U.S. NUCLEAR REGULATORY COMMISSION DOCKET 50-410 LICENSE NPF-69 NINE MILE POINT NUCLEAR STATION UNIT 2 UPDATED SAFETY ANALYSIS REPORT OCTOBER 2022 REVISION 25

NMP Unit 2 USAR CHAPTER 14 LIST OF EFFECTIVE FIGURES Revision Figure No. Number 14.2-1b-1 R00 14.2-213-1 A08 14.2-233-1 R00 14.2-234-1 A08 14.2-239-1 A08 14.2-1 A24 14.2-2 A28 14.2-3 A24 14.2-4 A28 14.2-5 R00 14.2-6 A22 14.2-7 A16 Chapter 14 EF 14-1 Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES Table Number Title 14.1 SPECIFIC INFORMATION TO BE INCLUDED IN PSAR 14.2 SPECIFIC INFORMATION TO BE INCLUDED IN FSAR-INITIAL TEST PROGRAM 14.2.1 Summary of Test Program and Objectives 14.2.1.1 Initial Test Program Phases 14.2.1.2 Preliminary Testing 14.2.1.3 Preoperational Test Phase 14.2.1.4 Initial Startup Test Phase 14.2.2 Organization and Staffing 14.2.2.1 Startup and Test Organization and Responsibilities 14.2.2.1.1 Station Superintendent 14.2.2.1.2 Startup Manager 14.2.2.1.3 Test Group Managers 14.2.2.1.4 Lead Engineers 14.2.2.1.5 Test Group Supervisors 14.2.2.1.6 Test Engineers 14.2.2.1.7 Test Support Personnel 14.2.2.2 Startup and Test Program Staff Organization and Responsibilities 14.2.2.2.1 Project Advisory Engineer 14.2.2.2.2 Startup Administrative Manager 14.2.2.3 Station Staff Responsibilities During the Startup and Test Program 14.2.2.3.1 Plant Operations 14.2.2.3.2 Station Support Staff 14.2.2.4 General Electric Company 14.2.2.4.1 Site Operations Manager 14.2.2.4.2 Operations Superintendent 14.2.2.4.3 Startup Test Operations (STO) Engineer 14.2.2.4.4 Lead Engineer Startup Test, Design and Analysis (STD&A) 14.2.2.4.5 GE Startup Test, Design and Analysis Engineers 14.2.2.5 Joint Test Group Membership and Responsibilities 14.2.2.5.1 Startup Manager 14.2.2.5.2 Startup and Test 14.2.2.5.3 Plant Operations Representative 14.2.2.5.5 Stone and Webster Engineering Corporation 14.2.2.5.6 General Electric Company 14.2.2.5.7 Conditional Members 14.2.2.6 Unit 2 Support of the Startup and Test Program 14.2.2.6.1 Unit 2 Project Management 14.2.2.6.2 NMPC Quality Assurance 14.2.2.6.3 Stone and Webster Engineering Corporation Chapter 14 14-i Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 INITIAL TEST PROGRAM TABLE OF CONTENTS (Cont'd)

Section Title 14.2.2.6.4 General Electrical Company 14.2.2.7 Site Operations Review Committee 14.2.2.8 Qualifications 14.2.2.8.1 General 14.2.2.8.2 Evaluation for Certification 14.2.2.8.3 Startup Manager 14.2.2.8.4 Test Group Manager 14.2.2.8.5 Lead Engineer 14.2.2.8.6 Test Group Supervisor 14.2.2.8.7 Test Engineers 14.2.2.8.8 Test Support Personnel 14.2.2.8.9 Plant Personnel 14.2.2.8.10 Joint Test Group 14.2.2.9 Certification of Test Personnel 14.2.2.9.1 Certification Authorities 14.2.2.9.2 Certification 14.2.2.9.3 Recertification 14.2.3 Test Procedures 14.2.3.1 Test Procedure Development and General Information 14.2.3.1.1 Plant Procedures 14.2.3.2 Preliminary Test Procedures 14.2.3.3 Preoperational and Initial Startup Test Procedures 14.2.4 Conduct of Testing 14.2.4.1 Preliminary Testing 14.2.4.2 Preoperational Testing 14.2.4.2.1 Pretest Review 14.2.4.2.2 Test Performance 14.2.4.3 Initial Startup Testing 14.2.4.4 Modifications to Test Procedures During Testing 14.2.4.4.1 Preliminary Tests 14.2.4.4.2 Preoperational Tests 14.2.4.4.3 Startup Tests 14.2.4.5 Modifications and Deficiencies 14.2.4.5.1 Preliminary and Preoperational Phases 14.2.4.5.2 Initial Startup Test Phase 14.2.5 Test Procedure Results Review and Approval 14.2.5.1 Preliminary Test Procedures 14.2.5.2 Preoperational Test Procedures 14.2.5.3 Initial Startup Test Procedures 14.2.6 Test Records 14.2.7 Conformance of Test Program with Regulatory Guides 14.2.8 Utilization of Reactor Operating and Testing Experience in Development of Test Program 14.2.9 Trial Use of Plant Operating and Emergency Procedures Chapter 14 14-ii Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 INITIAL TEST PROGRAM TABLE OF CONTENTS (Cont'd)

Section Title 14.2.9.1 Interim Operating Procedures 14.2.10 Initial Fuel Loading and Initial Criticality 14.2.10.1 Fuel Loading and Shutdown Power Level Tests 14.2.10.1.1 Loss of Power Demonstration - Standby Core Cooling Required (Table 14.2-129) 14.2.10.1.2 Cold Functional Testing 14.2.10.1.3 Routine Surveillance Testing 14.2.10.1.4 Master Tracking System 14.2.10.1.5 Initial Fuel Loading (Open Vessel Plateau) 14.2.10.1.6 Zero Power Level Tests (Open Vessel Plateau) 14.2.10.2 Initial Criticality and Heatup to Rated Temperature and Pressure 14.2.10.3 Power Testing from 25 to 100 Percent of Rated Output 14.2.11 Test Program Schedule 14.2.12 Individual Test Descriptions 14.2.12.1 Preoperational Tests 14.2.12.2 General Discussion of Initial Startup Tests 14.3 INITIAL TEST PROGRAM FOR OPERATION AT POWER UPRATE CONDITIONS (3,467 MWt) 14.3.1 Summary of Test Program and Objectives 14.3.1.1 Overview of Program 14.3.1.2 Test Conditions 14.3.1.3 Test Objectives 14.3.2 Organization and Staffing 14.3.3 Conduct of Testing 14.3.3.1 Test Procedures 14.3.3.2 Test Exceptions 14.3.3.3 Test Data 14.3.3.4 Criteria for Testing 14.3.3.5 Test Procedure Results Review and Approvals 14.3.3.6 Test Records 14.3.4 Conformance of Test Program with Regulatory Guidelines 14.3.5 Summary of Test Results 14.3.6 Reference 14.4 INITIAL TEST PROGRAM FOR OPERATION AT EXTENDED POWER UPRATE (EPU) CONDITIONS (3,988 MWt) 14.4.1 Summary of Test Program and Objectives 14.4.1.1 Overview of Program 14.4.1.2 Test Conditions 14.4.1.3 Test Objectives 14.4.2 Organization and Staffing Chapter 14 14-iii Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 INITIAL TEST PROGRAM TABLE OF CONTENTS (Cont'd)

Section Title 14.4.3 Conduct of Testing 14.4.3.1 Test Procedures 14.4.3.2 Test Exceptions 14.4.3.3 Test Data 14.4.3.4 Criteria for Testing 14.4.3.5 Test Procedure Results Review and Approvals 14.4.3.6 Test Records 14.4.4 Conformance of Test Program with Regulatory Guidelines 14.4.5 Summary of Test Results 14.4.6 References Chapter 14 14-iv Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES Table Number Title 14.2-1 DELETED 14.2-1a COMPARISON OF REGULATORY GUIDE 1.68, APPENDIX A, WITH TEST ABSTRACTS 14.2-1b SERVICE WATER PUMP NET POSITIVE SUCTION HEAD 14.2-2 DELETED thru 14.2-24 14.2-25 MAIN AND AUXILIARY STEAM SYSTEM 14.2-26 DELETED 14.2-27 CONDENSATE SYSTEM 14.2-28 CONDENSATE STORAGE AND TRANSFER SYSTEM 14.2-29 CONDENSATE DEMINERALIZATION AND RESIN REGENERATION 14.2-30 FEEDWATER SYSTEM 14.2-31 FEEDWATER CONTROL SYSTEM 14.2-32 FEEDWATER HEATERS AND EXTRACTION STEAM SYSTEM 14.2-33 CONDENSER AIR REMOVAL SYSTEM 14.2-34 CIRCULATING WATER SYSTEM 14.2-35 DELETED 14.2-36 SERVICE WATER SYSTEM 14.2-37 DELETED 14.2-38 REACTOR BUILDING CLOSED LOOP COOLING WATER SYSTEM 14.2-39 TURBINE BUILDING CLOSED LOOP COOLING WATER SYSTEM 14.2-40 MAKEUP WATER TRANSFER AND STORAGE SYSTEM 14.2-41 PROCESS SAMPLING SYSTEM 14.2-42 POST-ACCIDENT SAMPLE SYSTEM Chapter 14 14-v Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES (Cont'd)

Table Number Title 14.2-43 SERVICE AND INSTRUMENT AIR SYSTEM 14.2-43A LOSS OF AIR TEST 14.2-44 ELECTROHYDRAULIC CONTROL (EHC) SYSTEM 14.2-45 DELETED 14.2-46 NUCLEAR BOILER INSTRUMENTATION 14.2-47 REACTOR RECIRCULATION SYSTEM 14.2-48 CONTROL ROD DRIVE HYDRAULIC SYSTEM 14.2-49 RESIDUAL HEAT REMOVAL SYSTEM 14.2-50 LOW-PRESSURE CORE SPRAY SYSTEM 14.2-51 HIGH-PRESSURE CORE SPRAY SYSTEM 14.2-52 AUTOMATIC DEPRESSURIZATION SYSTEM 14.2-53 REACTOR CORE ISOLATION COOLING SYSTEM 14.2-54 STANDBY LIQUID CONTROL SYSTEM 14.2-55 REACTOR WATER CLEANUP SYSTEM 14.2-56 FUEL POOL COOLING AND CLEANUP SYSTEM 14.2-57 FUEL HANDLING AND REACTOR SERVICE EQUIPMENT SYSTEM 14.2-58 LIQUID RADWASTE SYSTEM 14.2-59 SOLID RADWASTE HANDLING SYSTEM 14.2-60 OFFGAS SYSTEM 14.2-61 FIRE PROTECTION (WATER) SYSTEM 14.2-62 FOAM FIRE PROTECTION SYSTEM 14.2-63 FIRE PROTECTION CO2 14.2-64 FIRE PROTECTION (HALON) SYSTEM Chapter 14 14-vi Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES (Cont'd)

Table Number Title 14.2-65 SMOKE, FLAME, AND TEMPERATURE DETECTION 14.2-66 DELETED 14.2-67 HOT WATER AND GLYCOL HEATING SYSTEMS 14.2-68 REACTOR BUILDING HVAC 14.2-69 CONTROL BUILDING AIR CONDITIONING 14.2-70 DELETED 14.2-71 TURBINE BUILDING HVAC SYSTEM 14.2-72 RADWASTE BUILDING VENTILATION 14.2-73 DIESEL GENERATOR BUILDING HVAC SYSTEM 14.2-74 ELECTRIC TUNNELS VENTILATION SYSTEM 14.2-75 DRYWELL COOLING SYSTEM 14.2-76 PRIMARY CONTAINMENT PURGE SYSTEM 14.2-77 STANDBY GAS TREATMENT SYSTEM 14.2-78 DBA HYDROGEN RECOMBINER SYSTEM 14.2-79 REACTOR BUILDING DRAINS 14.2-80 TURBINE BUILDING DRAINS 14.2-81 RADWASTE BUILDING DRAINS 14.2-82 MISCELLANEOUS DRAINS - DIESEL GENERATOR BUILDING FLOOR DRAINS, AUXILIARY SERVICE BUILDING, REACTOR BUILDING MAT, CONDENSATE STORAGE BUILDING, AND MAIN STACK DRAIN SYSTEM 14.2-83 DELETED thru 14.2-85 14.2-86 DRYWELL FLOOR AND EQUIPMENT DRAIN SYSTEM Chapter 14 14-vii Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES (Cont'd)

Table Number Title 14.2-87 DELETED thru 14.2-94 14.2-95 UNINTERRUPTIBLE POWER SUPPLY 14.2-96 DELETED thru 14.2-99 14.2-100 NORMAL DC SYSTEMS 14.2-101 EMERGENCY DC SYSTEMS 14.2-102 STATION EMERGENCY LIGHTING SYSTEM 14.2-103 PLANT COMMUNICATION SYSTEM 14.2-104 REMOTE SHUTDOWN 14.2-105 AREA, PROCESS AIRBORNE, AND GASEOUS RADIATION MONITORING SYSTEM 14.2-106 MAIN STEAM LINE RADIATION MONITORING SYSTEM 14.2-107 CONTAINMENT LEAKAGE MONITORING 14.2-108 CONTAINMENT ATMOSPHERE MONITORING 14.2-109 PRIMARY CONTAINMENT ISOLATION SYSTEM (NSSS) 14.2-110 REACTOR BUILDING - POLAR CRANE 14.2-111 DELETED 14.2-112 REACTOR COOLANT AND ECCS LEAK DETECTION SYSTEM 14.2-113 LOOSE PARTS MONITORING SYSTEM 14.2-114 CONTAINMENT INERTING SYSTEM 14.2-115 SEISMIC MONITORING SYSTEM 14.2-116 PROCESS COMPUTER 14.2-117 NEUTRON MONITORING SYSTEM Chapter 14 14-viii Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES (Cont'd)

Table Number Title 14.2-118 ROD BLOCK MONITORING SYSTEM 14.2-119 TRAVERSING IN-CORE PROBE SYSTEM 14.2-120 ROD WORTH MINIMIZER SYSTEM 14.2-121 ROD SEQUENCE CONTROL SYSTEM 14.2-122 REACTOR MANUAL CONTROL AND ROD POSITION INDICATION 14.2-123 REACTOR PROTECTION SYSTEM 14.2-124 DELETED 14.2-125 STANDBY DIESEL GENERATOR 14.2-126 HPCS DIESEL GENERATOR 14.2-127 DELETED 14.2-128 REDUNDANT REACTIVITY CONTROL SYSTEM 14.2-129 LOSS OF POWER/ECCS FUNCTIONAL TEST 14.2-130 DELETED 14.2-131 STRUCTURAL INTEGRITY INTEGRATED LEAK RATE TEST 14.2-132 SECONDARY CONTAINMENT LEAKAGE TEST 14.2-201 CHEMICAL AND RADIOCHEMICAL 14.2-202 RADIATION MEASUREMENT 14.2-203 FUEL LOADING 14.2-204 FULL CORE SHUTDOWN MARGIN 14.2-205 DELETED 14.2-206 CONTROL ROD DRIVE SYSTEM 14.2-207 SOURCE RANGE MONITOR PERFORMANCE 14.2-208 DELETED Chapter 14 14-ix Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES (Cont'd)

Table Number Title 14.2-209 INTERMEDIATE RANGE MONITOR PERFORMANCE 14.2-210 LPRM CALIBRATION 14.2-211 APRM CALIBRATION 14.2-212 NSSS PROCESS COMPUTER 14.2-213 RCIC SYSTEM 14.2-214 SELECTED PROCESS TEMPERATURES 14.2-215 WATER LEVEL REFERENCE AND VARIABLE LEG TEMPERATURES 14.2-216 SYSTEM EXPANSION 14.2-216A DELETED 14.2-217 TIP UNCERTAINTY 14.2-218 CORE PERFORMANCE 14.2-219 STEAM PRODUCTION 14.2-220 DELETED 14.2-221 PRESSURE REGULATOR 14.2-222 WATER LEVEL SETPOINT, MANUAL FEEDWATER FLOW CHANGES 14.2-223 LOSS OF FEEDWATER HEATING 14.2-224 FEEDWATER PUMP TRIP 14.2-225 MAXIMUM FEEDWATER RUNOUT CAPABILITY 14.2-226 TURBINE VALVE SURVEILLANCE 14.2-227 MAIN STEAM ISOLATION VALVES FUNCTIONAL TESTS 14.2-228 FULL REACTOR ISOLATION 14.2-229 DELETED Chapter 14 14-x Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES (Cont'd)

Table Number Title 14.2-230 RELIEF VALVES 14.2-231 TURBINE TRIP AND GENERATOR LOAD REJECTION 14.2-232 SHUTDOWN FROM OUTSIDE THE MAIN CONTROL ROOM 14.2-233 RECIRCULATION FLOW CONTROL, VALVE POSITION CONTROL 14.2-234 RECIRCULATION FLOW LOOP CONTROL 14.2-235 RECIRCULATION SYSTEM, ONE-PUMP TRIP 14.2-236 RECIRCULATION SYSTEM, TWO-PUMP TRIP 14.2-237 RECIRCULATION SYSTEM PERFORMANCE 14.2-238 RECIRCULATION PUMP RUNBACK 14.2-239 RECIRCULATION SYSTEM CAVITATION 14.2-240 LOSS OF TURBINE GENERATOR AND OFFSITE POWER 14.2-241 DRYWELL PIPING VIBRATION 14.2-242 RECIRCULATION SYSTEM FLOW CALIBRATION 14.2-243 REACTOR WATER CLEANUP SYSTEM 14.2-244 RESIDUAL HEAT REMOVAL SYSTEM 14.2-245 OFFGAS SYSTEM 14.2-301 DRYWELL COOLING SYSTEM 14.2-302 ESF AREA COOLING 14.2-303 BOP PIPING VIBRATION 14.2-304 BOP SYSTEM EXPANSION 14.2-305 REACTOR INTERNALS VIBRATION 14.2-306 EMERGENCY RECIRCULATION VENTILATION 14.2-307 DRYWELL HIGH-ENERGY PENETRATIONS Chapter 14 14-xi Rev. 25, October 2022

NMP Unit 2 USAR CHAPTER 14 LIST OF TABLES (Cont'd)

Table Number Title 14.2-401 DELETED 14.2-402 DELETED 14.2-403 QUALIFICATION OF GE PRINCIPAL TESTING PERSONNEL DURING STARTUP TESTING 14.3-1

SUMMARY

OF TESTING PERFORMED FOR THE POWER UPRATE POWER ASCENSION TEST PROGRAM 14.3-2 INDIVIDUAL POWER ASCENSION TESTS 14.4-1

SUMMARY

OF TESTING PERFORMED FOR THE EXTENDED POWER UPRATE POWER ASCENSION TEST PROGRAM Chapter 14 14-xii Rev. 25, October 2022

NMP UNIT 2 USAR CHAPTER 14 LIST OF FIGURES Figure Number Title 14.2-1 REVIEW CYCLE FOR SELECTED PRELIMINARY AND ALL PREOPERATIONAL TEST PROCEDURES 14.2-1b-1* SERVICE WATER PUMP CHARACTERISTIC CURVE 14.2-2 REVIEW CYCLE FOR INITIAL STARTUP TEST PROCEDURES 14.2-3 PRELIMINARY AND PREOPERATIONAL TEST RESULTS REVIEW 14.2-4 INITIAL STARTUP TEST RESULTS REVIEW 14.2-5 TEST CONDITION REGION DEFINITION 14.2-6 DELETED 14.2-7 UNIT 2 STARTUP ORGANIZATION 14.2-213-1* RCIC ACCEPTANCE CRITERIA CURVES FOR CAPACITY AND ACTUATION TIME 14.2-233-1* TRADEOFF CURVE FOR STEP SIZES 0.2% TO 0.5%

14.2-234-1* TRADEOFF CURVE FOR STEP SIZES 0.2% TO 0.3%

14.2-239-1* TWO-PUMP TRIP COASTDOWN CURVES

  • These figures follow the tables of the same number.

Chapter 14 14-xiii Rev. 25, October 2022