Second Motion for Extension of Time in Which to File Contentions.* Requests Extension for Filing Until 880620 Due to Continued Discussions Between Util & Commonwealth of Pa. Certificate of Svc Encl
ML20154H782
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 05/19/1988
From: Searchinger T
PENNSYLVANIA, COMMONWEALTH OF
To:
Atomic Safety and Licensing Board Panel
References
CON-#288-6363 88-569-06-OLA, 88-569-6-OLA, OLA, NUDOCS 8805260069
Download: ML20154H782 (4)


Text

---.. ~ . . -

pp h 3/o~k MY 19 '88 03: 43 C$T OF GW CCWSEl.

C0t hE 1Ei!

PNFC UNITED STATES OF AMERICA 's mY 20 P4 :15 NUCLEAR REGULATORT COMMISSION

i. , , , , -

ATOMIC SAFETY AND LICENSING BOARD gp ict . .,3, 00CKE M .s ~EiNiti B R a k. "

In the Matter of )

Docket Nos. 50-277-OLA

)

Philadelphia Electric Company ) 50-278-OLA ,

(Peach Bottom Atomic Power ) ASLBP No. 88-569-06-OLA Station, Units 2 and 3) )

SECOND MOTION FOR AN EXTENSION OF TIME IN WHICH TO FILE CONTENTIONS NOW COMES the Commonwealth of Pennsylvania and requests an extension of time in which to file its contentions in this licensing proceeding. In support of this motion, the Commonwealth states as follows:

1. On April 22, 1988, the commonwealth requested a first extension of time in which to file its contentions.

In support of this motion, the Commonwealth noted its desire to engage in discussions with the Philadelphia Electric Company (PECO) prior to filing its contentions.

2. On April 25th, this Board granted an oral extension of time until May 25, 1988.
3. On May 3, 1988, this Board issued a written order confirming this extension.

4 The Commonwealth and PECO nre now engaged in discus-sions.

5. In order to know if they can resolve their differ-ences, the Commonwealth and PECO believe they need more time than now provided by the May 25th deadline. They therefore kDob 00 h$k [7 G

pd3

, _ . ~ _ _ _ _ _

t%Y 19 'OO 03:43 CFF Or GEN ColtEL P.3/5 f

would like Ldditional time in which to engage in discussions before formally commencing adversarial hee. rings.

6. PECO supports this request for an extension of time.
7. The NRC staff is not opposed to this request.
8. The potential benefit from continued discussions constitutes good cause for an extension of time because the parties may be able to settle all or part of their dispute.

WHEREFORE this Board should grant an additional exten-sion of time of thirty days until June 20, 1988.

Respe tful,1y submitted.

Tim'othy D. searchinger

~

6/

Deputy General Counsel Commonwealth of Pennsylvania Thomas Y. Au Assistant Chief Counsel Richard P. Mather Assistant Counsel Department of Environmental Resources

  • S 0.5 Executive House P.O. Box 2357 Harrisburg, PA 17120 (203) 787-7060 Dated: May 19, 1988

PAY 19 '80 83 44 CfT Cr EN m ,

P.4/5 IN THE MATTER OF i g I PHILADELPHIA ELECTRIC COMPANY (Peach Bottom Atomic Power Station Units 2 and 3) 50-277-OLA and 50-278-OLA Docket Nos 1 CERTIFICATE _OF SER'VICE I hereby certify that ceples of the Commonwealth of Pennsylvania's Second Motion for an Extension of Time in which to file contentions were served this date upon the following by first-class mail, postage prepaid.

Samuel J. Chilk George C. Preeman, Jr., Esq.

Office of the Secretary Donald P. Irwin, Esquire U.S. Nuclear Regulatory Comm. Hunton & Williams Washington, D.C. 20555 707 East Main Street P.O. Box 1535 Richmond, Virginia 23212 Secretary of the Commission William T. Coleman, Esq.

Docketing and Service Section John H. Beisner, Esq.

Office of the Secretary O'Melvany & Meyers U.S. Nuclear Regulatory Comm. 555 - 13th Street, N.W.

Washington, D.C. 20555 Washington, D.C. 20004 Atomic Safety & Licensing John H. Prye , III, Chairman Board Panel Atomic Safety & Licensing Board U.S. Nuclear Ragulatory Comm. U.S. Nuclear Regulator 7 Comm.

Washington, D.C. 20555 Washington, D.C. 20555 Clenn O. Bright E.G. Bauer, Jr.

Atomic Safety & Licensing Brd. Philadelphia Electric Company U.S. Nuclear Regulatory Comm. 2301 Market Street Washington, D.C. 20555 Philadelphia, PA 19101 Richard F. Cole Ann P. Hodsdon Atomic Safety & Licensing Brd. Counsel for NRC Staff U.S. Nuclear Regulatory Comm. U.S. Nuclear Regulatory Comm.

Wachington, D.C. 20555 Washington, D.C. 20555

PFrf 19 '98 03:45 Cf7 0F GEN COLNSEL P.54 Jay Cutierrez Regional Counsel -

U.S. Nuclear Regulatory Conan, 475 Allendale Road ,

King of Prussia, PA 19406

) ado k Timothy I/. Searchinser U Deputy General Counsel Office of General Counsel 17th Floor. Harristown II 333 Market Street Harrisburg, PA 17120 (717)783-6563 DATED: May 19, 1988 f

I 4