|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217L7971999-10-20020 October 1999 Submits Results of Review of 990521 & 0709 Ltrs Which Provided Core Shroud Insp Results & Tie Rod Stabilizer Assemblies ML20217G1291999-10-15015 October 1999 Forwards Errata to Safety Evaluation for Amend 168 Issued to FOL DPR-63 on 990921.Description of Flow Control Trip Ref Cards to Be Consistent with Application for Amend ML20217K2831999-10-14014 October 1999 Submits Response to NRC Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates, for Fiscal Yrs 2000 & 2001 ML20217H3211999-10-0808 October 1999 Forwards Changed Pages for Issue 5,rev 1 of Nine Mile Point Station Physical Security & Safeguards Contingency Plan,Iaw 10CFR50.54(p).Without Encls ML20212K8601999-10-0606 October 1999 Responds to Concern in 990405 Petition Re Residual Heat Removal Alternate Shutdown Cooling Modes of Operation at Nine Mile Point Nuclear Station,Unit 2 ML20216J9311999-09-30030 September 1999 Forwards Response to NRC 981119 Suppl RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions ML20212J4651999-09-30030 September 1999 Informs of Completion of mid-cyle PPR of Nine Mile Point Nuclear Station on 990916.Determined That Problems in Areas of Human Performance & Work Control Required Continued Mgt Attention.Historical Listing of Plant Issues Encl ML18040A3701999-09-30030 September 1999 Provides Changes to Application for Amend Re Volumes 1-11 of 981016 Submittal & Discard & Insertion Instructions Re Integration of Proposed Changes,In Response to NRC RAIs ML20212K8641999-09-30030 September 1999 Informs That During 990927 Telcon Between J Williams & J Bobka,Arrangements Were Made for Administration of Exams at Plant During Wk of Feb 14,2000.Preliminary RO & SRO License Applications Should Be Submitted 30 Days Prior Exam ML20212J8831999-09-30030 September 1999 Informs That Util 980810 & 990630 Responses to GL 98-01 & Suppl 1, Y2K Readiness of Computer Sys at NPPs Acceptable. NRC Considers Subj GL to Be Closed for Plant ML20212E9801999-09-23023 September 1999 Submits Info in Response to Request for Estimated Initial Operator Licensing Exam Needs,Per Administrative Ltr 99-03 ML20216F7101999-09-17017 September 1999 Forwards Response to NRC 990806 RAI Re USI A-46,verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors.Nrc Is Informed That Actions Required for Resolution of USI A-46 Have Been Completed ML20212B2821999-09-14014 September 1999 Responds to 990712 Correspondence Which Responded to NRC Ltr Re High Failure Rate for Generic Fundamentals Exam of 990407 for Nine Mile Point.Considers Corrective Actions Taken to Be Acceptable ML20212D8981999-09-14014 September 1999 Forwards ISI Summary Rept for Refueling Outage 15 & Flaw Indication Repts.Supporting Info Repts & Calculations, Encl ML20212B2581999-09-10010 September 1999 Requests That Name of Bm Bordenick Be Removed from Nine Mile Point,Units 1 & 2 Service List ML20211P5771999-09-10010 September 1999 Forwards Application for Amends to Licenses DPR-63 & NPF-69, to Transfer Licenses to Amergen Energy Co,Llc.Ts Pages & Proprietary Addendum,Included.Proprietary Encl Withheld ML20212A1341999-09-0707 September 1999 Forwards Summary Rept Secondary Containment Leakage Testing, Dtd June 1999 for Nine Mile Point,Unit 1,IAW TS 6.9.3.f ML20211K8141999-09-0101 September 1999 Forwards Reactor Containment Bldg Ilrt,Iaw Plant TS 6.9.3.e.Testing Confirmed That TS 3.3.3/4.3.3 & 6.16 Primary Containment Leakage Requirements Were Satisfactorily Met ML20211L9221999-09-0101 September 1999 Confirms That Licensee Will Retain Weld 32-WD-050 as IGSCC Category F Until Completion of Reinspection Program,In Response to NRC ML20211J6461999-08-30030 August 1999 Forwards Response to NRC 990625 RAI Re NMPC Responses to GL 92-01,rev 1,supplement 1, Reactor Vessel Structural Integrity ML20211K3001999-08-30030 August 1999 Forwards Semi-Annual Radioactive Effluent Release Rept for 990101-990630 & Revised ODCM, for Nine Mile Point,Unit 1. Format Used for Effluent Data Is Outlined in App B of Regulatory Guide 1.21,rev 1 ML20211K5031999-08-30030 August 1999 Responds to Ltr Addressed to Chairman Dicus, Expressing Concerns Involving 990624 Automatic Reactor Shutdown.Insp Findings & Conclusions Will Be Documented in Insp Repts 50-220/99-06 & 50-410/99-06 by mid-Sept 1999 ML20211H1921999-08-26026 August 1999 Forwards Application for Amend to License DPR-63,supporting Implementation of Noble Metal Chemical Addition by Raising Reactor Water Conductivity Limits in TSs 3.2.3.a,3.2.3.c.1 & 3.2.3.b ML20211P5161999-08-26026 August 1999 Discusses Submitted on Behalf of Niagara Mohawk Power Corp Written Comments Addressing 10CFR2.206 Petition & Request That Ltr & Attached Response Be Withheld from Public Disclosure.Request Denied ML20211G4921999-08-26026 August 1999 Advises That Info Re Comments Addressing 10CFR2.206,dtd 990405 Will Be Withheld from Public Disclosure,In Response to ML20211D7731999-08-20020 August 1999 Forwards Semiannual FFD Program Performance Data Rept Covering Period 990101 Through 990630 ML20211B9371999-08-18018 August 1999 Provides Addl Info Re Application of Method a at Nmp,Unit 1 as Described in Generic Implementation Procedure,Rev 2 (GIP-2),NRC Supplemental SER 2 & Documents Ref in GIP-2 Upon Which GIP-2 Is Based ML18040A3691999-08-16016 August 1999 Forwards Response to NRC 990510 RAI Pertaining to NMP Application for Amend Re Conversion of NMPNS Unit 2 Current TS to Its.Nrc Requested Info Re Several Sections,Including Section 3.6, Containment Sys. ML20210Q0031999-08-11011 August 1999 Informs That Due to Printing Malfunction,Some Copies of Author Ltr Dtd 990726,may Not Have Included Second Page of Encl 2 of Ltr ML20210R6661999-08-10010 August 1999 Confirms Conversation on 990721 Re Concerns of Syracuse Anti-Nuclear Effort on Status of 2.206 Petition (Filed 990524) & Upcoming NRC Performance Review Meeting on Nine Mile Point Units 1 & 2 ML20210R8101999-08-10010 August 1999 Forwards 1998 Annual Repts for NMP & co-tenants,including Rg&E,Energy East Corp/Nyse&G,Chg&E & Long Island Power Authority,Per 10CFR50.71(b) ML20210L5321999-08-0606 August 1999 Forwards List of Subjects Discussed During 990714 Telcon with Representatives of Niagara Mohawk Power Corp on Unit 1 Re USI A-46 Issue ML18041A0711999-07-30030 July 1999 Forwards Rev 1 to NMP2-ISI-006, Second Ten Year Interval ISI Program Plan for Nine Mile Point Nuclear Power Station Unit 2. Significant Changes from Rev 0 Listed ML20210J9351999-07-29029 July 1999 Informs That NMP Is Changing Completion Date for Replacement of Valves Having O Rings with Installed Life Greater than Eight Years.Replacement to Be Completed by 991031, During Hydrogen Monitoring Sys Maintenance Outage ML20216E1491999-07-26026 July 1999 Forwards Two Ltrs Received from NMPC Re Nine Mile Point Unit 1 Core Shroud Related to 10CFR2.206 ML20210E9151999-07-23023 July 1999 Discusses Evaluation of Recirculation Line Weld 32-WD-050 Indication Found During 1997 Refueling Outage (RFO14) at NMPNS Unit 1.Requests Notification of Decision to Retain Category F Classification Until Listed Conditions Satisfied ML20209G7911999-07-12012 July 1999 Provides Info Requested in NRC Re 990407 Generic Fundamentals Exam Failure Causes & Corrective Actions ML20209G3711999-07-12012 July 1999 Provides Final Root Cause Evaluation Re GL 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in Bwrs, for Unit 1 ML20209G2001999-07-0909 July 1999 Forwards RFO-15 Core Shroud Insp Summary Rept, as Required by GL 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in BWRs & BWRVIP Rept BWR Core Shroud Insp & Flaw Evaluation Guideline (BWRVIP-01) ML20209F8561999-07-0606 July 1999 Forwards Rev 1 to Nmp,Unit 1 COLR for Cycle 14. Rept Is Being Submitted to Commission in Compliance with TS 6.9.1.f.4 ML20211K5071999-07-0606 July 1999 Submits Concerns Re 990624 Event Involving Automatic Reactor Shutdown.More than 5 Failures Were Identified in Event Number 35857 ML20196J6421999-06-30030 June 1999 Discusses Completion of Licensing Action for GL 96-01, Testing of Safety-Related Logic Circuits, Issued on 960110 ML20209B7071999-06-30030 June 1999 Responds to NRC Request for Info Re Y2K Readiness at Nuclear Facilities,As Contained in GL 98-01,Supp 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Y2K Readiness Disclosure,Encl ML20211P5271999-06-29029 June 1999 Submits Written Comments Addressing Petition Dtd 990405, Submitted by R Norway as It Relates to Expressed Concerns That Involve NMPC Activities.None of Relief Requested in Petition Warranted ML20196K6461999-06-29029 June 1999 Discusses Ofc of Investigations Rept 1-98-33 Re Unqualified Senior Reactor Operator Assuming Position of Assistant Station Shift Supervisor at Unit 1 on 980616.One Violation Being Cited as Described in Encl NOV ML20209B3501999-06-25025 June 1999 Submits Torus Shell & Coupon Corrosion Rate Determination for Nmpns,Unit 1.Torus Meets ASME Code Requirements,Iaw NRC 920825 & 940811 SERs ML20212J4431999-06-25025 June 1999 Discusses Responses to RAI Re GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20209B3531999-06-25025 June 1999 Informs NRC That All Actions Associated with NRC Bulletin 96-003, Potential Plugging of ECC Suction Strainers by Debris in Bwrs, Has Been Completed.Summary of Actions Completed & Other Pertinent Info Is Provided in Attachment ML20196F5721999-06-23023 June 1999 Forwards Rev 3 to NMP1-IST-003, Third Ten Year Inservice Testing Program Plan, Which Will Begin on 991226.Program Plan Conforms to Requirements of 1989 Edition of ASME Boiler & Pressure Vessel Code.Three Relief Requests,Encl ML20196G1461999-06-23023 June 1999 Informs That Actions Requested in GL 96-01, Testing of Safety-Related Logic Circuits Completed 1999-09-07
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217K2831999-10-14014 October 1999 Submits Response to NRC Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates, for Fiscal Yrs 2000 & 2001 ML20217H3211999-10-0808 October 1999 Forwards Changed Pages for Issue 5,rev 1 of Nine Mile Point Station Physical Security & Safeguards Contingency Plan,Iaw 10CFR50.54(p).Without Encls ML18040A3701999-09-30030 September 1999 Provides Changes to Application for Amend Re Volumes 1-11 of 981016 Submittal & Discard & Insertion Instructions Re Integration of Proposed Changes,In Response to NRC RAIs ML20216J9311999-09-30030 September 1999 Forwards Response to NRC 981119 Suppl RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions ML20212E9801999-09-23023 September 1999 Submits Info in Response to Request for Estimated Initial Operator Licensing Exam Needs,Per Administrative Ltr 99-03 ML20216F7101999-09-17017 September 1999 Forwards Response to NRC 990806 RAI Re USI A-46,verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors.Nrc Is Informed That Actions Required for Resolution of USI A-46 Have Been Completed ML20212D8981999-09-14014 September 1999 Forwards ISI Summary Rept for Refueling Outage 15 & Flaw Indication Repts.Supporting Info Repts & Calculations, Encl ML20212B2581999-09-10010 September 1999 Requests That Name of Bm Bordenick Be Removed from Nine Mile Point,Units 1 & 2 Service List ML20211P5771999-09-10010 September 1999 Forwards Application for Amends to Licenses DPR-63 & NPF-69, to Transfer Licenses to Amergen Energy Co,Llc.Ts Pages & Proprietary Addendum,Included.Proprietary Encl Withheld ML20212A1341999-09-0707 September 1999 Forwards Summary Rept Secondary Containment Leakage Testing, Dtd June 1999 for Nine Mile Point,Unit 1,IAW TS 6.9.3.f ML20211K8141999-09-0101 September 1999 Forwards Reactor Containment Bldg Ilrt,Iaw Plant TS 6.9.3.e.Testing Confirmed That TS 3.3.3/4.3.3 & 6.16 Primary Containment Leakage Requirements Were Satisfactorily Met ML20211L9221999-09-0101 September 1999 Confirms That Licensee Will Retain Weld 32-WD-050 as IGSCC Category F Until Completion of Reinspection Program,In Response to NRC ML20211K3001999-08-30030 August 1999 Forwards Semi-Annual Radioactive Effluent Release Rept for 990101-990630 & Revised ODCM, for Nine Mile Point,Unit 1. Format Used for Effluent Data Is Outlined in App B of Regulatory Guide 1.21,rev 1 ML20211J6461999-08-30030 August 1999 Forwards Response to NRC 990625 RAI Re NMPC Responses to GL 92-01,rev 1,supplement 1, Reactor Vessel Structural Integrity ML20211H1921999-08-26026 August 1999 Forwards Application for Amend to License DPR-63,supporting Implementation of Noble Metal Chemical Addition by Raising Reactor Water Conductivity Limits in TSs 3.2.3.a,3.2.3.c.1 & 3.2.3.b ML20211D7731999-08-20020 August 1999 Forwards Semiannual FFD Program Performance Data Rept Covering Period 990101 Through 990630 ML20211B9371999-08-18018 August 1999 Provides Addl Info Re Application of Method a at Nmp,Unit 1 as Described in Generic Implementation Procedure,Rev 2 (GIP-2),NRC Supplemental SER 2 & Documents Ref in GIP-2 Upon Which GIP-2 Is Based ML18040A3691999-08-16016 August 1999 Forwards Response to NRC 990510 RAI Pertaining to NMP Application for Amend Re Conversion of NMPNS Unit 2 Current TS to Its.Nrc Requested Info Re Several Sections,Including Section 3.6, Containment Sys. ML20210R6661999-08-10010 August 1999 Confirms Conversation on 990721 Re Concerns of Syracuse Anti-Nuclear Effort on Status of 2.206 Petition (Filed 990524) & Upcoming NRC Performance Review Meeting on Nine Mile Point Units 1 & 2 ML20210R8101999-08-10010 August 1999 Forwards 1998 Annual Repts for NMP & co-tenants,including Rg&E,Energy East Corp/Nyse&G,Chg&E & Long Island Power Authority,Per 10CFR50.71(b) ML18041A0711999-07-30030 July 1999 Forwards Rev 1 to NMP2-ISI-006, Second Ten Year Interval ISI Program Plan for Nine Mile Point Nuclear Power Station Unit 2. Significant Changes from Rev 0 Listed ML20210J9351999-07-29029 July 1999 Informs That NMP Is Changing Completion Date for Replacement of Valves Having O Rings with Installed Life Greater than Eight Years.Replacement to Be Completed by 991031, During Hydrogen Monitoring Sys Maintenance Outage ML20209G3711999-07-12012 July 1999 Provides Final Root Cause Evaluation Re GL 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in Bwrs, for Unit 1 ML20209G7911999-07-12012 July 1999 Provides Info Requested in NRC Re 990407 Generic Fundamentals Exam Failure Causes & Corrective Actions ML20209G2001999-07-0909 July 1999 Forwards RFO-15 Core Shroud Insp Summary Rept, as Required by GL 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in BWRs & BWRVIP Rept BWR Core Shroud Insp & Flaw Evaluation Guideline (BWRVIP-01) ML20209F8561999-07-0606 July 1999 Forwards Rev 1 to Nmp,Unit 1 COLR for Cycle 14. Rept Is Being Submitted to Commission in Compliance with TS 6.9.1.f.4 ML20211K5071999-07-0606 July 1999 Submits Concerns Re 990624 Event Involving Automatic Reactor Shutdown.More than 5 Failures Were Identified in Event Number 35857 ML20209B7071999-06-30030 June 1999 Responds to NRC Request for Info Re Y2K Readiness at Nuclear Facilities,As Contained in GL 98-01,Supp 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Y2K Readiness Disclosure,Encl ML20211P5271999-06-29029 June 1999 Submits Written Comments Addressing Petition Dtd 990405, Submitted by R Norway as It Relates to Expressed Concerns That Involve NMPC Activities.None of Relief Requested in Petition Warranted ML20209B3501999-06-25025 June 1999 Submits Torus Shell & Coupon Corrosion Rate Determination for Nmpns,Unit 1.Torus Meets ASME Code Requirements,Iaw NRC 920825 & 940811 SERs ML20209B3531999-06-25025 June 1999 Informs NRC That All Actions Associated with NRC Bulletin 96-003, Potential Plugging of ECC Suction Strainers by Debris in Bwrs, Has Been Completed.Summary of Actions Completed & Other Pertinent Info Is Provided in Attachment ML20196G1461999-06-23023 June 1999 Informs That Actions Requested in GL 96-01, Testing of Safety-Related Logic Circuits Completed ML20196F5721999-06-23023 June 1999 Forwards Rev 3 to NMP1-IST-003, Third Ten Year Inservice Testing Program Plan, Which Will Begin on 991226.Program Plan Conforms to Requirements of 1989 Edition of ASME Boiler & Pressure Vessel Code.Three Relief Requests,Encl ML20209B2951999-06-22022 June 1999 Informs That Training Re Pressure Relief Panels Was Completed for Remainder of Target Population on 990226 ML20196E9231999-06-21021 June 1999 Forwards Response to NRC 990510 RAI Re NMP 981116 Application Proposing Changes to TSs to Provide Reasonable Assurance That Coupled neutronic/thermal-hydraulic Instabilities Were Detected & Suppressed in NMPN-1 Reactor ML18040A3651999-06-0707 June 1999 Forwards for Filing Original Application of Central Hudson & Gas & Electric Corp Seeking Extension of Expiration Date of Order,Dtd 980719,issued by Commission ML18040A3661999-06-0404 June 1999 Informs That Entire Attachment to Ltr NMP2L 1862 Dtd 990421, Should Be Replaced with Entire Attachment Being Sent with Present Ltr ML20195C9751999-06-0101 June 1999 Informs That Weld 32-WD-050 Will Be Reclassified Back to GL 88-01 Category a Weld & ASME Code Section XI Insps Will Be Conducted in Next Three Insp Periods ML20195C9601999-05-28028 May 1999 Provides Final Extent of Condition Evaluation Re Failed Cap Screw Beyond Upper Spring.Nmpc Continues to Conclude as Stated in That No Addl Mods Are Needed Other than Those Indicated in Ltr ML20207F1811999-05-24024 May 1999 Petitions NRC to Suspend Operating License of NMP for NMPNS Unit 1 Until Such Time as NMPC Releases Most Recent Insp Data on Plant Core Shroud & Adequate Public Review of Plant Safety Accomplished Because of Listed Concerns ML20195B1861999-05-21021 May 1999 Requests Staff Approval of Proposed Mod to Each of Four Tie Rods Per 10CFR50.55a(a)(3)(i).Summary of Tie Rod Insp Findings,Summary of Root Cause Evaluation of Failure of Cap Screw,Calculation B-13-01739-23 & Summary of Se,Encl ML20207D1541999-05-21021 May 1999 Forwards Issue 5,rev 0 of Physical Security & Safeguards Contingency Plan for Nmpns.Summary of Changes Included to Facilitate Review.Encls Withheld ML20207D5331999-05-21021 May 1999 Forwards Issue 3,Rev 1 of NMP Nuclear Security Training & Qualification Plan.Summary of Changes Is Included with Plan to Provide Basis for Individual Changes & to Facilitate NRC Review.Plan Withheld Per 10CFR2.790 ML20206S2621999-05-16016 May 1999 Expresses Concerns About Safety of Nmp,Unit 1 Nuclear Reactor.Nrc Should Conduct Insp of Reactor Including Area Besides Core Shroud Welds & Publicly Disclose Results at Least Wk Before Restart Date ML20195D5911999-05-13013 May 1999 Submits Final Copy of Open Ltr to Central Ny,With Proposals Re Nine Mile One Core Shroud Insp During Refueling Outage Which Began on 990411 ML20206P1981999-05-11011 May 1999 Forwards Response to NRC RAI Re NMP Previous Responses to GL 96-05, Periodic Verification of Design-Basis of SR Movs, for NMP Units 1 & 2 ML20206R6941999-05-10010 May 1999 Responds to 990413 & 0430 Ltrs Re Apparent Violation Noted in Investigation Rept 1-98-033.Util Agrees with Violation, But Disagrees with Characterization That Violation Was Willful or Deliberate ML20206N0291999-05-0707 May 1999 Forwards Rev 39 to NMP Site Emergency Plan & Revised Epips,Including Rev 1 to EPMP-EPP-03,rev 5 to EPIP-EPP-25 & Rev 5 to EPIP-EPP-28 ML20206G8121999-04-30030 April 1999 Forwards Comments on Draft Reg Guide DG-1083, Content of UFSAR IAW 10CFR50.71(e), Dtd Mar 1999.Util Generally Supports DG-1083 ML20206F7731999-04-22022 April 1999 Forwards Renewal Application for SPDES Permit Number NY-000-1015 for Nmpns,Units 1 & 2 1999-09-07
[Table view] |
Text
r u a -
Niagara @ Mohawk' ,
Richard B. Abbott
- Phone: 315.349.1812 Vice President May 21,1999 NMPIL 1436 i
U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 RE: Nine Mile Point Unit 1 Docket No. 50-220 DPR-63
Subject:
Generic Letter 94-03, "Intergranular Stress Corrosion Cracking of Core Shrouds in Boiling Water Reactors," Requestfor Approval Under the Provision of 10CFR50.55a(a)(3)(i)for Modification of the Four Stabilizer Assemblies (Tie Rods)for Nine Mile Point Unit 1 (NMP1)
Gentlemen:
By letters dated January 6 and 23,1995, Niagara Mohawk Power Corporation (NMPC) proposed a repair of the Nine Mile Point Unit 1 (NMP1) core shroud by installation of four stabilizer l assemblies (i.e., tie rods). The Staff approved the proposed repair in its letter dated March 31, 1995, as an alternate to the American Society of Mechanical Engineers (ASME) Code as allowed by 10CFR50.55a(a)(3)(i). This alternate repair was installed during the 1995 refueling outage (i.e., RFOl3).
Subsequently, during the 1997 refueling outage (i.e, RF014), NMPC identified the need for modification of tie rod lower wedge assemblies by letter dated April 8,1997. The Staff also approved this modification, which was installed during RF014, as an alternate to the ASME Code by letter dated May 8,1997.
The purpose of this submittal is to request Staff approval of a proposed modification to each of the four tie rods pursuant to 10CFR50.55a(a)(3)(i). A visual examination of a tie rod during the current outage (i.e., RF015) revealed that a 3/8 inch cap screw had failed and that the broken '
portion was dislodged from the upper spring assembly. An extent of condition evaluation for the !
uppper spring identified other cap screw locations on each of the tie rods that could experience similar failures in the future. In addition, although determined to be acceptable, visual !
examination of the reactor pressure vessel (RPV) cladding revealed areas of scratches and some evidence of wear at the locations where the upper spring of the four tie rods comes into contact with the RPV cladding.
J Accordingly, a proposed modification will replace the design function of the failed cap screw and other cap screws that have the potential for future failure. The modification includes changes to each end of the upper spring for each of the four tie rods. This proposed modification also i contains provisions to prevent the creation of loose parts in the reactor vessel due to the potential g for failure of the subject cap screws. In addition, the modification includes rounding off the c 9905280177 990521 PDR ADOCK 05000220 hgb p PDR ex 63. lycoming. New York 13093-0063
m; Page 2 ,
leading edges of the upper wedge and upper contact of the upper spring for the four tie rods as a preventative measure to reduce stresses on the tie rods and to reduce the likelihood of future wear on the cladding of the RPV.
t The proposed modification is being submitted to the Staff for review and approval as an alternative repair p_ursuant to 10CFR50.55a(a)(3)(i). This submittal contains the basis for -
concluding that the modification provides an acceptable level of quality and safety. Approval of this proposed alternative is requested prior to June 7,1999, which is the scheduled startup date of NMPl.-
Enclosure 1 contains a summary of the tie rod inspection findings.
Enclosure 2 contains a summary of the root cause evaluation of the failure of the cap screw.
Enclosures 3 and 4 contain the design documents that describe the proposed modification of the tie rods.' Specifically, Enclosure 3 contains four figures which depict the modification to the tie rods and a design stress report. Enclosure 4 contains a summary of the 10CFR50.59 safety evaluation of the proposed changes (i.e., the modification of the tie rods) to the facility as -
described in the Updated Final Safety Analysis Report (UFSAR). NMPC has concluded that the modification of the tie rods would not involve an unreviewed safety question.
The root cause evaluation provided in Enclosure 2 is preliminary in that it acknowledges one cause with the potential for the inclusion of two other causes. Specifically, the root cause of the cap screw failure was intergranular stress corrosion cracking in the alloy X-750 material driven by large, sustained differential thermal expansion stress due to fastening of dissimilar materials with the cap screw. A potential contributing cause was the sustained stresses that were attributed to the torquing of the cap screw associated with the original assembly of the tie rods. A second potential contributing cause was the stresses associated with friction between the vessel wall and the upper spring contact points. The proposed modification, as evaluated in NMPC's safety evaluation, already considers the combined effects of the one cause plus the two potential contributing causes. Therefore, it is expected that the proposed modification and the basis for concluding that it provides an acceptable level of quality and safety will be unaffected by our final evaluation of the two potential contributing causes. NMPC will provide the results of our final root cause evaluation within 30 days following restart of the unit. !
In addition, NMPC is continuing to evaluate the extent of condition beyond the upper spring.
Most of the evaluation has been completed and NMPC to date has concluded that no additional )
modifications are required to support restart of the unit other than those indicated in this letter.
l By May 28,1999. NMPC will provide the Staff the results of our final extent of condition j evaluation.
Very truly yours, BddQQw Richard B. Abbott Vice President - Nuclear Engineering
.RBA/KWK/ kap
s,
.. . ,0 .
Page 3 xc: Mr. H. J. Miller, NRC Regional Administrator Mr. S. S. Bajwa, Section Chief PD-1, Section 1 NRR -
Mr. G. K. Hunegs, NRC Senior Resident Inspector Mr. D. S. Hood, Senior Project Manager, NRR
~ Records Management
-l l
4 i
l r l i
- b. ._ f ')
? '.
. ENCLOSURE 1 i
l
SUMMARY
OF THE TIE ROD INSPECTION FINDINGS <
l
SUMMARY
OF THE TIE ROD INSPECTION FINDINGS TIE ROD INSPECTION FINDINGS The re-inspection plan for the core shroud tie rods was provided to the Staff in NMPC's letter dated December 30,1998 and approved by letter dated March 24,1999. The tie rod inspections included a combination of visual examinations.
Visual inspections (i.e., overall visual scan and the VT-3/EVT-1 visual examinations) were performed on each of the four tie rods. The following observations were made:
- 1. Adequate contact and engagement was verified at specified locations.
- 2. The tic rods were confirmed to be visually tight by verifying that contact existed at the clevis pin-to-hook interface and other critical locations.
- 3. Deflection measurements made on the RFO14 modified lower wedge latches indicates no significant loading and confirms the integrity of the modified latch design.
- 4. , Enhanced visual examinations of all the tie rod latches confirmed the integrity of the latches. I After completion of the overall visual scan and the VT-3/EVT-1 visual examinations, tightness
~
inspections were performed on each of the four tie rods. The tightness inspections demonstrated that sufficient preload was maintained for each of the four tie rods.
'The degraded condition of the four tie rods was discovered during the tightness inspections.
. Specifically, the post-torquing visual inspection of the critical areas of the 166 degree tie rod revealed that a 3/8 inch cap screw made of alloy X-750 material had failed and the_ broken
- portion had dislodged from the upper spring assembly. The broken portion included the cap screw head and part of J.e threaded screw. Approximately 2 to 3 threads were included with the broken portion. The failed cap screw is one of the four cap screws that attaches the upper
. spring bracket to the upper spring.
l Performance of the torquing activity during the tightness inspections for three of the tie rods does not require the removal of the upper springs. However, performance of the torquing -
L activity on the 166 degree tie rod requires removal of the upper spring to allow engagement of-the tie rod torque wrench to the tie rod nut due to interference with the shroud head bolt lugs. i This interface does not exist at the other three tie rod locations. After completing the torquing j
activity, the upper spring was re-installed. Subsequently, a visual re-inspection was performed on the 166 degree tie rod. It was this visual re-inspection that identified the degraded I condition (i.e., a broken cap screw).
Visual examination of the reactor pressure vessel (RPV) cladding revealed areas of scratches
. and some evidence of wear at the locations where the upper spring of the four tie rods comes I
.1 l
+ l
.;; .' 2 .
into contact with the RPV. This wear was most noticeable at the upper contact location on the {
RPV cladding for the 166 degree tie rod. Specifically, the wear included evidence of metal deformation.
1 1
i l l l
i 2
l
1 1
4 ENCLOSURE 2 '
I 1
SUMMARY
OF ,
ROOT CAUSE EVALUATION l
1 l
SUMMARY
OF ROOT CAUSE EVALUATION The core shroud tie rod assemblies at Nine Mile Point Unit I were designed and installed during RF313 in 1995, to replace shroud welds H1 through H7. There are four tie rod assemblies and each assembly includes an upper spring. The upper springs are attached to an upper spring bracket by (4) 3/8" cap screws. The upper spring and cap screws are made of alloy X-750 material and the upper spring bracket is made of Type 316 stainless steel.
During the 1999 outage, a cap screw was found to be broken during a visual inspection of the 166 degree tie rod assembly. An evaluation identified the root cause to be intergranular stress corrosion cracking (IGSCC) in the alloy X-750 cap screw material in conjunction with large, sustained differential thermal expansion stress due to fastening of dissimilar materials with the cap screw. A potential contributing cause was the sustained stresses that were attributed to the torquing of the cap screw associated with the original assembly of the tie rods. A second potential contributing cause is the stresses associated with friction between the vessel wall and the upper spring contact points.
The broken cap screw was shipped to the General Electric (GE) Vallecitos Center for metallurgical evaluation. The results of the metallurgical evaluation confirm IGSCC as the failure mechanism. The tie rod dissimilar metal connections affected by this condition exists at two locations per tie rod assembly. These locations involve four cap screws at the upper end and two cap screws at the lower end of each upper spring. A modification to the upper spring assembly has been designed so as to eliminate this problem and will be installed during the current outage.
l l
l 1
l
ENCLOSURE 3 I
MODIFICATION FIGURES AND DESIGN STRESS REPORT l
1 I
7 LPPER SUPPORT
\ stEmm omm
[ Ti [I E3 Ji RE I\
nI II a z a n UPPER wtOGE% l is se z
/-.o\
- ,Locs te nao nur upera snais - '
J
... (m nau e
%%,e so ,
im i LPPER CONTACT mio surecat LEFT/MICMT FM = i l
M-jm ano -"-
c-s m e .
4 l 1
Conc etarc se csa Y -
oort= semiac fx i unsiot Conc s.*ouo>g f
/ c,,,,,,c E
LOWER titDGE j
[ ,,
" l k 2B
[~g NLOWER CONTACT l, I 7 peCa nuts -
_ nam u
, , w_as. sann.v s, ,
CLEvts PIN i,
asWIDis e .l., i SECTION L-L l
Fi6tlRE \ - CORE SHROUD STABILIZERS
F
- 3, .
4 e
b~ 5tch3 p.,
"q >J 14
\ RE AGuRE 5 e
FbR EPMR BB6N J__ .
i s
M D E B SEE n WRE 4
- a. F- /EDR REPMR hE%R i Fi6URE 7. - UPPER SPR\MGr '
s c
0 0 ,l,l " O ,,ll
. . .L _ _'_ _ , ,_ _ ;_ _ _ _.{
,__._ t_q______ _4_ j 7_ _9_ _'
' - i h_ -
Y __J ;
k ______ [
, i. i ri*: .
,,y g7 _ __ - m t3a.s ,. ,., y1 n 4, 3, -- .
4 l;
- O _j i i i i :O, --
a
. _ _ s _; :
j
- g,_;.g
_a____.
_7__ _,
. _ a y _ _ .,_ =
!l NV m s ;
FIGURE 3 - UPPER CLAMP INSTALLATION
e g s
(, .' _ q _,_ _ _ _y.,
% M a* M
== 1 m. m.l .
i *'-% t !
l /
\f I6 &
__p__a___
l 1
. . . 'y e- $ \
t____l i i
l i .
a l i _
l I l 7
i
_ _ q _ ,i i I l
l 1
1 C c==
l 4 i I i
_pp.
l l
-__ I _' _
1 I f
/
FIGURE 4 - LOWER CLAMP ASSEMBLY
.