322016-02-0101 February 2016 Request for Withholding Information from Public Disclosure for H. B. Robinson Steam Electric Plant, Unit No. 2 and Shearon Harris Nuclear Power Plant, Unit 1 ML15328A0612015-12-16016 December 2015 Request for Withholding of Proprietary Information from Public Disclosure for Shearon Harris Nuclear Power Plant, Unit 1 and H. B. Robinson Steam Electric Plant Unit No. 2 ML15097A4612015-08-26026 August 2015 Request for Withholding of Proprietary Information from Public Disclosure ML15180A0722015-08-0707 August 2015 Request for Withholding of Proprietary Information from Public Disclosure ML15180A0812015-08-0707 August 2015 Request for Withholding of Proprietary Information from Public Disclosure ML15182A1832015-08-0707 August 2015 Request for Withholding of Proprietary Information from Public Disclosure ML15009A2842015-01-22022 January 2015 Request for Withholding of Proprietary Information from Public Disclosure ML14022A1032014-02-0303 February 2014 Request for Withholding Proprietary Information from Public Disclosure Related to Use of Gothic Code ML1018303312010-07-26026 July 2010 Request for Withholding Information from Public Disclosure ML1010601022010-06-0909 June 2010 Request for Withholding Information from Public Disclosure ML1002809022010-01-29029 January 2010 Request for Withholding Information from Public Disclosure ML0918308732009-07-23023 July 2009 Request for Withholding Information from Public Disclosure ML0734606762008-01-16016 January 2008 Carolina Power and Light Company- Request for Withholding of Proprietary Information from Public Disclosure for H.B. Robinson Steam Electric Plant, Unit No. 2 TAC No. MD7468) ML0321207062003-07-30030 July 2003 Withholding of Proprietary Version of Westinghouse Electric Companys Topical Reports WCAP-15628 & WCAP-15363, Revision 1 - Request for Withholding Information from Public Disclosure 2024-12-04
[Table view] |
Text
December 4, 2024 Laura Basta Site Vice President H. B. Robinson Steam Electric Plant Duke Energy Progress, LLC 3581 West Entrance Road, RNPA11 Hartsville, SC 29550
SUBJECT:
REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE, H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 (EPID L-2024-LLR-0017)
Dear Laura Basta:
By letter dated February 15, 2024 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML24050A006), you submitted an affidavit executed on January 30, 2024, by Gayle Elliott, Director, Licensing and Regulatory Affairs, Framatome, Inc. requesting that the information contained in the following document be withheld from public disclosure pursuant to Section 2.390 of Title 10 of the Code of Federal Regulations (10 CFR):
2R33 Reactor Pressure Vessel 10 Year ISI [inservice inspection] Weld Final Report [this document was Enclosure 4 of your letter and retitled as Fifth ISI Interval Coverage NDE Examination Data]
A nonproprietary copy of this document, with redacted pages, has been placed in the U.S.
Nuclear Regulatory Commissions (NRC) Public Document Room and added to the NRC Library in ADAMS (Enclosure 2 to ML24050A006).
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(d) The information reveals certain distinguishing aspects of a process, methodology, or component, the exclusive use of which provides a competitive advantage for Framatome in product optimization or marketability.
(e) The information is vital to a competitive advantage held by Framatome, would be helpful to competitors to Framatome, and would likely cause substantial harm to the competitive position of Framatome.
The NRC staff has reviewed your submittal and the material in accordance with the requirements of 10 CFR 2.390 and based on the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. Therefore, the version of the
L. Basta submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of the information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-0272.
Sincerely,
/RA/
Luke Haeg, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-261 cc:
Gayle Elliott, Director Licensing and Regulatory Affairs Framatome 3315 Old Forest Road Lynchburg, VA 24501 gayle.elliott@framatome.com cc: Listserv
ML24320A003 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DNRL/NVIB/BC NAME LHaeg ABaxter ABuford DATE 11/14/2024 11/18/2024 12/2/2024 OFFICE NRR/DORL/LPL2-2/BC NRR/DORL/LPL2-2/PM NAME DWrona LHaeg DATE 12/3/2024 12/4/2024