MONTHYEARIR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23213A0302023-08-11011 August 2023 Form 5.1-1 Postexamination Check Sheet ML23212A8732023-07-31031 July 2023 Form 1.3-1 Examination Security Checklist ML23200A2182023-06-28028 June 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Final ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis ML23200A2572023-06-19019 June 2023 Form 2.1-1 Examination Prep Checklist ML23200A2562023-06-19019 June 2023 IP 21 Operator Licensing Exam Schedule ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23200A1852023-06-0202 June 2023 Form 2.3-2 Operating Test Quality Checklist ML23200A1862023-06-0202 June 2023 Form 2.3-4 Written Exam Quality Checklist ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 ML23200A2212023-02-0808 February 2023 Form 2.3-1 Outline Quality Checklist ML23200A2162023-01-20020 January 2023 Outline Submittal Letter ML23200A2172023-01-20020 January 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Draft ML22322A1082022-11-18018 November 2022 Confirmation of Initial License Examination ML21258A0602021-09-15015 September 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21327A1702021-06-16016 June 2021 ES-401-6 ML21327A4272021-06-16016 June 2021 Post Exam Submittal Letter ML21327A4252021-06-16016 June 2021 ES-403-1 ML21327A4242021-06-16016 June 2021 ES-201-3 ML21327A4212021-06-16016 June 2021 ES-201-1 ML21327A1062021-06-16016 June 2021 Proposed Exam Submittal Letter ML21327A1042021-06-16016 June 2021 ES-301-4 ML21327A0952021-06-16016 June 2021 ES-301-3 ML21327A0922021-06-16016 June 2021 ES-301-6 ML21326A1242021-06-16016 June 2021 Licensee Outline Submittal Letter ML21326A1212021-06-16016 June 2021 ES-301-5 ML21326A1202021-06-16016 June 2021 ES-201-2 ML21327A3362021-06-16016 June 2021 Handouts to Applicants (Summary) ML21327A3262021-06-16016 June 2021 Administered Written Exam with Answer Key ML21328A1382021-06-16016 June 2021 Proposed Admin JPMs ML21327A3212021-06-16016 June 2021 Administered Scenarios ML21328A1622021-06-16016 June 2021 Proposed Control Room and In-Plant JPMs ML21328A1642021-06-16016 June 2021 Proposed Scenarios ML21328A1662021-06-16016 June 2021 Proposed Written Exam with Answer Key ML21327A3082021-06-16016 June 2021 Administered Admin JPMs ML21327A3422021-06-16016 June 2021 Modified Question Source Information ML21327A3142021-06-16016 June 2021 Administered Control Room and In-Plant JPMs ML21120A0202021-05-0303 May 2021 Operator Licensing Examination Approval IR 05000341/20203022021-03-18018 March 2021 NRC Initial License Examination Report 05000341/2020302 ML22158A1462021-02-0505 February 2021 Fer 2020 Ile ES-301-7 Operating Test Review Worksheet-Final ML22158A1302021-02-0505 February 2021 Fer 2020 ES-201-1 Rev 11 ML22158A1332021-02-0505 February 2021 Fer 2020 Ile Final Es 201-3 ML22158A1382021-02-0505 February 2021 Fer 2020 Ile Es 403-1 RO-SRO Written Exam Grading Quality Checklist ML22158A1582021-02-0505 February 2021 Fer 2020 Ile NRC ES-401-4 Record of Rejected KAs Rev 11 2023-08-16
[Table view] Category:Part 55 Examination Related Material
MONTHYEARIR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23213A0302023-08-11011 August 2023 Form 5.1-1 Postexamination Check Sheet ML23212A8732023-07-31031 July 2023 Form 1.3-1 Examination Security Checklist ML23200A2182023-06-28028 June 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Final ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis ML23200A2572023-06-19019 June 2023 Form 2.1-1 Examination Prep Checklist ML23200A2562023-06-19019 June 2023 IP 21 Operator Licensing Exam Schedule ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23200A1852023-06-0202 June 2023 Form 2.3-2 Operating Test Quality Checklist ML23200A1862023-06-0202 June 2023 Form 2.3-4 Written Exam Quality Checklist ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 ML23200A2212023-02-0808 February 2023 Form 2.3-1 Outline Quality Checklist ML23200A2162023-01-20020 January 2023 Outline Submittal Letter ML23200A2172023-01-20020 January 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Draft ML22322A1082022-11-18018 November 2022 Confirmation of Initial License Examination ML21258A0602021-09-15015 September 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21327A1702021-06-16016 June 2021 ES-401-6 ML21326A1202021-06-16016 June 2021 ES-201-2 ML21326A1212021-06-16016 June 2021 ES-301-5 ML21326A1242021-06-16016 June 2021 Licensee Outline Submittal Letter ML21327A0922021-06-16016 June 2021 ES-301-6 ML21327A0952021-06-16016 June 2021 ES-301-3 ML21327A1042021-06-16016 June 2021 ES-301-4 ML21327A1062021-06-16016 June 2021 Proposed Exam Submittal Letter ML21327A4212021-06-16016 June 2021 ES-201-1 ML21327A4242021-06-16016 June 2021 ES-201-3 ML21327A4252021-06-16016 June 2021 ES-403-1 ML21327A4272021-06-16016 June 2021 Post Exam Submittal Letter ML21327A3362021-06-16016 June 2021 Handouts to Applicants (Summary) ML21327A3262021-06-16016 June 2021 Administered Written Exam with Answer Key ML21327A3212021-06-16016 June 2021 Administered Scenarios ML21327A3142021-06-16016 June 2021 Administered Control Room and In-Plant JPMs ML21327A3082021-06-16016 June 2021 Administered Admin JPMs ML21328A1662021-06-16016 June 2021 Proposed Written Exam with Answer Key ML21328A1642021-06-16016 June 2021 Proposed Scenarios ML21328A1622021-06-16016 June 2021 Proposed Control Room and In-Plant JPMs ML21327A3422021-06-16016 June 2021 Modified Question Source Information ML21328A1382021-06-16016 June 2021 Proposed Admin JPMs ML21120A0202021-05-0303 May 2021 Operator Licensing Examination Approval IR 05000341/20203022021-03-18018 March 2021 NRC Initial License Examination Report 05000341/2020302 ML22158A1582021-02-0505 February 2021 Fer 2020 Ile NRC ES-401-4 Record of Rejected KAs Rev 11 ML22158A1382021-02-0505 February 2021 Fer 2020 Ile Es 403-1 RO-SRO Written Exam Grading Quality Checklist ML22158A1332021-02-0505 February 2021 Fer 2020 Ile Final Es 201-3 ML22158A1302021-02-0505 February 2021 Fer 2020 ES-201-1 Rev 11 ML22158A1642021-02-0505 February 2021 Ile Outline Review Comments 2023-08-16
[Table view] |
Text
ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Fermi Power Plant, Unit 2 Date of Examination: 05/10/2021 Developed: Written: Facility: NRC: // Operating: Facility: NRC:
Days from Chief Examiner's Target Date* Task Description (Reference)
Exam Initials
- 1. Examination administration date confirmed (C.1.a; C.2.a-b). For NRC-prepared exams,
-240 09/12/2020 JD 1/24/2020 arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; Attachment 3).
-210 10/12/2020 2. NRC examiners and facility contact assigned (C.1.d; C.2.f). JD 1/24/2020
- 3. Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility JD 1/24/2020
-210 10/12/2020 contact submits to the NRC any prescreened K/As for elimination from the written examination (exam sec. only);
outline, with a description of the facilitys prescreening process (ES-401, D.1.b). JD 5/28/2020
-210 10/12/2020 4. Reference material due for NRC-prepared exams (C.1.e; C.3.c; Attachment 3). JD 2/10/2020
-210 10/12/2020 5. Corporate notification letter sent (C.2.e). JD 6/01/2020
- 6. NRC-developed written examination outline (ES-401-1/2 or ES-401N-1/2 and ES-401-3 or JD 1/24/2020 (Draft);
-195 10/27/2020 ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e-f; C.2.h; JD 2/7/2020 (Rev 0)
C.3.d-e).
- 7. Operating test outline(s) and other checklists due, including Forms ES-201-2, ES-201-3,
-150 12/11/2020 JD 4/16/2020 ES-301-1, ES-301-2, ES-301-5, and ES-D-1, as applicable (C.1.e-f; C.3.d-e).
- 8. Operating test outline(s) reviewed by the facility licensee and feedback provided to the NRC
-136 12/25/2020 JD 4/30/2020 (C.2.h; C.3.d-e). (Operating Test outlines prepared by NRC.)
- 9. Proposed examinations (written, JPMs, and scenarios, as applicable) and outlines (Forms ES-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES-401-3 or ES-401N-3);
02/26/2021 JD 03/02/2021
-75 supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-6, 03/02/2021* (Operating Test)
ES-401N-6, and any Form ES-201-2 and ES-201-3 updates); and reference materials due (C.1.e-h; C.3.d). *Target date adjusted by Chief Examiner in coordination with Licensee.
- 10. Examinations prepared by the NRC are approved by the NRC supervisor and forwarded for 02/26/2021 JD 1/08/2021
-75 facility licensee review (C.1.i; C.2.h; C.3.f-g); Form ES-401-6. (Written Exam prepared by NRC.)
01/20/2021** (Written Exam)
- Target date adjusted for NRC developed exam.
-60 03/11/2021 11. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES-202). JD 3/11/2021 JD 1/20/2021 (Written);
-50 03/21/2021 12. Written exam and operating test reviews completed (C.3.f). JD 3/11/2021 (Op Test) 13a. Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k-l; JD 1/22/2021 (Written);
-35 04/05/2021 C.2.h; C.3.g). JD 3/16/2021 (Op Test)
-35 04/05/2021 13b. The NRC and the facility licensee conduct exam preparatory week. JD 4/05/2021
- 14. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form 398)
-30 04/10/2021 JD 4/09/2021 due (C.1.m; C.2.i; ES-202).
- 15. Final license applications and waiver/excusal requests, as applicable (NRC Form 398), due
-14 04/26/2021 JD 4/26/2021 and Form ES-201-4 prepared (C.1.m; C.2.k; ES-202).
-7 05/03/2021 16. Written examinations and operating tests approved by the NRC supervisor (C.2.j-k; C.3.h). JD 5/03/2021
-7 05/03/2021 17. Request facility licensee management feedback on the examination (C.2.l). JD 5/03/2021
- 18. Final applications reviewed; one or two (if more than 10) applications audited to confirm
-7 05/03/2021 qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; JD 5/03/2021 Attachment 5; ES-202, C.3.j; ES-204).
-7 05/03/2021 19. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k). JD 5/03/2021
-7 05/03/2021 20. Approved scenarios and job performance measures distributed to NRC examiners (C.3.i). JD 5/03/2021
- Target dates are based on facility prepared examinations and the examination date identified in the corporate Exam Date: 05/10/2021 notification letter. These dates are for planning purposes and may be adjusted on a case by case basis in coordination with the facility licensee. (Exam date changed from 5/10/2021 to 5/24/2021 due to COVID impact.)