November 18, 2022 Mr. Peter Dietrich Senior VP and Chief Nuclear Officer DTE Electric Company Fermi 2 - 260 TAC 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

FERMI POWER PLANT, UNIT 2 - CONFIRMATION OF INITIAL LICENSE EXAMINATION

Dear Mr. Dietrich:

In a telephone conversation on November 9, 2022, between Mr. R. Baker, Senior Operations Engineer, and Mr. M. Donigian, Program Supervisor, NRC Exam Development, arrangements were made for the administration of operator licensing examinations at Fermi Power Plant, Unit 2 during the weeks of June 19 and June 26, 2023.

As agreed, upon during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 12 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors. The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered.

To meet the above schedule, it will be necessary for your staff to furnish the operating test outlines by January 20, 2023. The NRC staff has previously provided your staff with the written examination outline. The written examinations, operating tests, and supporting reference materials identified in NUREG-1021, Examination Standard (ES)-2.1, Preparing for Operator Licensing Initial Examinations, will be due by April 3, 2023. Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 55.40(b)(3), an authorized representative of the facility licensee shall approve the examinations and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready to use.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be cancelled or rescheduled.

To conduct the requested written examinations and operating tests, your staff will need to provide adequate space and accommodations and to make the simulation facility available on the dates noted above. In accordance with ES-3.5, Administering Operating Tests, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.

ES-1.2, Guidelines for Taking NRC Examinations, contains a number of NRC guidelines for the written examinations and operating tests as they are being administered.

P. Dietrich 2 To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) Control Number 3150-0090) at least 60 days before the first examination date (if possible). Contact Mr. B. Bergeon, the Chief Examiner for your examination, to determine the method for submission of any waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB Control Number 3150-0090) and medical certifications (OMB Control Number 3150-0024) should be submitted at least 30 days before the first examination date. If the NRC does not receive the preliminary applications at least 30 days before the examination date, a postponement may be necessary. Final, signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.

Although the guidelines for waiver or excusal requests call for their receipt at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the facility licensee to the NRC are not binding. Submittals addressing waivers or excusals, or both, should be in writing (i.e.,

using NRC Form 398 or as directed by Mr. B. Bergeon when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.

Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approvedby the OMB, Approval Number 3150-0018.

The burden to the public for these voluntary information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. Send comments regarding this information collection to the FOIA, Library, and Information Collections Branch (T6-A10M), U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the OMB reviewer at: OMB Office of Information and Regulatory Affairs (3150-0018), Attn:

Desk Officer for the Nuclear Regulatory Commission, 725 17th Street, NW Washington, DC 20503; e-mail: oira_submission@omb.eop.gov.

Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless the document requesting or requiring the collection displays a currently valid OMB Control Number.

This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with (10 CFR) Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

P. Dietrich 3 Thank you for your cooperation in this matter. Mr. S. Schmus, Principal Instructor, Exam Author, has been advised of the policies and guidelines referenced in this letter. If you have any questions about the NRCs examination procedures and guidelines, please contact Mr. B. Bergeon at 630-829-9851 or Mr. R. Orlikowski at 630-829-9834.

Sincerely, Signed by Orlikowski, Robert on 11/18/22 Robert J. Orlikowski, Chief Operations Branch Division of Operating Reactor Safety Docket No. 50-341 License No. NPF-43 cc: Distribution via LISTSERV J. Angel, Director-Nuclear Training

P. Dietrich 4 Letter to Peter Dietrich from Robert J. Orlikowski dated November 18, 2022.

SUBJECT:

FERMI POWER PLANT, UNIT 2 - CONFIRMATION OF INITIAL LICENSE EXAMINATION DISTRIBUTION:

Jessie Quichocho Marc Ferdas RidsNrrDorlLpl3 RidsNrrPMFermi2 Resource RidsNrrDroIrib Resource John Giessner Julio Lara Diana Betancourt-Roldan Allan Barker R3-DORS Ikeda Betts Colleen Schmidt ADAMS Accession Number: ML22322A108 OFFICE RIII/DORS/OB/CE RIII/DORS/OB:BC NAME RBaker:gmp ROrlikowski DATE 11/18/22 11/18/22 OFFICIAL RECORD COPY