ML21328A138

From kanterella
Jump to navigation Jump to search
Proposed Admin JPMs
ML21328A138
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 06/16/2021
From: Joseph Demarshall
NRC/RGN-III/DRS/OLB
To:
Demarshall J
Shared Package
ML20055D852 List:
References
Download: ML21328A138 (67)


Text

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 1 Work Instruction WI 5.14 Job Performance Measures Rev 10 Job Position SRO / RO No.

JP-OP-802-3006-402 Revision 0

JPM Title Perform Torus Water Average Temperature Calculation Duration 8 minutes*

Page 1

  • 2 times Duration for ILO Exams Examinee:

SRO / RO / NO Evaluator:

Validating Representatives Name: ____Chris Chambers_____

JPM Type:

Normal / Alternate Path / Time Critical Start Time Evaluation Method:

Perform / Walkthrough / Discuss Stop Time Location:

Plant / Simulator / Classroom Total Time:

PERFORMANCE EVALUATION

SUMMARY

Element S

U Comment Element S

U Comment Element S

U Comment

  • 1.
  • 2.
  • 3.
  • 4.

OPERATOR FUNDAMENTALS OBSERVATION Monitor operator fundamentals during the JPM set. Rate each area based on the criteria by placing a checkmark in the appropriate column. Indicate the comment number associated with the observation.

Operator Fundamental Meets all Expectations Opportunity for Improvement Does not meet Expectations Comment Number Monitoring Control Conservatism Teamwork Knowledge OVERALL EVALUATOR COMMENTS:

REMEDIAL CONTENT:

______ PASS

______ FAIL Evaluator Signature / Date:

/

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 2 Work Instruction WI 5.14 Job Performance Measures Rev 10 JPM Observation Criteria Fundamental Meets all Expectations Opportunity for Improvement Does not meet Expectations Monitoring Equipment status monitored at proper frequency, using multiple means if available.

Understood which indications were critical.

Some monitoring was performed but undue focus on task or lack of system knowledge prevented ideal monitoring.

Did not recognize key equipment status indicators, too much focus on single indications and ignored total system status.

Control Task preview used to prepare for job. Aware of control bands and maintained them.

Configuration control maintained.

Adequate control of system maintained throughout task but some improvements could be made such as better manual control or greater depth of knowledge for anticipating system response.

No anticipation of results of actions. Unaware or control bands or not able to maintain them. Lack of knowledge of how to control system parameters.

Conservatism Low threshold for identification of problems.

Questioning attitude. Uses stop when unsure if needed. Sensitive to nuclear safety.

Some opportunities existed to question before proceeding, High focus on task completion without consideration for other system affects.

Proceeds even when unsure with unanswered questions.

High threshold for problem conditions.

Teamwork Routinely communicates system status changes to the team. Communicates actions before taking them.

Communicated most status and actions. Some improvement would be warranted.

Routinely takes action without informing the team.

Knowledge Able to anticipate system response based on solid system knowledge. Good working knowledge of generic fundamentals to predict and monitor system response.

Plant, system, or generic fundamental knowledge has some gaps.

Unable to predict system response, unsure of generic fundamentals concepts related to plant operation.

Only relied on procedure for operating knowledge.

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 3 Work Instruction WI 5.14 Job Performance Measures Rev 10 JPM Information System:

T5000 - Primary Containment Monitoring System Task:

52016 - Calculate Torus Water Average Temperature

References:

Required (R) / Available (A) 29.ESP.01, Supplemental Information, Section 15, Torus Water Temperature Calculation (R)

Tools and Equipment Required:

Calculator Initial Conditions:

You are an extra person on shift Primary Containment Control EOP has been entered due to Drywell temperature of 147°F Torus Water level is 140 RPV pressure is being controlled by Main Turbine Bypass Valves Point T23N004 is INOPERABLE Initiating Cue(s):

The CRS directs you to calculate Torus Water Average Temperature in accordance with 29.ESP.01.

Terminating Cue(s):

Torus Water temperature has been determined by calculation.

Task Standard:

Perform Torus Water Average Temperature Calculation in accordance with 29.ESP.01, Section 15.0.

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 4 Work Instruction WI 5.14 Job Performance Measures Rev 10 Licensed Operator Exam Information (required for NRC exams)

Safety Function/Category:

10 - Emergency Plant Evolutions K/A

Reference:

(from NUREG 1123)

K/A SYSTEM: 295026 - Suppression Pool High Water Temperature K/A STATEMENT:

2.1.45 Ability to identify and interpret diverse indications to validate the response of another indication.4.3/4.3 EA2.

Ability to determine and/or interpret the following as they apply to Suppression Pool High Water Temperature:

EA2.01 Suppression Pool Water temperature......................................................... 4.1 / 4.2 Maintenance Rule Safety Classification:

N/A Maintenance Rule Risk Significant? (Yes or No)

N/A

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 5 Work Instruction WI 5.14 Job Performance Measures Rev 10 PERFORMANCE EVALUATION Start Time ELEMENT STANDARD CUE:

Provide examinee with Cue Sheet and copy of 29.ESP.01, Section 15.0

  • 1.

[15.0 CAUTION] Evaluate Torus Water Level to determine which instrument(s) to use for determining Torus Water Temperature.

  • 1.

Evaluates Torus Water Level and determines that T23-R800 instrument points can be used.

  • 2.

[15.0 NOTE (1/2)] Determine if an SRV has actuated and point 4 is INOP

  • 2.

Determines that an SRV has NOT actuated and point 4 is INOP.

CUE:

When asked for the instrument point readings, provide the examinee with the Data Sheet.

  • 3.

Determine T23-R800, Torus Water Temperature Recorder, instrument point readings and substitute the highest reading temperature for the inoperable instrument point.

  • 3.

T23-R800 instrument point readings determined and 79.35°F substituted for Point 4.

  • 4.

Calculate Average Torus Water Temperature.

  • 4.

Calculates Average Torus Water Temperature (78.96°F).

CUE:

End JPM when Torus Water temperature has been determined by calculation.

______ SATISFACTORY

______ UNSATISFACTORY Stop Time

  • Critical Step

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 6 Work Instruction WI 5.14 Job Performance Measures Rev 10 Evaluator Notes:

ENSURE ALL INDUSTRIAL AND PERSONNEL SAFETY PRACTICES ARE USED AND ENFORCED AT ALL TIMES.

FAILURE TO WEAR ALL PPE REQUIRED FOR TASK PERFORMANCE WILL RESULT IN FAILURE OF THIS JPM.

Generic Notes and Cues:

None System Specific Notes and Cues:

None Task Performance and Cues:

The Elements of this JPM are step by step in accordance with the procedure. The Standard is that the procedure is performed as written. The Cues are as listed above for indication or as each step is completed the appropriate information is reported to the examinee. Notify Examinee that time compression may be used for activities performed outside of the Control Room. Notify Examinee if JPM is Time Critical (only if JPM is NOT Alternate Path.)

Critical Steps:

Critical Tasks are identified by asterisk (*) and bolded steps on the cover sheet. Verify that the latest revision of the procedure is used and critical tasks are correctly identified.

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 7 Work Instruction WI 5.14 Job Performance Measures Rev 10 EVALUATOR KEY:

Per NOTE (2):

  • Point 4 is INOP
  • Lo-Lo set controlling pressure indicates SRVs have operated within the last 48 hrs
  • This results in substituted value of 124.35 (79.35+45) vice 69.03 (79.25+78.55+79.05+124.35+79.35+78.65+79.15+78.35) / 8 =84.59

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 8 Work Instruction WI 5.14 Job Performance Measures Rev 10 FOLLOW-UP DOCUMENTATION QUESTIONS Reason for follow-up question(s):

Question:

Reference:

Response

Question:

Reference

Response

JOB PERFORMANCE MEASURE JPM Title Perform Torus Water Average Temperature Calculation No.: JP-OP-802-3006-402 Revision: 0 Page 9 Work Instruction WI 5.14 Job Performance Measures Rev 10 Simulator Setup IC#:

N/A Malfunctions:

Number Title Value Delay Ramp N/A Remote Functions:

Number Title Value Delay Ramp N/A Override Functions:

Number Title Value Delay Ramp N/A Special Instructions:

N/A

JOB PERFORMANCE MEASURE Data Sheet: (JP-OP-802-3006-401)

T23-R800, Torus Water Temperature Recorder, Instrument Point Readings

JOB PERFORMANCE MEASURE Cue Sheet: (JP-OP-802-3006-401)

Initial Conditions:

  • You are an extra person on shift
  • Torus Water level is 0

The CRS directs you to calculate Torus Water Average Temperature in accordance with 29.ESP.01.

JOB PERFORMANCE MEASURE Work Instruction WI 5.14 Job Performance Measures Rev 10 Job Position SRO / RO No.

JP-OP-802-4101-211 Revision 0

JPM Title Determine RHR Reservoir and RHR Cooling Tower Operation Duration 10 minutes Page COVER SHEET

  • 2 times Duration for ILO Exams Examinee:

SRO / RO Evaluator:

Validating Representatives Name: ___Chris Chambers________

JPM Type:

Normal / Alternate Path / Time Critical Evaluation Method:

Perform / Walkthrough / Discuss Start Time (Circle method used)

Plant / Simulator / Classroom Stop Time Total Time:

PERFORMANCE EVALUATION

SUMMARY

Element S

U Comments Element S

U Comments

  • 1.
  • 2.
3.
4.
  • 5.
  • 6.

OPERATOR FUNDAMENTALS OBSERVATION Monitor operator fundamentals during the JPM set. Rate each area based on the criteria by placing a checkmark in the appropriate column. Indicate the comment number associated with the observation.

Operator Fundamental Meets all Expectations Opportunity for Improvement Does not meet Expectations Comment Number Monitoring Control Conservatism Teamwork Knowledge OVERALL EVALUATOR COMMENTS:

REMEDIAL CONTENT:

______ PASS

______ FAIL Evaluator Signature / Date:

/

JOB PERFORMANCE MEASURE JPM Title Determine RHR Reservoir and RHR Cooling Tower Operation No.: JP-OP-802-4101-211 Revision: 0 Page 0 Work Instruction WI 5.14 Job Performance Measures Rev 10 JPM Observation Criteria Fundamental Meets all Expectations Opportunity for Improvement Does not meet Expectations Monitoring Equipment status monitored at proper frequency, using multiple means if available.

Understood which indications were critical.

Some monitoring was performed but undue focus on task or lack of system knowledge prevented ideal monitoring.

Did not recognize key equipment status indicators, too much focus on single indications and ignored total system status.

Control Task preview used to prepare for job. Aware of control bands and maintained them.

Configuration control maintained.

Adequate control of system maintained throughout task but some improvements could be made such as better manual control or greater depth of knowledge for anticipating system response.

No anticipation of results of actions. Unaware or control bands or not able to maintain them. Lack of knowledge of how to control system parameters.

Conservatism Low threshold for identification of problems.

Questioning attitude. Uses stop when unsure if needed. Sensitive to nuclear safety.

Some opportunities existed to question before proceeding, High focus on task completion without consideration for other system affects.

Proceeds even when unsure with unanswered questions.

High threshold for problem conditions.

Teamwork Routinely communicates system status changes to the team. Communicates actions before taking them.

Communicated most status and actions. Some improvement would be warranted.

Routinely takes action without informing the team.

Knowledge Able to anticipate system response based on solid system knowledge. Good working knowledge of generic fundamentals to predict and monitor system response.

Plant, system, or generic fundamental knowledge has some gaps.

Unable to predict system response, unsure of generic fundamentals concepts related to plant operation.

Only relied on procedure for operating knowledge.

JOB PERFORMANCE MEASURE JPM Title Determine RHR Reservoir and RHR Cooling Tower Operation No.: JP-OP-802-4101-211 Revision: 0 Page 1 Work Instruction WI 5.14 Job Performance Measures Rev 10 JPM Information System:

N/A Task:

Determine RHR Reservoir and RHR Cooling Tower Operation

References:

Required (R) / Available (A) 20.000.18, Control of the Plant from the Dedicated Shutdown Panel (R)

Tools and Equipment Required:

None Initial Conditions:

You are an extra licensed operator assigned to shift.

There was a confirmed fire in Zone 12A.

20.000.18, Control of the Plant from the Dedicated Shutdown Panel, has been entered and Condition N is being performed.

The fire is out but there is severe damage.

RHR Shutdown Cooling is in service.

Outside air temperature is 23°F.

An I & C technician reports the RHRSW return temperature multimeter reading is 32.8 milliamps.

An I & C technician reports the RHRSW Reservoir Temperature multimeter reading is 27 milliamps.

Initiating Cue(s):

The CRS directs you to determine the correct configuration for MDCT Fan operation and RHRSW flow configuration IAW 20.000.18.

Terminating Cue(s):

Terminate the JPM when information is provided to the examiner.

Task Standard:

Using the information provided and 20.000.18 Enclosures B and C, determines that the MDCT Fans should be OFF and RHRSW flow should be through the Cooling Towers.

JOB PERFORMANCE MEASURE JPM Title Determine RHR Reservoir and RHR Cooling Tower Operation No.: JP-OP-802-4101-211 Revision: 0 Page 2 Work Instruction WI 5.14 Job Performance Measures Rev 10 Licensed Operator Exam Information (required for NRC exams)

Safety Function:

SF4 - Heat Removal from Reactor Core K/A

Reference:

(from NUREG 1123)

K/A SYSTEM: Generic K/A STATEMENT:

2.1.25 Ability to interpret reference materials, such as graphs, curves, tables, etc..................3.9 / 4.2 Maintenance Rule Safety Classification:

N/A Maintenance Rule Risk Significant? (Yes or No)

No

JOB PERFORMANCE MEASURE JPM Title Determine RHR Reservoir and RHR Cooling Tower Operation No.: JP-OP-802-4101-211 Revision: 0 Page 0 Work Instruction WI 5.14 Job Performance Measures Rev 10 PERFORMANCE EVALUATION Start Time ELEMENT STANDARD CUE:

Provide Cue Sheet to Examinee.

  • 1.

Determine RHRSW Heat Exchanger Return Temperature using information provided from I&C Technician.

  • 1.

Determines RHRSW Return Temperature is approximately 85°F based on multimeter reading provided (32.8 milliamps).

  • 2.

Determine RHR Reservoir Temperature using information provided from I&C Technician and Enclosure B.

  • 2.

Determines RHR Reservoir Temperature is approximately 65°F based on multimeter reading provided (27 milliamps).

3.

Refer to Step 2.2.1 due to outdoor ambient temperature <36°F.

3.

Refers to 20.000.18 Enclosure C Step 2.2.1.

4.

Anytime RHR Reservoir Temperature approaches 75°F, operate the Cooling Tower and Fan as needed. Otherwise, use the following steps.

4.

Determines RHR Reservoir Temperature is not approaching 75°F and uses following steps.

  • 5.

When RHRSW Return Temperature is 80°F, align RHRSW Flow through the Cooling Tower.

  • 5.

Determines that RHRSW flow should be aligned through the Cooling Tower based on RHRSW Return Temperature of 85°F.

  • 6.

When RHRSW Return Temperature is 90°F, run Cooling Tower Fan.

Note: Prerequisite 1.1 also applies Minimum outside ambient temperature should be greater than 36°F for Mechanical Draft Cooling Fan operation unless Reservoir Temperature cannot be maintained below 75°F.

  • 6.

Determines that MDCT Fans should be OFF based on (1) RHR Reservoir Temperature is approximately 65°F and (2) Outside ambient temperature is 23°F.

CUE:

Terminate JPM when the requested information is provided to the evaluator.

______ SATISFACTORY

______ UNSATISFACTORY Stop Time

  • Critical Step

JOB PERFORMANCE MEASURE JPM Title Determine RHR Reservoir and RHR Cooling Tower Operation No.: JP-OP-802-4101-211 Revision: 0 Page 1 Work Instruction WI 5.14 Job Performance Measures Rev 10 Evaluator Notes:

ENSURE ALL INDUSTRIAL AND PERSONNEL SAFETY PRACTICES ARE USED AND ENFORCED AT ALL TIMES.

Generic Notes and Cues:

None System Specific Notes and Cues:

None Task Performance and Cues:

The Elements of this JPM are step by step in accordance with the procedure. The Standard is that the procedure is performed as written. The Cues are as listed above for indication or as each step is completed the appropriate information is reported to the examinee.

Critical Steps:

Critical Tasks are identified by asterisk (*) and bolded steps on the cover sheet. Verify that the latest revision of the procedure is used and critical tasks are correctly identified.

JOB PERFORMANCE MEASURE JPM Title Determine RHR Reservoir and RHR Cooling Tower Operation No.: JP-OP-802-4101-211 Revision: 0 Page 2 Work Instruction WI 5.14 Job Performance Measures Rev 10 FOLLOW-UP DOCUMENTATION QUESTIONS Reason for follow-up question(s):

Question:

Reference:

Response

Question:

Reference

Response

JOB PERFORMANCE MEASURE JPM Title Determine RHR Reservoir and RHR Cooling Tower Operation No.: JP-OP-802-4101-211 Revision: 0 Page 3 Work Instruction WI 5.14 Job Performance Measures Rev 10 EVALUATOR KEY MDCT Fan Recommendation (Check one):

OFF: ___X___ Running: ________

RHRSW Flow Recommendation (Check one):

Cooling Tower Bypassed: ____ Flow Through Cooling Tower: __X__

JOB PERFORMANCE MEASURE Cue Sheet: (JP-OP-802-4101-211)

Initial Conditions:

  • You are an extra licensed operator assigned to shift.
  • There was a confirmed fire in Zone 12A.
  • 20.000.18, Control of the Plant from the Dedicated Shutdown Panel has been entered.
  • The fire is out but there is severe damage.
  • Outside air temperature is 23°F.
  • An I & C technician reports the RHRSW return temperature multimeter reading is 32.8 milliamps.
  • An I & C technician reports the RHRSW Reservoir Temperature multimeter reading is 27 milliamps.

Initiating Cue(s):

The CRS directs you to determine the correct configuration for MDCT Fan operation and RHRSW flow configuration IAW 20.000.18 Enclosures B and C.

MDCT Fan Recommendation (Check one):

OFF: ______ Running: ________

RHRSW Flow Recommendation (Check one):

Cooling Tower Bypassed: ____ Flow Through Cooling Tower: _____

JOB PERFORMANCE MEASURE Work Instruction WI 5.14 Job Performance Measures Rev 10 Job Position RO No.

JP-OP-315-0004-101 Revision 0

JPM Title Perform Jet Pump Operability Test Duration 20 minutes*

Page 1

  • 2 times Duration for ILO Exams Examinee:

SRO / RO Evaluator:

Validating Representatives Name: ____C. Chambers_______________

JPM Type:

Normal / Alternate Path / Time Critical Start Time Evaluation Method:

Perform / Walkthrough / Discuss Stop Time Location:

Plant / Simulator / Classroom Total Time:

PERFORMANCE EVALUATION

SUMMARY

Element S

U Comment Element S

U Comment Element S

U Comment

  • 1.
  • 9.
  • 17.
  • 2.
10.
  • 18.
  • 3.
  • 11.
  • 19.
  • 4.
  • 12.
  • 20.
  • 5.
  • 13.
  • 21.
  • 6.
  • 14.
  • 22.
7.
15.
  • 23.
8.
16.
  • 24.
25.

OPERATOR FUNDAMENTALS OBSERVATION Monitor operator fundamentals during the JPM set. Rate each area based on the criteria by placing a checkmark in the appropriate column. Indicate the comment number associated with the observation.

Operator Fundamental Meets all Expectations Opportunity for Improvement Does not meet Expectations Comment Number Monitoring Control Conservatism Teamwork Knowledge OVERALL EVALUATOR COMMENTS:

REMEDIAL CONTENT:

______ PASS

______ FAIL Evaluator Signature / Date:

/

JOB PERFORMANCE MEASURE JPM Title Perform Jet Pump Operability Test No.: JP-OP-315-0004-101 Revision: 0 Page 2 Work Instruction WI 5.14 Job Performance Measures Rev 10 JPM Observation Criteria Fundamental Meets all Expectations Opportunity for Improvement Does not meet Expectations Monitoring Equipment status monitored at proper frequency, using multiple means if available.

Understood which indications were critical.

Some monitoring was performed but undue focus on task or lack of system knowledge prevented ideal monitoring.

Did not recognize key equipment status indicators, too much focus on single indications and ignored total system status.

Control Task preview used to prepare for job. Aware of control bands and maintained them.

Configuration control maintained.

Adequate control of system maintained throughout task but some improvements could be made such as better manual control or greater depth of knowledge for anticipating system response.

No anticipation of results of actions. Unaware or control bands or not able to maintain them. Lack of knowledge of how to control system parameters.

Conservatism Low threshold for identification of problems.

Questioning attitude. Uses stop when unsure if needed. Sensitive to nuclear safety.

Some opportunities existed to question before proceeding, High focus on task completion without consideration for other system affects.

Proceeds even when unsure with unanswered questions.

High threshold for problem conditions.

Teamwork Routinely communicates system status changes to the team. Communicates actions before taking them.

Communicated most status and actions. Some improvement would be warranted.

Routinely takes action without informing the team.

Knowledge Able to anticipate system response based on solid system knowledge. Good working knowledge of generic fundamentals to predict and monitor system response.

Plant, system, or generic fundamental knowledge has some gaps.

Unable to predict system response, unsure of generic fundamentals concepts related to plant operation.

Only relied on procedure for operating knowledge.

JOB PERFORMANCE MEASURE JPM Title Perform Jet Pump Operability Test No.: JP-OP-315-0004-101 Revision: 0 Page 3 Work Instruction WI 5.14 Job Performance Measures Rev 10 JPM Information System:

B3100 - Reactor Recirculation System Task:

02B3100049 - Perform Jet Pump Operability Test

References:

Required (R) / Available (A) 23.138.06, Jet Pump Operability Test (R)

Tools and Equipment Required:

None Initial Conditions:

You are an extra operator on shift.

The plant is operating at 100% power.

Initiating Cue(s):

The CRS directs you to perform Surveillance Procedure 24.138.06, Jet Pump Operability Test, sections 5.1, 5.2, and 5.5.

The 24.138.06 Excel spreadsheet is NOT available.

All section 4.0 prerequisites are met.

Utilize provided panel indication photos for data.

An operator in the Relay Room has reported individual Jet Pump indications.

Terminating Cue(s):

Surveillance complete, all data properly recorded and acceptance criteria evaluated.

Task Standard:

Perform Surveillance Procedure 24.138.06, Jet Pump Operability Test and evaluate data for compliance with acceptance criteria.

Licensed Operator Exam Information (Required for NRC Exams Only)

Safety Function:

N/A K/A

Reference:

(from NUREG 1123)

K/A SYSTEM: Generic K/A STATEMENT:

G2.2.12 Knowledge of Surveillance Procedures.. 3.7 / 4.1 Maintenance Rule Safety Classification:

B2100-05 Maintenance Rule Risk Significant? (Yes or No)

Yes

JOB PERFORMANCE MEASURE JPM Title Perform Jet Pump Operability Test No.: JP-OP-315-0004-101 Revision: 0 Page 4 Work Instruction WI 5.14 Job Performance Measures Rev 10 PERFORMANCE EVALUATION Start Time ELEMENT STANDARD CUE:

Provide examinee with Cue Sheet, procedure copy, calculator, and photos of recorders and instruments.

  • 1. [5.1.1] Record operating value of Recirculation Loop A Drive Flow from B31-R614, Recirc Loops Flow Recorder, Blue Pen.
  • 1. Refers to photo of B31-R614, records loop A drive flow value, and initials procedure.
  • 2. [5.1.2] Record operating value of Recirculation Pump A Speed from C32-K816, FW and RR Flat Panel Display.
  • 2. Refers to photo of C32-K816, FW and RR Flat Panel Display, records loop A speed value, and initials procedure.
  • 3. [5.1.3] Record operating value of Recirculation Loop B Drive Flow from B31-R614, Recirc Loops Flow Recorder, Red Pen.
  • 3. Refers to photo of B31-R614, records loop B drive flow value, and initials procedure.
  • 4. [5.1.4] Record operating value of Recirculation Pump B Speed from C32-K816, FW and RR Flat Panel Display.
  • 4. Refers to photo of C32-K816, FW and RR Flat Panel Display, records loop B speed value, and initials procedure.
  • 5. [5.1.5] Using the data from Steps 5.1.1 and 5.1.2, plot and verify point is between -10%

and +10% curve on Attachment 1.

  • 5. Refers to attachment 1, plots data from 5.1.1 and 5.1.2 and verifies point is between -10%

and +10% curve. Determines the plot meets the acceptance criteria and initials procedure.

  • 6. [5.1.6] Using the data from Steps 5.1.1 and 5.1.2, plot and verify point is between -10%

and +10% curve on Attachment 2.

  • 6. Refers to attachment 2, plots data from 5.1.3 and 5.1.4 and verifies point is between -10%

and +10% curve. Determines the plot meets the acceptance criteria and initials procedure.

7. [5.1.7] Record Reactor power.
7. Records current reactor power (from cue sheet), and initials procedure.
8. [5.1.8] Record test personnel.
8. Records printed name, initials, and signature.
  • 9. [5.2.1] Record total core flow indication from B21-R613, Reactor Core DP & Jet Pump Total Flow Rec, Red Pen.
  • 9. Refers to photo of B31-R613, records total core flow value, and initials procedure.
10. [5.2.2] Record core differential pressure from B21-R613, Reactor Core DP & Jet Pump Total Flow Rec, Blue Pen.
10. Refers to photo of B31-R613, records core dP value, and initials procedure.
  • 11. [5.2.3] Record Recirculation Loop A Drive Flow from B31-R614, Recirc Loops Flow Recorder, Blue Pen.
  • 11. Refers to photo of B31-R614, records loop A drive flow value, and initials procedure.
  • 12. [5.2.4] Record Recirculation Loop B Drive Flow from B31-R614, Recirc Loops Flow Recorder, Red Pen.
  • 12. Refers to photo of B31-R614, records loop B drive flow value, and initials procedure.

JOB PERFORMANCE MEASURE JPM Title Perform Jet Pump Operability Test No.: JP-OP-315-0004-101 Revision: 0 Page 5 Work Instruction WI 5.14 Job Performance Measures Rev 10

  • 13. [5.2.5] Calculate Total Recirculation Loop Drive Flow below by adding recorded values of Recirculation Loop A and Loop B Drive Flows.
  • 13. Calculate Total Recirculation Loop Drive Flow, records result, and initials procedure.
  • 14. [5.2.6] Using the data from Steps 5.2.1 and 5.2.5, plot and verify point is between -10%

and +10% curve on Attachment 3.

  • 14. Refers to attachment 3, plots data from 5.2.1 and 5.2.5 and verifies point is between -10%

and +10% curve. Determines the plot meets the acceptance criteria and initials procedure.

15. [5.2.7] Record Reactor power and Rod Line.
15. Records current reactor power (from cue sheet), and initials procedure.
16. [5.2.8] Record test personnel.
16. Records printed name, initials, and signature.

NOTE: Data for Table 1 (step 5.5.1) and table 2 (step 5.5.5) may be gathered at the same time

  • 17. [5.5.1] Record individual percent dP indications for Jet Pumps 11 through 20 in Table 1 (RR H11-P619).
  • 17. Refers to photo of RR H11-P619, records individual Jet Pump dP indications in applicable table, and initials procedure.
  • 18. [5.5.2] Calculate and record Recirculation Loop A Average dP (Average A) by adding dP values recorded in TABLE 1 for Jet Pumps 11 through 20 and dividing sum by 10.
  • 18. Calculates and records loop A average Jet Pump dP, and initials procedure.
  • 19. [5.5.3] Calculate and record in TABLE 1, percent deviation from Loop Average for Jet Pumps 11 through 20.
  • 19. Calculates and records loop A percent deviation for each Jet Pump, and initials procedure.
  • 20. [5.5.3] Using the deviation from Average %

points recorded on Table 1, plot and verify all points are between -20% and +20% points on Attachment 5.

  • 20. Refers to attachment 5, plots data Table 1 and verifies all points are between -20% and

+20% points on attachment 5. Determines the plots meet the acceptance criteria and initials procedure.

NOTE: Data for Table 2 may have been previously recorded when step 5.5.1 was performed.

  • 21. [5.5.5] Record individual percent dP indications for Jet Pumps 1 through 10 in Table 2 (RR H11-P619).
  • 21. Refers to photo of RR H11-P619, records individual Jet Pump dP indications in applicable table, and initials procedure.
  • 22. [5.5.6] Calculate and record Recirculation Loop B Average dP (Average B) by adding dP values recorded in TABLE 2 for Jet Pumps 1 through 10 and dividing sum by 10.
  • 22. Calculates and records loop B average Jet Pump dP, and initials procedure.
  • 23. [5.5.7] Calculate and record in TABLE 2, percent deviation from Loop Average for Jet Pumps 1 through 10.
  • 23. Calculates and records loop B percent deviation for each Jet Pump, and initials procedure.
  • 24. [5.5.8] Using the deviation from Average %

points recorded on Table 2, plot and verify all points are between -20% and +20% points on Attachment 6.

  • 24. Refers to attachment 6, plots data Table 2 and verifies all points are between -20% and

+20% points on attachment 6. Determines the plots meet the acceptance criteria and initials procedure.

JOB PERFORMANCE MEASURE JPM Title Perform Jet Pump Operability Test No.: JP-OP-315-0004-101 Revision: 0 Page 6 Work Instruction WI 5.14 Job Performance Measures Rev 10

25. [5.5.9] Record test personnel.
25. Records printed name, initials, and signature.

CUE: Stop the JPM when the surveillance has been completed for sections 5.1, 5.2, and 5.5.

______ SATISFACTORY

______ UNSATISFACTORY Stop Time

  • Critical Step

JOB PERFORMANCE MEASURE JPM Title Perform Jet Pump Operability Test No.: JP-OP-315-0004-101 Revision: 0 Page 7 Work Instruction WI 5.14 Job Performance Measures Rev 10 Evaluator Notes:

ENSURE ALL INDUSTRIAL AND PERSONNEL SAFETY PRACTICES ARE USED AND ENFORCED AT ALL TIMES.

FAILURE TO WEAR ALL PPE REQUIRED FOR TASK PERFORMANCE WILL RESULT IN FAILURE OF THIS JPM.

Generic Notes and Cues:

CMC switches will turn RED and amperage will increase when the switch is rotated to the start position started. The current should initially be five to seven times the normal running amps with the ammeter flashing. As counter EMF is developed, the amperage will lower to the normal running amperage and the ammeter will no longer flash. CMC switches will turn GREEN when the pumps are stopped and amperage will decrease to zero.

Remotely operated valve position is determined with open and close indicating lights. A RED light only would indicate that the valve is open. A GREEN light only would indicate that the valve is closed. Dual indication would indicate that the valve is in some intermediate position.

System Specific Notes and Cues:

None Task Performance and Cues:

The Elements of this JPM are step by step in accordance with the procedure. The Standard is that the procedure is performed as written. The Cues are as listed above for indication or as each step is completed the appropriate information is reported to the examinee.

Critical Steps:

Critical Tasks are identified by asterisk (*) and bolded steps on the cover sheet. Verify that the latest revision of the procedure is used and critical tasks are correctly identified.

JOB PERFORMANCE MEASURE JPM Title Perform Jet Pump Operability Test No.: JP-OP-315-0004-101 Revision: 0 Page 8 Work Instruction WI 5.14 Job Performance Measures Rev 10 FOLLOW-UP DOCUMENTATION QUESTIONS Reason for follow-up question(s):

Question:

Response

Question:

Reference

Response

JOB PERFORMANCE MEASURE JPM Title Perform Jet Pump Operability Test No.: JP-OP-315-0004-101 Revision: 0 Page 9 Work Instruction WI 5.14 Job Performance Measures Rev 10 Simulator Setup N/A IC#:

Malfunctions:

Number Title Value Delay Ramp None Remote Functions:

Number Title Value Delay Ramp Override Functions (Setup Steps):

Number Title Value Delay Ramp Override Functions (JPM Steps):

Number Title Value Delay Ramp Notes:

Special Instructions:

JOB PERFORMANCE MEASURE Cue Sheet: (JP-OP-315-0004-101)

Initial Conditions:

  • You are an extra operator on shift
  • The plant is operating at 100% power Initiating Cue(s):

The CRS directs you to perform Surveillance Procedure 24.138.06, Jet Pump Operability Test, sections 5.1, 5.2, and 5.5 for current plant conditions.

  • The 24.138.06 Excel spreadsheet is NOT available.
  • All section 4.0 prerequisites are met.
  • Utilize provided panel indication photos for data.
  • An operator in the Relay Room has reported individual Jet Pump indications.

JOB PERFORMANCE MEASURE

JOB PERFORMANCE MEASURE Jet Pump Data Reported by Relay Room Operator Jet Pump Indicator dP (%)

Jet Pump Indicator dP (%)

1 B21-R608B 34 11 B21-R608A 32 2

B21-R608D 34 12 B21-R608C 29 3

B21-R608F 32 13 B21-R608E 31 4

B21-R608H 30 14 B21-R608G 28 5

B21-R608K 32 15 B21-R608J 32 6

B21-R608M 34 16 B21-R608L 31 7

B21-R608P 30 17 B21-R608N 29 8

B21-R608S 30 18 B21-R608R 30 9

B21-R608U 32 19 B21-R608T 28 10 B21-R608W 32 20 B21-R608V 30

JOB PERFORMANCE MEASURE

JOB PERFORMANCE MEASURE

EVALUATOR KEY FOR TRAINING USE ONLY Plant Technical Procedure - Fermi 2 24.138.06 Surveillance Procedure Revision 47 Continuous Use Page 1 Information and Procedures DTC TPNPP DSN 24.138.06 Revision 47 Date Issued DCR#

20-0065 File #

1703.02 IP I

ISFSI N

Recipient JET PUMP OPERABILITY TEST Revision Summary

1)

Revised Step 1.1 deleting Frequency statement to align procedure with WG-001.

2)

Updated ARMs Stamp per WG-001, no rev bar used.

Attachments 1

050914 Reactor Recirc Pump A Speed Versus Drive Flow Curves 2

050914 Reactor Recirc Pump B Speed Versus Drive Flow Curves 3

050914 Total Recirculation Drive Flow Versus Two Loop Total Core Flow 4

050914 Active Loop Drive Flow Versus Single Loop Total Core Flow 5

050914 Jet Pump Differential Pressure Deviation From Average - Loop A 6

050914 Jet Pump Differential Pressure Deviation From Average - Loop B Enclosures

24.138.06 Revision 47 Page 2 A

041716 Planning and Preparation B

070700 Impact Statement

24.138.06 Revision 47 Page 3 1.0 PURPOSE 1.1 To demonstrate the operability of all installed jet pumps.

Tech Spec:

SR 3.4.2.1 Applicability:

Modes 1 and 2 Testing Mode:

Mode 1 or 2 Section:

Two Loop Operation - 5.1, 5.2, 5.5 Single Loop Operation - 5.3, 5.4, 5.5 Note:

1) This surveillance is not required to be performed until 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> after associated recirculation loop is in operation.
2) Not required to be performed until 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after exceeding 25% of rated thermal power.

2.0 PRECAUTIONS AND LIMITATIONS 2.1 For constant recirculation loop drive flow, jet pump flow inherently fluctuates as a result of feedback effects between lower plenum and jet pumps (jet pump noise). Pump vortexing, differential pressure (dP) variations of about 3 to 4 times the normal dP variation, may also exist.

2.1.1 Relative time to observe jet pump noise and jet pump vortexing varies. Jet pump noise occurs over 30 seconds to one minute. Jet pump vortexing (if it exists) occurs randomly. Normally, approximately 20 seconds per jet pump indicator is required to obtain a reading. If vortexing is occurring/suspected, time period may increase.

2.1.2 For jet pump average dP pressure, take the average of maximum and minimum values observed if jet pump vortexing is occurring.

2.2 During single loop operations at high Recirculation Pump speed, the outer jet pumps (Jet Pumps 1, 2, 9, 10, 11, 12, 19, and 20) dP indication tends to be noisy. Should problems occur in meeting Section 5.5 acceptance criteria, contact System Engineering for assistance.

2.3 The core flow summer is not calibrated to be accurate for single recirculation loop operation with Active loop drive flow less than 21,500 gpm. When operating below 21,500 gpm in the active loop, Section 5.4 shall not be performed.

24.138.06 Revision 47 Page 4 3.0 REQUIRED EQUIPMENT - None 4.0 PREREQUISITES 4.1 Verify that reactor is operating with steady state recirculation flow for duration of data acquisition.

INITIALS 4.2 Verify Jet Pumps (1 - 10) Loop B flow and Jet Pumps (11 - 20) Loop A flow are matched if in two loop operation. Otherwise, N/A this step.

INITIALS 4.3 Verify Post Accident Sampling System sampling is not in progress.

INITIALS

24.138.06 Revision 47 Page 5 5.0 PROCEDURE NOTE (1): The preferred methods to obtain Loop Drive Flows are from Recirculation Loop Flow Recorders, B31-R614 blue pen and B31-R614 red pen. Drive Flow Indicators, B31-R613 and B31-R617, may be used as an alternate indication if the flow recorders are unavailable.

NOTE (2): The preferred method to obtain Total Core Flow is from the Flow Recorder B21-R613 red pen. The IPCS Core Power and Flow Report may be used to indicate Total Core Flow as an alternate method. Ensure WT flag = 2 when using IPCS.

NOTE (3): The preferred method to obtain Core Differential Pressure is from recorder B21-R613 Blue Pen. The IPCS Core Power and Flow Report may be used to indicate Core Differential Pressure as an alternate method.

NOTE (4): Sections 5.1, 5.2, 5.3, 5.4, and 5.5 may be performed in any order.

5.1 Two Recirculation Loop Drive Flow Deviation Verification NOTE (1): This section is only applicable in two loop operation. If not applicable, steps may be marked N/A.

NOTE (2): All indications are on COP H11-P603.

5.1.1 Record operating value of Recirculation Loop A Drive Flow from B31-R614, Recirc Loops Flow Recorder, Blue Pen.

kgpm INITIALS 5.1.2 Record operating value of Recirculation Pump A Speed from C32-K816, FW and RR Flat Panel Display.

INITIALS

24.138.06 Revision 47 Page 6 5.1.3 Record operating value of Recirculation Loop B Drive Flow from B31-R614, Recirc Loops Flow Recorder, Red Pen.

kgpm INITIALS 5.1.4 Record operating value of Recirculation Pump B Speed from C32-K816, FW and RR Flat Panel Display.

INITIALS 5.1.5 Using the data from Steps 5.1.1 and 5.1.2, plot and verify point is between -10%

and +10% curve on Attachment 1.

ACCEPTANCE CRITERIA INITIALS 5.1.6 Using the data from Steps 5.1.3 and Step 5.1.4, plot and verify point is between

-10% and +10% curve on Attachment 2.

ACCEPTANCE CRITERIA INITIALS 5.1.7 Record Reactor power below:

INITIALS 5.1.8 Record test personnel.

Printed Name Initials Signatures

24.138.06 Revision 47 Page 7 5.2 Two Recirculation Loop Total Core Flow Deviation Verification NOTE (1): This section is only applicable in two loop operation. If not applicable, steps may be marked N/A.

NOTE (2): All indicators are on COP H11-P603.

5.2.1 Record total core flow indication from B21-R613, Reactor Core DP & Jet Pump Total Flow Rec, Red Pen.

Mlb/hr INITIALS 5.2.2 Record core differential pressure from B21-R613, Reactor Core DP & Jet Pump Total Flow Rec, Blue Pen.

psid INITIALS 5.2.3 Record Recirculation Loop A Drive Flow from B31-R614, Recirc Loops Flow Recorder, Blue Pen.

kgpm INITIALS 5.2.4 Record Recirculation Loop B Drive Flow from B31-R614, Recirc Loops Flow Recorder, Red Pen.

kgpm INITIALS 5.2.5 Calculate Total Recirculation Loop Drive Flow below by adding recorded values of Recirculation Loop A and Loop B Drive Flows.

Loop A Loop B kgpm +

kgpm =

kgpm (Step 5.2.3)

(Step 5.2.4)

INITIALS

24.138.06 Revision 47 Page 8 5.2.6 Using the data from Steps 5.2.1 and 5.2.5, plot and verify point is between -10%

and +10% curve on Attachment 3.

ACCEPTANCE CRITERIA INITIALS 5.2.7 Record Reactor power and rod line below:

Reactor Power:

Rod Line:

INITIALS 5.2.8 Record test personnel Printed Name Initials Signature

24.138.06 Revision 47 Page 9 5.3 Single Recirculation Loop Drive Flow Deviation Verification NOTE (1): This section is only applicable in single loop operation. If not applicable, steps may be marked N/A.

NOTE (2): All indications are on COP H11-P603.

5.3.1 Record operating loop value of Recirculation Drive Flow from B31-R614, Recirc Loops Flow Recorder.

Operating Loop:

Recirc Loop Flow:

kgpm INITIALS 5.3.2 Record operating value of Recirculation Pump Speed from C32-K816, FW and RR Flat Panel Display.

Operating Loop:

Recirc Pump Speed:

INITIALS 5.3.3 Using the data from Steps 5.3.1 and Step 5.3.2, plot and verify point is between

-10% and +10% curve on Attachment 1 or 2, as applicable.

ACCEPTANCE CRITERIA INITIALS 5.3.4 Record Reactor power below.

INITIALS 5.3.5 Record test personnel.

Printed Name Initials Signatures

24.138.06 Revision 47 Page 10 5.4 Single Recirculation Loop Total Core Flow Deviation Verification NOTE (1): This section is only applicable in single loop operation. If not applicable, steps may be marked N/A.

NOTE (2): All indicators are on COP H11-P603.

NOTE (3): The core flow summer is not calibrated to be accurate for single recirculation loop operation with Active loop drive flow less than 21,500 gpm. When operating below 21,500 gpm in the active loop, Section 5.4 shall not be performed.

5.4.1 Record total core flow indication from B21-R613, Reactor Core DP & Jet Pump Total Flow Rec, Red Pen.

Mlb/hr INITIALS 5.4.2 Record operating recirculation loop drive flow from B31-R614, Recirc Loops Flow Recorder.

kgpm INITIALS 5.4.3 Using the data from Steps 5.4.1 and 5.4.2, plot and verify point is between -10%

and +10% curve on Attachment 4.

ACCEPTANCE CRITERIA INITIALS 5.4.4 Record Reactor thermal power and rod line below.

Reactor Power:

Rod Line:

INITIALS

24.138.06 Revision 47 Page 11 5.4.5 Record test personnel Printed Name Initials Signature

24.138.06 Revision 47 Page 12 5.5 Jet Pump Differential Pressure Deviation Verification NOTE (1): Data for Tables 1 and 2 may be gathered at the same time.

NOTE (2): Steps 5.5.1 through 5.5.4 are only required if the Recirculation Loop A is in operation. Otherwise, N/A these steps.

5.5.1 Record individual percent dP indications for Jet Pumps 11 through 20 in Table 1 (RR H11-P619).

INITIALS TABLE 1 Recirculation Loop A Jet Pump #

Indicator PIS #

Symbol dP (%)

Deviation from Average

(%)

11 B21-R608A JP11 12 B21-R608C JP12 13 B21-R608E JP13 14 B21-R608G JP14 15 B21-R608J JP15 16 B21-R608L JP16 17 B21-R608N JP17 18 B21-R608R JP18 19 B21-R608T JP19 20 B21-R608V JP20 5.5.2 Calculate and record Recirculation Loop A Average dP (Average A) by adding dP values recorded in TABLE 1 for Jet Pumps 11 through 20 and dividing sum by 10.

(

)

/10 =

Sum (Table 1)

Average A INITIALS 5.5.3 Calculate and record in TABLE 1, percent deviation from Loop Average for Jet Pumps 11 through 20, using the following equation:

[(Jet Pump dP - Average A)/(Average A)] x 100 INITIALS

24.138.06 Revision 47 Page 13 5.5.4 Using the deviation from Average % points recorded on Table 1, plot and verify all points are between -20% and +20% points on Attachment 5.

ACCEPTANCE CRITERIA INITIALS NOTE: Steps 5.5.5 through 5.5.8 are only required if the Recirculation Loop B is in operation. Otherwise, N/A these steps.

5.5.5 Record individual percent dP indications for Jet Pumps 1 through 10 in Table 2 (RR H11-P619).

INITIALS TABLE 2 Recirculation Loop B Jet Pump #

Indicator PIS #

Symbol dP (%)

Deviation from Average (%)

1 B21-R608B JP1 2

B21-R608D JP2 3

B21-R608F JP3 4

B21-R608H JP4 5

B21-R608K JP5 6

B21-R608M JP6 7

B21-R608P JP7 8

B21-R608S JP8 9

B21-R608U JP9 10 B21-R608W JP10 5.5.6 Calculate and record Recirculation Loop B Average dP (Average B) by adding dP values recorded in Table 2 for Jet Pumps 1 through 10 and dividing sum by 10.

(

)

/10 =

Sum (Table 2)

Average B INITIALS 5.5.7 Calculate and record in Table 2, percent deviation from Loop Average for Jet Pumps 1 through 10, using the following equation:

[(Jet Pump dP - Average B)/(Average B)] x 100 INITIALS

24.138.06 Revision 47 Page 14 5.5.8 Using the deviation from Average % points recorded on Table 2, plot and verify all points are between -20% and +20% points on Attachment 6.

ACCEPTANCE CRITERIA INITIALS 5.5.9 Record test personnel Printed Name Initials Signature

24.138.06 Revision 47 Page 15 6.0 INDEPENDENT VERIFICATION - None 7.0 ACCEPTANCE CRITERIA NOTE: Acceptance Criteria shall be reviewed by STA or an SRO other than test performer.

7.1 Verification of the following meets requirements of SR 3.4.2.1.

7.1.1 All calculations are correct.

7.1.2 Two of the following have been satisfactorily completed (check sections completed).

1.

Section 5.1 (Two loop operation only)

2.

Section 5.2 (Two loop operation only)

3.

Section 5.3 (Single loop operation only)

4.

Section 5.4 (Single loop operation only)

5.

Section 5.5 Delegated Reviewer Signature Date END OF TEXT

24.138.06, Page 1 of 1 050914 REACTOR RECIRC PUMP A SPEED VERSUS DRIVE FLOW CURVES 10 15 20 25 30 35 40 45 50 55 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 PUMP A DRIVE FLOW (KGPM)

PUMP A SPEED (%)

24.138.06, Page 1 of 1 050914 REACTOR RECIRC PUMP B SPEED VERSUS DRIVE FLOW CURVES 10 15 20 25 30 35 40 45 50 55 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 PUMP B DRIVE FLOW (KGPM)

PUMP B SPEED (%)

24.138.06, Page 1 of 1 050914 TOTAL RECIRCULATION DRIVE FLOW VERSUS TWO LOOP TOTAL CORE FLOW 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 Total Core Flow (Mlbs/hr)

Total Recirculation Drive Flow (KGPM)

24.138.06, Page 1 of 1 050914 ACTIVE LOOP DRIVE FLOW VERSUS SINGLE LOOP TOTAL CORE FLOW 30 35 40 45 50 55 20 22 24 26 28 30 32 34 36 38 40 TOTAL CORE FLOW (Mlbm/hr)

ACTIVE LOOP DRIVE FLOW (x1000 gpm)

+ 10%

Curve

-10% Curve

24.138.06, Page 1 of 1 050914 JET PUMP DIFFERENTIAL PRESSURE DEVIATION FROM AVERAGE - LOOP A

-35

-30

-25

-20

-15

-10

-5 0

5 10 15 20 25 30 35 11 12 13 14 15 16 17 18 19 20 Deviation From Average %

Jet Pump Number

+20% Curve

-20% Curve

24.138.06, Page 1 of 1 050914 JET PUMP DIFFERENTIAL PRESSURE DEVIATION FROM AVERAGE - LOOP B

-30

-25

-20

-15

-10

-5 0

5 10 15 20 25 30 1

2 3

4 5

6 7

8 9

10 Deviation From Average %

Jet Pump Number

+20% Curve

-20% Curve

JOB PERFORMANCE MEASURE Work Instruction WI 5.14 Job Performance Measures Rev 10 Job Position RO No.

JP-OP-802-4101-454 Revision 0

JPM Title Calculate Offgas Release Rate During Fuel Failure Duration 15 minutes*

Page 1

  • 2 times Duration for ILO Exams Examinee:

SRO / RO Evaluator:

Validating Representatives Name: __John Holdwick/Chris Chambers/Art Snowberger__________

JPM Type:

Normal / Alternate Path / Time Critical Start Time Evaluation Method:

Perform / Walkthrough / Discuss Stop Time Location:

Plant / Simulator / Classroom Total Time:

PERFORMANCE EVALUATION

SUMMARY

Element S

U Comment Element S

U Comment Element S

U Comment

  • 1.
  • 2.
  • 3.
  • 4.
  • 5.

OPERATOR FUNDAMENTALS OBSERVATION Monitor operator fundamentals during the JPM set. Rate each area based on the criteria by placing a checkmark in the appropriate column. Indicate the comment number associated with the observation.

Operator Fundamental Meets all Expectations Opportunity for Improvement Does not meet Expectations Comment Number Monitoring Control Conservatism Teamwork Knowledge OVERALL EVALUATOR COMMENTS:

REMEDIAL CONTENT:

______ PASS

______ FAIL Evaluator Signature / Date:

/

JOB PERFORMANCE MEASURE JPM Title Calculate Offgas Release Rate During Fuel Failure No.: JP-OP-802-4101-454 Revision: 0 Page 2 Work Instruction WI 5.14 Job Performance Measures Rev 10 JPM Observation Criteriaj Fundamental Meets all Expectations Opportunity for Improvement Does not meet Expectations Monitoring Equipment status monitored at proper frequency, using multiple means if available.

Understood which indications were critical.

Some monitoring was performed but undue focus on task or lack of system knowledge prevented ideal monitoring.

Did not recognize key equipment status indicators, too much focus on single indications and ignored total system status.

Control Task preview used to prepare for job. Aware of control bands and maintained them.

Configuration control maintained.

Adequate control of system maintained throughout task but some improvements could be made such as better manual control or greater depth of knowledge for anticipating system response.

No anticipation of results of actions. Unaware or control bands or not able to maintain them. Lack of knowledge of how to control system parameters.

Conservatism Low threshold for identification of problems.

Questioning attitude. Uses stop when unsure if needed. Sensitive to nuclear safety.

Some opportunities existed to question before proceeding, High focus on task completion without consideration for other system affects.

Proceeds even when unsure with unanswered questions.

High threshold for problem conditions.

Teamwork Routinely communicates system status changes to the team. Communicates actions before taking them.

Communicated most status and actions. Some improvement would be warranted.

Routinely takes action without informing the team.

Knowledge Able to anticipate system response based on solid system knowledge. Good working knowledge of generic fundamentals to predict and monitor system response.

Plant, system, or generic fundamental knowledge has some gaps.

Unable to predict system response, unsure of generic fundamentals concepts related to plant operation.

Only relied on procedure for operating knowledge.

JOB PERFORMANCE MEASURE JPM Title Calculate Offgas Release Rate During Fuel Failure No.: JP-OP-802-4101-454 Revision: 0 Page 3 Work Instruction WI 5.14 Job Performance Measures Rev 10 JPM Information System:

NA Task:

References:

Required (R) / Available (A) 20.000.07, Fuel Cladding Failure (R)

Fermi 2 Tech Spec 3.7.5 (R)

Tools and Equipment Required:

Calculator Initial Conditions:

The plant is operating at 100% power.

You are the CRLNO.

A fuel cladding failure has occurred, and the crew has entered 20.000.07, Fuel Cladding Failure.

Initiating Cue(s):

The CRS directs you to calculate Offgas radioactivity release rate and determine if the Tech Spec 3.7.5 LCO value has been exceeded.

Terminating Cue(s):

Offgas release rate has been calculated and TS LCO 3.7.5 compliance evaluated Task Standard:

Offgas release rate is calculated in accordance with AOP 20.000.07 and the Offgas Log Radiation Monitors Conversion Factors For Technical Specifications 3.7.5 posted worksheet; and verified within Tech Spec LCO 3.7.5 required value.

Licensed Operator Exam Information (Required for NRC Exams Only)

Safety Function:

9 - Radioactivity Release K/A

Reference:

(from NUREG 1123)

K/A SYSTEM: Generic 2.3 - Radiation Control K/A STATEMENT:

2.3.5 Ability to use radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc........................... 2.9 / 2.9 Maintenance Rule Safety Classification:

NA Maintenance Rule Risk Significant? (Yes or No)

NA

JOB PERFORMANCE MEASURE JPM Title Calculate Offgas Release Rate During Fuel Failure No.: JP-OP-802-4101-454 Revision: 0 Page 4 Work Instruction WI 5.14 Job Performance Measures Rev 10 PERFORMANCE EVALUATION Start Time ELEMENT STANDARD CUE:

Provide Examinee with Cue Sheets and copy of 20.000.07

  • 1.

[Condition B Note 1] To obtain mCi/sec use the Off Gas Log Radiation Monitors Conversion Factors sheet (posted on the rear of the H11-P601).

  • 1.

Refers to the Offgas Log Radiation Monitors Conversion Factors For Technical Specifications 3.7.5 sheet.

  • 2.

Obtain readings from Offgas Rad Monitors D11-K601A & B

  • 2.

Obtains readings from Offgas Rad Monitors D11-K601A & B.

  • 3.

Obtain reading from N62-R808, Outlet Flow Recorder, Charcoal Unit Flow

  • 3.

Obtains reading from N62-R808, Outlet Flow Recorder, Charcoal Unit Flow

  • 4.

Calculates Offgas Release Rate using mCi/sec = (conversion factor) X (rad monitor reading) X (offgas flow rate)

  • 4.

Calculates Offgas Release Rate:

Rad Monitor A 0.68 mCi/sec = (2.703E-4) X (200 mr/hr)

X (12.63 scfm)

Rad Monitor B 0.68 mCi/sec = (2.403E-4) X (223 mr/hr)

X (12.63 scfm)

  • 5.

Evaluates Offgas Release Rate per TS LCO 3.7.5

  • 5.

Evaluates Offgas Release Rate per TS LCO 3.7.5, and determines release rate is below the TS limit of 340 mCi/sec CUE:

End JPM when Offgas release rates have been calculated and TS limit evaluated.

______ SATISFACTORY

______ UNSATISFACTORY Stop Time

  • Critical Step

JOB PERFORMANCE MEASURE JPM Title Calculate Offgas Release Rate During Fuel Failure No.: JP-OP-802-4101-454 Revision: 0 Page 5 Work Instruction WI 5.14 Job Performance Measures Rev 10 Evaluator Notes:

ENSURE ALL INDUSTRIAL AND PERSONNEL SAFETY PRACTICES ARE USED AND ENFORCED AT ALL TIMES.

FAILURE TO WEAR ALL PPE REQUIRED FOR TASK PERFORMANCE WILL RESULT IN FAILURE OF THIS JPM.

Generic Notes and Cues:

None System Specific Notes and Cues:

None Task Performance and Cues:

The Elements of this JPM are step by step in accordance with the procedure. The Standard is that the procedure is performed as written. The Cues are as listed above for indication or as each step is completed the appropriate information is reported to the examinee.

Critical Steps:

Critical Tasks are identified by asterisk (*) and bolded steps on the cover sheet. Verify that the latest revision of the procedure is used and critical tasks are correctly identified.

JOB PERFORMANCE MEASURE JPM Title Calculate Offgas Release Rate During Fuel Failure No.: JP-OP-802-4101-454 Revision: 0 Page 6 Work Instruction WI 5.14 Job Performance Measures Rev 10 FOLLOW-UP DOCUMENTATION QUESTIONS Reason for follow-up question(s):

Question:

Reference:

Response

Question:

Reference

Response

JOB PERFORMANCE MEASURE JPM Title Calculate Offgas Release Rate During Fuel Failure No.: JP-OP-802-4101-454 Revision: 0 Page 7 Work Instruction WI 5.14 Job Performance Measures Rev 10 Simulator Setup IC#:

20 Malfunctions:

Number Title Value Delay Ramp N/A Remote Functions:

Number Title Value Delay Ramp N/A Override Functions:

Number Title Value Delay Ramp H_P601_C046_1 Log rad monitor recorder channel A 200 0

0 H_P601_C046_2 Log rad monitor recorder channel B 223 0

0 H_P806_C006_2 Offgas flow (charcoal bed) flow recorder 12.63 0

0 Special Instructions:

1. Reset to IC-20 or predetermined IC as desired
2. Execute and trigger JP4101-454 Calculate Release Rate.lsn (N/A if using preset IC)
3. Freeze simulator and perform JPM

JOB PERFORMANCE MEASURE Examiner Reference Sheet Training Use Only Formula:

Offgas Rad Release Rate = Conversion Factor X Offgas Log Rad Monitor Reading X Offgas Flowrate Rad Monitor A conversion factor = 2.703E-4 Rad Monitor A indication = 200 mr/hr Rad Monitor B conversion factor = 2.403E-4 Rad Monitor B indication = 223 mr/hr Rad Monitor A calculation:

(2.703E-4) (200 mr/hr) (12.63 scfm) = 0.683 mCi/sec Rad Monitor B calculation:

(2.403E-4) (223 mr/hr) (12.63 scfm) = 0.677 mCi/sec Tech Spec 3.7.5 required value: 340 mCi/sec

JOB PERFORMANCE MEASURE 78.000.09 Att 3 P1/1 033016 DTC: TGCHEM DSN:

File: 1327.01 IP: I FOR TRAINING USE ONLY Cue Sheet 1: (JP-OP-802-4101-454)

Initial Conditions:

  • The plant is operating at 100% power.
  • You are the CRLNO.

Initiating Cue(s):

The CRS directs you to calculate Offgas radioactivity release rate and determine if the Tech Spec 3.7.5 LCO value has been exceeded.

JOB PERFORMANCE MEASURE 78.000.09 Att 3 P1/1 033016 DTC: TGCHEM DSN:

File: 1327.01 IP: I FOR TRAINING USE ONLY Cue Sheet 2: (JP-OP-802-4101-454)

Training Use Only

JOB PERFORMANCE MEASURE 78.000.09 Att 3 P1/1 033016 DTC: TGCHEM DSN:

File: 1327.01 IP: I FOR TRAINING USE ONLY Cue Sheet 2 (cont.): (JP-OP-802-4101-454)

Training Use Only

JOB PERFORMANCE MEASURE 78.000.09 Att 3 P1/1 033016 DTC: TGCHEM DSN:

File: 1327.01 IP: I FOR TRAINING USE ONLY Cue Sheet 2 (cont.): (JP-OP-802-4101-454)

FOR TRAINING USE ONLY OFFGAS LOG RADIATION MONITORS CONVERSION FACTORS FOR TECHNICAL SPECIFICATIONS 3.7.5 SAMPLE INFORMATION Offgas Radioactivity Rate. 4.29E-01 mCi/sec Offgas System Flow Rate. 12.4 SCFM Offgas Log Rad Monitor D11-K601A Reading. 12.8 mR/hr Offgas Log Rad Monitor D11-K601B Reading. 14.4 mR/hr CONVERSION FACTORS THESE CONVERSION FACTORS ARE TO BE USED TO OBTAIN A mCi/sec RELEASE RATE FROM OFFGAS LOG RADIATION MONITORS.

TO USE CONVERSION FACTORS, MULTIPLY FACTOR BY CURRENT OFFGAS LOG RADIATION MONITOR READING (mr/hr) AND CURRENT OFFGAS FLOW RATE (cfm):

mCi/sec = FACTOR x MONITOR READING x OFFGAS FLOW*

  • Flow as read from N62-R808, O/G Outlet Flow Rec pen labeled Charcoal Unit 1-6.

Performed By Date Approved By Date Chemist/designee Noted By Date SM 2.703E-2.403E-mCi/sec mr/hr x cfm mCi/sec mr/hr x f