Responds to Requesting Schedule for Providing Detailed Info on Mark III Containment Sys for Plant.Plans to Submit Info During First Half of 1978.Engineering Largely Suspended Due to Deferment of Commercial Operation Dates
ML20235C914
Person / Time
Site: 05000000, 05000449, 05000448
Issue date: 06/06/1975
From: Dragoumis P
POTOMAC ELECTRIC POWER CO.
To: Butler W
Office of Nuclear Reactor Regulation
Shared Package
ML20235B454 List:
References
FOIA-87-554 7198, NUDOCS 8709250057
Download: ML20235C914 (2)


Text

- - _ _ _ _ _ - _ _ - _ _ _ _ _ - _

. a cop 1]

numA, -

Y POTOMAC ELECTRIC POWER COMPANY . t 900 et N NSY LVANI A AVEN U E. N. W., WASHINGTON. D.C. 20006 P Aut. DnacouMis (202) #M538

"=.... . -a. .,.-,.. ,

e June 6, 1975 5' 'JUN6 1975

  • 1 i

Dr. Walter R. Butler, Chief Light Water Reactor Branch 1-2 s.s. n unt t e st k/

g t@"g

, Division of Reactor Licensing se,i heuen Nuclear Regulatory Commission e Washington, D. C. 20555 w

. RE: Potomac Electric Power Company Douglas Point Nuclear Generating

, Station, Units l and 2 Docket Nos. 50-448 and 50-449

Dear Dr. Butler:

?' This is in response to your letter of May 28, 1975 which requests

,- a schedule for providing detailed information on the Mark III containment system for Douglas Point Nuclear Generating Station.

As you know, in November, 1974 the Potomac Electric Power Company l

.. deferred the commercial operation dates for Douglas Point Units 1 and 2 to 1985 and 1987 respectively. Since taking this action, ent,ineer Lng has been largely suspended. As a result, the contain-ment system design is not yet sufficiently developed to provide the I detailed 1cvel of information which you are requesting. Speficially, the current schedule for completing the applicable portion of struc-tural design is one year prior to start of construction. Therefore, we are planning to submit the information which you have requested during the first half of 1978. It is expected that the containment system structural dasign and anticipated loads will be similar to those of other Mark III containments which the Staff will have reviewed by that time. Results of development work occurring prior to submittal of this information will be factored into the Douglas i Point design. j In establishing this schedule, we have given heavy consideration to assuring support of the licensing activities which PEPC0 and the NRC Staff are jointly pursuing.

[ Sincer hr, ,

FoM-F 7JW Q obs**'

73 8//y 4 PD: mas g , / A ~

c' ,.p[ 71gg i 8709250057 870922 8 PDR FOI/,

MCCREA07-554 PDR

.. n i - '

POTOMAC ELEcliRIC POWER COMPANY cc: George'F. TroWbridge, tsq.

.Shaw, Pitt:an, Potts G Trowbridge 910 17th Street, N. W.

Washington, D. C. 20006 Edward lawson, Esq.

Special Assistant Attorney General Tawes State Office Building 580 Taylor Avenue-C4 Annapolis Maryland 21401 Frederick S..Fich e ft L , Attorney General tlcmonwealth of.Virgisia Supreme Court; Building lloi East Broad Street Richmond, Virginia 23219 -

i l

Robert A. Vanderhye, Esq.

7807 Cliffside Court Springfield, Virginia 22153 1

Mr. Fred Kelly Chesapeake Bay Foundation F. O. Box 1709 Annapolis, Maryland 21404 Philip J. Mause, Esq.

Environmental Defense Fund, Inc.

1525 18th Street, N. W.

Washington, D. C. 20036 William H.' Carroll, Jr., Esq.

Headquarters, U. S. Marine Corps Counsel for the Comandant Washington, D. C. 20380 Mr. T. Ray Jones, Chairman Citizens Council for a Clean Potomac 918 Kenbrook Court Silver Spring, Maryland 20902 m._-___ _ _ _ . _ .