|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:UTILITY
MONTHYEARIR 05000245/19900231990-11-15015 November 1990 Insp Repts 50-245/90-23,50-336/90-25 & 50-423/90-23 on 901001-05.No Violations Noted.Major Areas Inspected: Radiological Controls Program IR 05000423/19900191990-11-14014 November 1990 Insp Rept 50-423/90-19 on 900905-1015.Violations Noted. Major Areas Inspected:Operations,Radiological & Chemistry Controls & Security & Maint & Surveillance IR 05000213/19900831990-11-0505 November 1990 Insp Repts 50-213/90-83,50-245/90-82,50-336/90-82 & 50-423/90-83 on 900924-28.No Violations Noted.Major Areas Inspected:Licensee Timeliness for Reporting/Operability Determinations IR 05000336/19900181990-11-0505 November 1990 Insp Rept 50-336/90-18 on 900822-1001.One Cited Violation, One Noncited Violation & One Deviation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint,Previously Identified Items,Engineering/Technical Support IR 05000245/19900191990-10-26026 October 1990 Safety Insp Repts 50-245/90-19,50-336/90-21 & 50-423/90-17 on 900904-07.No Violations or Deviations Identified.Major Areas Inspected:Qa Program Implementation IR 05000213/19900821990-10-23023 October 1990 Insp Repts 50-213/90-82,50-245/90-81,50-336/90-81 & 50-423/90-82,on 901001-12.No Violations Noted.Major Areas Inspected:Licensee Occupational Radiation Protection Program Activities During Unit 1 Refueling Outage IR 05000336/19900191990-10-15015 October 1990 Insp Rept 50-336/90-19 on 900910-14.No Violations Noted. Major Areas Inspected:Open Items & Allegations from Insp Rept 50-336/89-13 IR 05000245/19900161990-10-0303 October 1990 Partially Withheld Insp Repts 50-245/90-16,50-336/90-17 & 50-423/90-16 on 900827-31.Violations Noted IR 05000423/19900101990-08-17017 August 1990 Insp Rept 50-423/90-10 on 900612-0723.Violations Noted.Major Areas Inspected:Normal & Backshift Work Periods of Plant Operations,Maint & Surveillance,Security,Engineering & Technical Support,Radiological Controls & Safety Assessment IR 05000245/19900141990-08-16016 August 1990 Insp Repts 50-245/90-14,50-336/90-15 & 50-423/90-13 on 900723-27.One Noncited Violation Noted.Major Areas Inspected:Radiological Controls IR 05000423/19900061990-08-14014 August 1990 Insp Rept 50-423/90-06 on 900604-08.No Violations or Deviations Noted.Major Areas Inspected:Training Program, Including Licensed Operator Training Program for Initial Licensing & Requalification Program for Licensed Operators IR 05000245/19900111990-08-0909 August 1990 Insp Repts 50-245/90-11,50-336/90-12 & 50-423/90-09 on 900611-15 & 25-29.No Violations Noted.Major Areas Inspected: Review of Licensee Emergency Diesel Generator Fuel Oil Program IR 05000423/19900801990-08-0202 August 1990 Insp Rept 50-423/90-80 on 900416-25.No Violations Noted. Major Areas Inspected:Development of Sufficient Procedures in Appropriate Areas to Cover Broad Spectrum of Accidents & Equipment Failures IR 05000336/19900111990-07-31031 July 1990 Insp Rept 50-336/90-11 on 900530-0711.Noncited Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls/Emergency Preparedness,Maint/Surveillance, Engineering/Technical Support & Security IR 05000245/19900131990-07-24024 July 1990 Insp Repts 50-245/90-13,50-336/90-13 & 50-423/90-11 on 900609-13.No Violations or Deviations Noted.Major Areas Inspected:Radiological Environ Monitoring Program,Including Mgt Controls,Audits & Surveillance Procedures IR 05000245/19900091990-07-20020 July 1990 Insp Rept 50-245/90-09 on 900515-0625.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000245/19900071990-07-0606 July 1990 Insp Rept 50-245/90-07 on 900403-0514.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000423/19900081990-07-0303 July 1990 Partially Withheld Insp Rept 50-423/90-08 on 900503-0611 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Maint & Surveillance,Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000336/19900081990-07-0202 July 1990 Insp Rept 50-336/90-08 on 900425-27.No Violations Noted. Major Areas Inspected:Results of Eddy Current Exam of Steam Generators Performed During Oct 1989,w/emphasis on Acceptable Period of Operation for Steam Generators ML20055E7991990-06-29029 June 1990 Insp Rept 50-336/90-09 on 900417-0529.Violations Noted. Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Engineering/Technical Support, Committee Activities,Periodic Repts,Lers & Allegations ML20055D1431990-06-20020 June 1990 Enforcement Conference Rept 50-245/90-08 on 900615.Major Areas Discussed:Findings in Insp Rept 50-245/90-08 Re Shipment of Irradiated Hardware as Radwaste to Low Level Waste Disposal Facility in Barnwell,Sc on 900507 ML20055C3161990-02-21021 February 1990 Insp Rept 50-245/89-19 on 891023-27.Unresolved Items Noted. Major Areas Inspected:Review of Selected Deviations from Rev 4 to to GE Topical Rept NEDO-31331, Emergency Procedure Guidelines & Response to NRC Bulletin 88-007,Suppl 1 IR 05000423/19890191989-09-22022 September 1989 Insp Rept 50-423/89-19 on 890828-0901.No Violations Noted. Major Areas Inspected:Radiological & non-radiological Chemistry Program Including Confirmatory Measurements, Chemistry & Lab Qa/Qc IR 05000245/19890181989-09-13013 September 1989 Insp Repts 50-245/89-18,50-336/89-18 & 50-423/89-15 on 890807-11.No Violations Noted.Major Areas Inspected:Util Compliance W/Atws Rule (10CFR50.62) & QA Annual Review, Including Procurement Program & Matl Receipt & Storage IR 05000245/19890801989-08-31031 August 1989 Insp Repts 50-245/89-80,50-336/89-80 & 50-423/89-80 on 890530-0616 & 0710-14.No Violations Noted.Major Areas Inspected:Units 1,2 & 3 Maint Program & Implementation, Review of Maint Documents & Observation of Work in Progress IR 05000336/19890161989-08-21021 August 1989 Insp Rept 50-336/89-16 on 890616-0726.Violation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Committee Activities,Emergency Diesel Generator Operation & Fuel Oil Sys IR 05000423/19890131989-08-21021 August 1989 Insp Rept 50-423/89-13 on 890724-28.No Violations Noted. Major Areas Inspected:Fire Protection Prevention Program IR 05000245/19890161989-08-0202 August 1989 Insp Repts 50-245/89-16 & 50-336/89-15 on 890711-14.No Violations Noted.Major Areas Inspected:Implementation of Radiation Protection Program IR 05000423/19890111989-08-0202 August 1989 Insp Rept 50-423/89-11 on 890613-0717.No Violations Noted. Major Areas Inspected:Facility Tours of MP-3 Site,Esf Sys Walkdowns of Recirculation Spray Sys,Si Pump Cooling Sys, Turbine Driven Auxiliary Feed Pump Sys & Review of LERs IR 05000245/19890141989-07-28028 July 1989 Insp Rept 50-245/89-14 on 890616-0717.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Physical Security,Control Room Exercise Equipment & NRC Temporary Instruction 2513/93 IR 05000336/19890111989-07-21021 July 1989 Insp Rept 50-336/89-11 on 890505-0615.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Surveillance, Maint,Previously Identified Items,Allegations,Committee Activities,Licensee self-assessment & LERs IR 05000423/19890121989-07-21021 July 1989 Insp Rept 50-423/89-12 on 890626-30.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Program,Steam Generator Eddy Current Insps & Water Chemistry Results IR 05000245/19890121989-07-19019 July 1989 Insp Rept 50-245/89-12 on 890509-0615.Major Areas Inspected: Previously Identified Items,Outage Activities,Plant Operations,Physical Security,Recirculation Pump Seal Failure Event,Reactor Scram on Low Main Condenser Vacuum & LERs IR 05000423/19890081989-07-11011 July 1989 Insp Rept 50-423/89-08 on 890515-0612.No Violations Noted. Major Areas Inspected:Plant Operations,Unresolved Item 50-423/87-12-01,previous Insp Findings,Plant Incident Repts, in-core Thimble Degradation & 10CFR50.59 Safety Evalautions IR 05000245/19890151989-07-0505 July 1989 Insp Repts 50-245/89-15,50-336/89-14 & 50-423/89-10 on 890619-23.No Violations or Deviations Noted.Major Areas Inspected:Effluent,Transportation & Solid Radwaste Programs, Including Mgt Controls,Audits,Qa & Program Implementation IR 05000245/19890131989-06-29029 June 1989 Enforcement Conference Rept 50-245/89-13 on 890621.Major Areas Discussed:Shipment of High Pressure Pump & Trailer W/ Removable External Radioactive Contamination from Licensee Reactor Site to Vendor Site in Moorestown,Nj IR 05000423/19890041989-06-28028 June 1989 Insp Rept 50-423/89-04 on 890405-0515.No Violations Noted. Major Areas Inspected:Plant Incident Repts,Reactor Scrams, Shutdown to Repair High Unidentified Leakage & Repair to Svc Water Piping & Physical Security IR 05000336/19890081989-06-20020 June 1989 Insp Rept 50-336/89-08 on 890324-0504.No Violations Noted. Major Areas Inspected:Plant Operations,Outage Activities, Surveillance,Maint,Plant Incident Repts & Allegations IR 05000245/19890081989-06-15015 June 1989 Insp Rept 50-245/89-08 on 880328-0508.No Unsafe Plant Conditions Noted.Major Areas Inspected:Plant Operations, Physical Security,Licensee Receipt Insp of New Fuel, Refueling,Plant Mods & LERs ML20245A8371989-06-0909 June 1989 Insp Rept 50-245/89-13 on 890517-18.Violations Noted Re Shipment of Package W/Removable External Radioactive Contamination in Excess of Limits & Failure to Supply Shipping Papers.Major Areas Inspected:Shipment of Pump ML20245A6781989-06-0707 June 1989 Insp Rept 50-245/89-11 on 890501-05.No Violations Noted. Major Areas Inspected:Observations,Review of Data,Licensee Response to Generic Ltr 88-01,NDE Procedures,Engineering Support & QA Involvement IR 05000245/19890101989-06-0707 June 1989 Insp Repts 50-245/89-10 & 50-336/89-12 on 890515-19.No Violations Noted.Major Areas Inspected:Fire Protection & Prevention Program,Including Program Administration & Organization & Administrative Control of Combustibles IR 05000245/19890091989-05-18018 May 1989 Insp Repts 50-245/89-09 & 50-336/89-10 on 890417-21.No Violations Noted.Major Areas Inspected:Review of Radiation Protection Activites at Unit 2 & Begining of Refueling Outage at Unit 1 IR 05000245/19890051989-05-17017 May 1989 Insp Repts 50-245/89-05 & 50-336/89-07 on 890417-21.No Violations Noted.Major Areas Inspected:Engineering Organization & Staffing,Qa,Plant Mods & Technical Training IR 05000423/19890031989-05-0303 May 1989 Insp Rept 50-423/89-03 on 890228-0404.No Violations Noted. Major Areas Inspected:Plant Operations,Status of Previous Insp Findings,Fuel Receipt & Insp,Generic Concerns About Steam Generator Tube Plugs,Esf Walkdown & LERs IR 05000245/19890041989-05-0303 May 1989 Insp Rept 50-245/89-04 on 8902214-0327.Major Areas Inspected:Previously Identified Items,Plant Operations, Physical Security,Ultrasonic Testing of Condensate Storage Tank,Maint Program Implementation & Committee Activities ML20246K0931989-04-26026 April 1989 Insp Rept 50-336/89-05 on 890211-0323.No Violations Noted. Major Areas Inspected:Outage Activities,Surveillance,Maint, Previously Identified Items,Plant Incident Repts & Allegations IR 05000245/19890061989-04-0707 April 1989 Insp Repts 50-245/89-06,50-336/89-09 & 50-423/89-06 on 890306-10.No Violations Noted.Major Areas Inspected:Review of Implementation of Radiation Protection Program at Unit 2 During Refueling Outage & Preparation of Outages for Units IR 05000245/19890071989-03-23023 March 1989 Insp Repts 50-245/89-07,50-336/89-06 & 50-423/89-07 on 890221-0303.No Violations or Deviations Noted.Major Areas Inspected:Site Observations & in-ofc Review of Data in Areas of Inservice Insp & Secondary Water Chemistry IR 05000245/19890031989-03-15015 March 1989 Insp Repts 50-245/89-03 & 50-336/89-04 on 890213-17.No Violations Noted.Major Areas Inspected:Unit 2 Refueling Outage Activities,Unit 1 Refueling Outage Preparation Activities & Station ALARA Practices 1990-08-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-039, 980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 9808111998-08-12012 August 1998 PNO-I-98-039:980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 980811 ML20237D3041998-08-12012 August 1998 Notice of Violation from Insp on 980413-0508.Violations Noted:Two Examples Identified Where Licensee Not Performing Leakage Testing of safety-related Valves in Sys That Could Contain Highly Radioactive Fluids During Accident IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20237B0741998-08-12012 August 1998 Notice of Violation from Insp on 980428-0629.Violation Noted:Licensee Failed to Direct Test Personnel to Close & Lock RHR Outboard Drain Valve IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc PNO-I-98-026, on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release1998-07-0101 July 1998 PNO-I-98-026:on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release PNO-I-98-025, on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting1998-06-30030 June 1998 PNO-I-98-025:on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support ML20249C6931998-06-19019 June 1998 Notice of Violations from Combined Insp on 980301-0427. Violations Noted:Prior to 980424,instrument Min Accuracy of Wind Speed Channels Were Not Measured as Required by Table 3.3-8 of Unit 2 TS 3/4.3.3.4 IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 ML20249B0421998-06-12012 June 1998 Notice of Violations from Insp on 980413-24.Violations Noted:Only 1 RCS Loop Operable W/Plant in Mode 4 on 980407 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes 1999-09-14
[Table view] |
See also: IR 05000423/1988004
Text
. ._ .. ,
!
'
. ..
.
.
'
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
' ENFORCEMENT CONFERENCE REPORT
. Report No. 50-423/88-04
Docket No. 50-423
License No. NPF 49
Licensee: Northeast Nuclear Energy Company
Facility: M111 stone 3, Waterford, Connecticut
'
- '
Confarence At: NRC Region I, King of Prussia, Pennsylvania
Conference Date: July 20, 1988
Approved by- s M/m8
E. C. McCabe, Chief, Reactor Projects Section 18
7b/88
Date
- Conference Summary:
Environmental Qualification (EQ) enforcement conference held to discuss signific-
ance of concerns about EQ of certain cable splices, Litton-Veam connectors, and
containment high range radiation monitors. The licensee provided their evaluation
of the regulatory and safety significance of these matters (Appendix A to this
, report). The NRC will evaluate the licensee input and separately issue appropriate
enforcement action.
!
,
?
A
8808160424 880809
PDR ADOCK 05000423
'
O PNU ..
J
,
. - -
,
o
-
.
..
.
DETAILS
1. Conference Attendees
Northeast Nuclear Energy Company
.
E. Mroczka, Senior Vice President, Nuclear Engineering and Operations
R. Werner, Vice President, Generation Engineering and Construction
P. Blastoli, Supervisor,-Licensing
M. Gentry, Millstone 3 Operations Supervisor
R. Peterson, Senior Engineer, Environmental Qualification
A. Roby, System Manager, Nuclear Engineering and Operations
B. Tuthill, Qualification Engineering
NRC Region I
W. Johnston, Acting Director, Division of Reactor Safety (DRS)
C. Anderson, Chief, Plant Systems Section (PSS), DRS
~
J. Durr, Chief, Engineering Branch, DRS
.
J. Gutierrez, Regional Counsel
R. Mathew, Reactor Engineer, PSS, DRS
E. McCabe, Chief, Reactor Projects Section 1B, Division of. Reactor Projects
R. Paolino, Senior Reactor Engineer, PSS, DRS
2. Conference Scope
r
The Director, Division of Reactor Safety outlined the enforcement conference
considerations as being the following.
--
Environmental qualification (EQ) issues identified during EQ inspection .
"
earlier this year.
.
--
Enforcement criteria are the general criteria applicable to a plant in
the operating license issue process, not the enforcement criteria for ,
plants in operation at the time the NRC environmental qualification rule ;
was issued.
--
The specific concerns are Litton-Veam connectors not potted as required,
the qualification status of Litton-Veam connectors at the time of the
EQ inspection, and high radiation monitor cable qualification under high
temperature conditions.
3. Licensee Presentation
The licensee presented their position on the EQ issues of concern, as identi- t
, fled in the appended presentation outline. '
2
I
3
, -
-
.
.
3
.
4. Raychem Splices Discussion
The licensee stated that their response to the already issued Raychem splice
violation will include justification of their position on the acceptability
of as-installed splice bends.
5. Litton-Veam Connectors ,
The NRC asked whether the Litton-Veam connectors were used to initiate a
safety function or affected the ability to achieve cold shutdown. The lic-
ensee responded that the Litton-Veam connectors are used to initiate safety
. functions but that their review had found that instrument redundancy, instru-
ment diversity (e.g., use of Veritrac instruments in some channels), and the
early time of required instrument actuatinn (in all cases except a slow loss
of feedwater level) all showed that the required safety functions would be i
performed. Also, the loss of the affected indications had been evaluated l
through covering the associated indicators on the plant simulator. In that .
condition, the operators achieved safety shutdown despite the loss of the L
indications. The licensee identified the only safety concern being the un-
likely simultaneous failure of all the affected instruments.
The NRC asked, for the Litton-Veam connectors installed in a configuration .
for which they were not qualified, whether the two valves of concern were
containment isolation valves (CIVs) and if so, were they in the same system.
The licensee responded that the two valves were inside containment CIVs in
different systems, with the outside containment CIVs valves available to
effect isolation not being affected by this problem.
6. Cont.ainment High Range Radiation Monitor (HRRM) Discussion
There was extended discussion of the licensee conclusion that the containment
..' HRRMs met NRC Regulatory Guide 1.97 accuracy criterion even with the identi-
fled cabling problem. The licensee also affirmed that the HRRM post accident i
function was not impeded by this problem. The licensee stated that the mag-
nitude of the error was greater at Millstone 1 than at Millstont 3 and that
an exemption from the Regulatory Guide 1.97 accuracy criteria may be requested.
(Functional capability is not suspect.)
The NRC questioned the timeliness of licensee resolution of the HRRM cabling
when the problem was identified. The licensee stated that their chronology
(Appendix A to this report) showed the timing of their resolution. Resolution
timeliness will receive further NRC evaluation.
The licensee committed to submit the documentation justifying HRRM operability
to the NRC. [
,
)
.
e
.
,
.
ENFORCEMENT CONFERENCE
50-423/88-04 *
APPENDIX A
Northeast Nuclear Energy Company
Millstone Unit No. 3
Docket 50 423
Equipment Qualification
July 20, 1988
. -
+
'
1
-
Meeting Agenda l
'o ,
.
July 20, 1988
Northeast Nuclear Energy Company '
.
EQ Enforcement Conference
for
Millstape Unit No. 3 .
.
I. Introductory Comments - NRC Staff
II. Introduction - E. J. Mroczka
III. Background and Summary of Findings - R. P. Werner
IV. Discussion of Potential Violation and Unresolved items
A. Potential Violations
1. Raychem Splices (50-423/88 04-06) -
B. A. Tuthill
2. Litton-Veam Connectors (IR Concerns) -
A. R. Roby
(50 423/88 04-05)
3. Litton-Veam Connectors (Configuration -
A. R. Roby
Concerns) (50 423/88 04-07)
4. GA High Range Radiation Monitors -
R. S. Peterson
(50-423/88-04-02)
B. Unresolved items
1. GA High Range P.adiation Monitor -
R. S. Peterson
(Potential for a 1.7 rad / hour error)
(50-423/88 04-03)
2. JC0 for Potential EQ Deficiencies -
P. A. Blasioli
(50 423/88-04-01)
3. Target Rock S0Vs (50 423/88 04-04) -
B. A. Tuthill
V. Conclusion - R. P. Werner
._______
.
-
.
'
. .
,
. NORTHEAST NUCLEAR ENERGY COMPANY
N!LLSTONE UNIT NO. 3
DOCKET 50 423 ,
.
EQUIPMENT QUALIFICATION
JULY 20, 1988
Introduction
Northeast Nuclear Energy Company (NNECO) received a full power operating
license for Millstone Unit No. 3 from the NRC on 'anuary 31, 1986. At that
time NNECO had implemented a comprehensive program to address the
environme. ital qualification of electrical equipment (EQ). Both NNECO and the
NRC determined that there was reasonable assurance that the plant w's in
compliance with the requirements of 10 CFR 50.49.
An NRC inspection tecm conducted an inspection at the plant on March 14-18,
1988, to verify NNECO's implementation of the EQ program. In Inspection
Report No. 50 423/88 04 dated July 6, 1988 (EA-88 177), the NRC identified one
Severity Level IV violation, four potential violations, and three unresobed
items with respect to 10 CFR 50.49. In this presentation NNECO addresses
thbe items. In addition, NNECO will respond separately to the Notice of
Violation by August 8, 1980 in accordance with 10 CFR 2.201.
Because Millstone Unit No. 3 received its full-power operating license after
November 30, 1985, the NPC's modified EQ enforcement policy of Generic
Letter 88 07 is inapplicable to the items identified to the NRC's ,
s
[m--
~
l
,' 2-
'
.
., _
,
inspection report. Accordingly, the potential violations noted in the
Inspection Report are addressed below in accordance with the considerations of
F
the NRC's general enforcement policy (10 CFR Part 2, Appendix C).
In summary, NNECO admits the proposed' violation regarding the installation of
1
Raychem splices over braided jacketing. NNEC0 denies the potential violation
with respect to bend radius and seal length of Raychem splices. Further, even
if such deficiencies are found, NNEC0 maintains that testing in March 1987
reflects they would have no safety significance. NNECO admits in part the
potential violations regarding Litton-Veam connectors, but maintains they also
have minimal safety significance given NNECO's demonstration of present
~
qualification, operabi1ity and corrective actions. Finally, NNECO denies the
potential violation regarding General Atomics (GA) High-Range Radiation
Monitors (HRRM). This equipment was qualified when installed. NNECO has
since evaluated vendor information to determine whether qualification status
is impacted, and concluded that 1) qualification has not been undermined and
2) th(. identified concerns have no safety significance. In all these cases,
NNECO has taken prompt measures to address the underlying concerns and to
ensure that qualification is maintained or promptly established.
The E0 Proaram
! NNECO, as the licensee for Millstone Unit No. 3, has implemented an effective
program for the qualification of electrical equipment. NNECO has and
continues to recognize the importance of the EQ program to safe operation of
its nuclear units, and its management is committed to completely addressing
f any EQ deficiencies or unresolved items at Millstone linit No. 3.
l
l
l
l
l
l
.
-3
.
.
'
.
.
NNEC0's EQ program for Millstone Unit No. 3 has been developed and implemented
.
to assure that appropriate electrical equipment will remain functional in a
.
harsh environment during and following a design basis event. As. a result of
the program, equipment should also remain qualified and be maintained in a
qualified condition throughout the life of the plant.
i
NNECO Nuclear Engineering and Operations Procedure Number NEO 2.21, "Nuclear
Plant Environmental Qualification Program," establishes the Millstone Unit
No. 3 EQ program. The program addresses, among other things, the scope of
equipment requiring qualification, the actions to be taken in the event any
equipment becomes unqualified, and the maintenance of the qualified condition
of the equipment. Auditable records of the selection, qualification, and
.
maintenance of the equipment are also maintained. Finally, the program
includes the requirements for EQ training, control of purchases of qualified
equipment, and control of design changes to assure proper EQ consideration.
Overall responsibility for the EQ orogram lies with the Senior Vice President,
Nuclear Engineering and Operations. Specific responsibility 'for overall
coordination, development, and implementation of the program rests with the
Vice President, Generation Engineering and Construction. These individuals
are knowledgeable with respect to the program and are committed to its
continued success.
In the NRC's July 6, 1988 inspection report, the Staff specifically found that
NNECO has implemented its program in compliance with 10 CFR 50.49. The NRC
which classified as Severity Level IV.
identified one violation, it
.
_ _ _ ..
'
.
,
-4-
'., -
In addition, the Staff identified four potential violations and three
.
unresolved items. In terms of both the number of potential deficiencies and
the low safety significance of those items (as discussed below). NNECO
believes that the EQ Program at Millstone Unit No. 3 has been eTfective and
compares favorably to EQ programs throughout the industry. The deficiencies
identified are isolated in nature and do not reflect any programmatic
weaknesses.
The following discussions of each enforcement item separately address the
questions raised by the NRC in the July 6, 1988 inspection report.
.
b
6
1
e
a
,
w
.
.,
,
.
5-
'
.
.,
, ISSUE N0. 1
(RAYCHEMSPLICES)
.
.
A. STATEMENT OF THE ISSUE
<
NRC Inspection Report Issue 50 423/88-04 06 states, "A review of licensee
walkdown records for Raychem splices indicate (s) additional nonconforming
conditions involving excessive splice bends (less than the recommended
5 X cable outside diameter) and splice seal length areas of less than
2 inches." According to the Staff, these deficiencies constitute a
potential violation of 10 CFR 50.49 in that the splices were not
qualified per the instruction procedures in effect at the time of the
installation. In addition, the Staff has issued a Notice of Violation
proposing a Severity Level IV violation for Raychem splices installed
over braided cable jacketing, contrary to the Raychem installation
procedures.
B. NNECO POSITION REGARDING THE EXISTENCE OF A VIOLATION
NNECO admits the proposed violation regarding installation of Raychem
splices over braided cable jacketing and will provide its written
response in accordance with 10 CFR 2.201.
NNECO does not agree that the walkdown records indicate that the Raychem
installations had splice lengths less than two inches.
.
'
, 6-
.
.
.,
NNECO also does not agree with the Staff's conclusions that installation
.
of Raychem splices with a bend radius less than 5 x the cable outside
diameter was contradictory to the Raychem procedure / instructions existing
'
at that time.
NNECO followed existing procedures with regard to these installation at
the time the plant went into operation,
in the event the Staff concludes that its assertions are valid, NNECO
maintains that the alleged deficiencies should be treated as further
examples of the deficiency already addressed in the Severity Level IV
Notice of Violation (NOV) issued in Inspection Report 50-423/88 04. A
separate violation on these related issues would not be warranted.
Further, should the Staff decide that a separate NOV is appropriate
regarding the potential violation based on the information provid 1
below, NNECO believes that the issue has no safety significance. The
lack of safety significance of this issue and other relevant factors are
discussed below.
C. BASIS FOR DENYING THAT A DEFICIENCY EXISTED
Bend Radius
The original installation of the splices was made in accordance with
Millstone 3 Electrical Installation Specification No. E-350. This
.
.
7
-
.
'
-
.
procedure stated that Raychem installation instructions shall be in
accordance with Raychem's "Product Installation and Inspection Guide -
WCSF-N Heavy Wall, Flar.e Retarded Nuclear Cable Sleeves" '. PII-57100-A
~
and installation instructions provided with each kit. E-350 also states
that QC shall verify (in accordance with specifications) that proper
Raychem components are used, manufacturer's installation instruction have
been followed, and an acceptable splice has been made.
During the time at which Raychem froduct Guide PII-57100-A
(November 1982) was in effect, Raychem did not provide bend radius
acceptance criteria. Accordingly, contrary to the inspection report
findings, the Raychem installations were made in accordance with
procedures in existence at this time. Upon issuance of NRC Information
Notice 86 53 (June 26,1986), NNECO took reasonable and prudent actions
to address the issue. Bend radius criteria were first published in
Pil 57100 0 (November 1987).
Seal Lenath
Contrary to the NRC inspection report, NNECO's review of walkdown records
does not reveal any instances where RUchem splices with less than 2 inch
seal lengths exist. QC witnessed the installation of some of the splices
and did not note any such seal length deficiencies. NNECO has no other
indications that such seal length deficiencies exist. Therefore, NNECO
denies that the alleged seal length deficiency existed. It should be
noted that after issuance of Information Notice 86-53, where this issue
was raised, NNECO took reasonable and prudent actions to address it.
-
-
.
-
.
.. -8-
.
D. SAFETY SIGNIFICANCE FINDINGS
These issues have no safety significance because:
1. March 1987 testing has established that application over braid, a
bend radius much less than 5 x the outside diameter, and seal
lengths much less than 2 inches are qualified configurations.
Accordingly, no replacements or modifications of the components were
required to establish or maintain qualification.
2. Similar enforcement actions at Ginna (J1ne 10,1987), Haddam Neck
(April 1, 1988), Grand Gul f (March 25, 1988). and North Anna
(April 19, 1988) did not have significant safety implications in
that the enforcement actions were categorized at a Severity
Level IV.
E. OTHER FACTORS THAT SHOULD BE CONSIDERED
1. Notwithstanding the final determination regarding the existence of a
violation, craft personnel have received additional training to
emphasize the importance of following procedures during component
installations.
2. In addition to the above, specific Raychem training war provided by
Raychem personnel to ensure that installations were correct.
!L
!;
.
.. _ _ - __ _. ~ _ __
,
'
.
,
.
- 9-
,
- 3. The EQ file was revised prior to the inspection to include test data
,
(dated March 1987) that confirms the qualifiention of Raychem
splices with over braided cable jacket, splices less than a 2-inch
seal -length and less than 5X outside diameter splice bends. The
Staff has concurred with the acceptability of the March 1987
report to further establish qualification. (itt Inspection
! Report 50423/8804,atp.21.)
1
)
!
.
.
-
1
4
I
(
_ - ~ . . . . . . , _ _ , --,__-.-__y .,---_,m --w. , -
-._,
,
.
,
.
-
- 10 -
..
LITTON-VEAM
(INSULATIONRESISTANCE(IR) MEASUREMENTS)
A. STATEMENT OF THE ISSUE
NRC Inspection Report Issue 50-423/88 04-05 states that "[t]he inspector
was concerned that low IR values during LOCA test could be the result of
moisture penetration into the seal. Due to a lack of IR measurements
during the LOCA transient conditions, the worst-case IR measurements and
hence leakage current could not be established, thus making it impossible
to detemine the contribution of the connectors to the instrument loop
accuracy under a LOCA envirnment . . . . Thus, for the Litton Ver.m
multipin connector assemblies installed on instruments located inside
containment, the licensee did not adequately establish the equipment
performance standards in the test acceptance criteria and did not provide
adequate evidence that this equipment we.uld perform its intended function
for all service conditions postulated to occur during the qualified
life."
8. NNECO'S POSITION REGARDING THE EXISTENCE OF A VIOLATION
NNECO agrees that IR measurements were not tahen during LOCA transient
extremes and that inappropriate performance standards were used during
the evaluation of Litton-Veam qualification test results. This
deficiency resulted in insufficient evidence (at the time of the NRC
inspection) to fully support an EQ file conclusion that certain
,
.
.
. .
-
- 11 -
.
Litton-Veam (L-V) connectors were qualified for a 40-year life. NNECO
does not contest this potential violation.
.
.
As discussed further below, NNECO believes that because the IR concerns
do not apply to un-aged connectors, these connectors were in fact
qualified both for their present installed life and for the near term.
Moreover, because the associated components would have performed their
intended function, there was no resultant safety significance.
C. . SAFETY SIGNIFICANCE
This issue is not safety significant because:
1. At a March 21, 1988 meeting, NNECO and the Staff agreed that IR
degradation did not unacceptably affect un-aged connector
performance requirements. Further, until significant aging of the
connector has occurred, NNECO and the Staff agreed that there is
reasonable assurance that existing equipment will perform its
intended function if called upon to operate in a harsh environment,
in that Millstone Unit No. 3 did not receive its full-power
operating license until January 1986, the installed connectors have
to date not been sufficiently aged so as to affect performance
'
requirements for accuracy to a degree that renders them unqualified.
NNECO acknowledges that a definitive long-term qualified life cannot
be determined with current test results. However, NNECO also
4
believes that it is reasonable to conclude that the second refueling
outage is not beyond qualified life. .(Ita Item 2 below). This will
.
.
.
',_ -
- 12 -
l
!
take place when the connectors have experienced 36 months of service
life. At that time the connectors will not have aged more than
~
1.6 % of end of-life condition calculated at normal maximum average
service temperature.
2. The Staff has previously concurred with NNECO's decision to replace
the connectors during the refueling outage currently scheduled for
June 1989. This supports NNECO's conclusion that the connectors are
still qualified and functional, and that there is no safety
significance in using the connectors until replacement.
3. A similar enforcement action at Sequoyah (June 17,1987) resulted in
the aggregation of eight items as a Severity level IV, one of which
was failure to meet loop accuracy requirements for Eaton
multiconductors signal cables, reflecting no significant safety
implications.
D. ROOT CAUSE
The root cause for the L-V testing deficiency is an isolated failure to
sufficiently incorporate IR measurements in the testing program and
adequately consider the effect of IR changes in determining qualification
and qualified life.
E. CORRECTIVE ACTIONS / ACTIONS TO PREVENT RECURRENCE
1. NNECO will take extensive corrective action by replacing the
affected Litton-Veam connectors (i.e., 43) with qualified
{
,
.
'
-
..
13
.
feed-through devices during the June 1989 refueling outage. This is
a conservative action in that we believe that additional testing
?
would likely have justified an extended qualified life. ,
2. NNECO believes that continuing training addressing the evolving
level of knowledge regarding the use of IR data will ensure that
appropriate IR requirements are considered during future testing.
F. OTHER FACTORS THAT SH0VLD BE CONSIDERED
1. As previously stated, NNECO has conservatively agreed to replace
co r'. a i n affected connectors at the next refueling outage, even
though we do not believe that their qualified life will be exhausted
at that time.
2. This deficiency was isolated in that a single root cause affected
only one type of component. The deficiency identified related only
to connectors used in instrument loop applications subject to a LOCA
environment.
3. NNECO did establish acceptance criteria prior to testing, but later
determined that the criteria were not anplicable to the intended use
of the connectors in instrument loop c'rcuits.
4. The issue of loop accuracy is an evolving issue which has only
recently been fully addressed by either the Staff or industry.
.
,
'
e
'
- 14
. .
-
ISSUE N0. 3
LITTON-VEAN(CONFIGURATION)
.
P
A. STATEMENT OF THE ISSUE >
HRC Inspection Report issue 50-286/88-04-07 states that "(djuring the
test plan review (NTS QPP No. 5581657, Revision 1), the inspector
observed that the test specimens were prepared following an assembly
procedure, VAP 241. This procedure required that heat shrink tubing be
applied over the contact wire crimped termination before potting the rear
1
of the connector with epoxy. The licensee's Electrical Installation
Specification No. E-350, which was in place from the initial commencement
of installation of the connectors on March 6,1984, until its cancella-
tion on March 26, 1984, did not incorporate the heat shrink tubing over
the pin / conductor interface . . . . Of the 21 connectors identified
(without heat shrink tubing) only two cases were found that were required
to remain functional to mitigate a LOCA/HELB event. These two cases
involved position indication for two containment isolation valves."
8. NNECO'S POSITION REGARDING THE EXISTENCE OF A VIOLATION
NNECO agrees that 21 titton-Yeam connectors were found in a configuration
for which qualification had not been established. As further discussed
below, the safety significance of this finding is minimal.
- - . ._.
.
,
. - 15 -
'.. '
C. SAFETY SIGNIFICANCE
.
This issue has minimized safety significance because:
1. Analysis reflects that virtually all components associated with
these connectors were qualified for their environments and, as a
practical matter, some could likely be removed from the EQ Master
List. Discussed further below are specific safety significance
findings regarding the 21 connectors. At bottom, only two cases
(four connectors) were found where the equipment (see item e below)
would have been required to remain operable to mitigate the event
causing the local harsh environment. For these two cases, the
failure would not have impacted operation of the associated valves,
but only valve position indication.
a. Several connectors and associated limit switches provide (a)
isolation of component cooling water (non-safety related return
sub-header on a containment isolation Phase A signal (CIA) on a
loss of power signal); (b) isolation of redundant reactor plant
component cooling water flow (to the Train A non safety related
return sub-header on a CIA and/or loss of power signal); and
(c) isolation of Train A/B reactor plant (non-safety related
supply sub-header on a CIA signal and/or a LOP signal). The
connectors are not located inside containment and are not in a
moisture environment. A one-time HELB is postulated for these
connectors. However, the Millstone Unit No. 3 design basis
does not analyze a one-time HELB in the area of the connectors
concurrent with an inside containment HELB. Therefore, the
,
.
-
16 -
..
, connectors would navs remained functional throughout an inside
containment design basis accident or would not have been
required to mitigate an accident while in a moisture
environment.
,
b. Several connectors (located outside containment) involve the
operation of the charging pump cooling pumps. These pumps are
required whenever the charging pumps must operate. A one time
HELB is postulated for the affected connectors. However, the
HELB is net postulated coincident with an inside containment
LOCA or main steam line break (MSLB). Therefore, either the
connector will not be in a moisture environment when required
to respond to an inside containment design basis accident (for
a LOCA and MSLB) or will not be required to mitigate an
accident while in a moisture environment.
c. Certain connectors in conjunction with level switches monitor
reactor plant component cooling water surge tank level, split
,
flow to the reactor coolant pumps and shut the supply / return
valves to the containment air recirculation cooling coils and
neutron shield tank coolers on low surge tank level. The
connectors / switches are located outside containment in a
i
non moisture environment. They are postulated to experience a '
one-time HELB. In that tne HELB is not postulated to occur
concurrent with a requirement to isolate containment (due to a
LOCA), the ability of the connectors / switches to perform
intended safety functions has not been impaired. In addition,
- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
.
-
.
'.. -
37
these level indication switches provide a control function
only. Failure does not provide misleading information and,
according to E0Ps, would have resulted in t,he operator
utilizing alternate level indication.
d. Certain connectors in conjunction with pressure switches l
isolate Trains A/B service water system supply to the turbine
plant component cooling water (TPCCW) system (closes TPCCW heat
exchangers tube side inlet isolation valves on low Train A/B
service water header pressure on a Train A/B containment
depressurization activation and/or loss of power signal). The
connectors are not located in a moisture environment (outside
containment) and are postulated to be exposed to a one-time
HELB. However, the one-time HELB is not postulated concurrent
with an inside containment design basis accident. Therefore,
as with several other connectors previously discussed, the
connectors will either be able to perform intended functions or
will fail without being required to mitigate a design basis
accident.
l e. Four connectors are associated with providing nitrogen charge
I
to the pressurizer relief tank, and maintaining a supply of
l
l
primary grade water to the pressurizer relief tank, the reactor
coolant pump level standpipes and the neutron shield tank
cooling system. These connectors are located inside
containment and reasonable assurance that these connectors
.
18 -
,
.
[
would not fail in the event of a LOCA or MSLB was not provided
.
by the qualification file. However, it should be noted that
the associated limit switches impacted by such a failure
provide only valve position indication. The functioning of
associated valves would not be affected should the connectors
fail.
2. In a NOV dated November 19, 1987 agiinst the Maine Yankee Atomic
Power Company (MY), the NRC cited MY for failing to provide a
similarity analysis between the tested specimen and installed
connectors (configuration). This NOV was categorized.as a Severity
Level IV. We believe that the finding at Millstone Unit No. 3 is
similar to the NY NOV in that a similarity analysis should have been
provided to address connectors without heat shrink tubing. We also
believe that the Millstone Unit No. 3 finding is certainly no more
safety significant than the MY enforcement action.
D. ROOT CAUSES
1. An engineering design / Stone & Webster interface failure to ensure
that a design intent was included in an installation procedure.
2. An engineering design failure to include in the test program
adequate requirements to demonstrate operability of connectors s
without heat shrink tubing being applied and subsequent
misapplication of the test report,
,
r
I
.
.
-
,
19 -
.
E. CORRECTIVE ACTIONS / ACTIONS TO PREVENT RECURRENCE i
1. Promptly after it was determined that certain connector
configurations had not been fully analyzed, NNECO performed an
operability evaluation, modified administrative controls, and
"caution tagged" the two affected valves. Position indication for
the two valves is assured by tagging them closed except when needed
to be opened. This provides continuous administrative verification
of valve position.
2. After issuance of a stop work order on March 26, 1984, to terminate
installation without heat shrink tubing, the installation procedure
was promptly revised (by April 5,1984). Prior to implementing the
procedure to require the correct installation configuration, craft
and engineering personnel were retrained.
3. NNECO met on March 27, 1984 with Stone and Webster to discuss
requirements for heat shrink tubing. After significant discussion,
a revised procedure was initiated to require the use of heat shrink
tubing. Additionally, it was decided that connectors without heat
shrink tubing would be included in an upcoming qualification test
program to demonstrate connector qualification without heat shrink
tubing. However, in retrospect, this testing did not resolve the
issue of concern,
4. From that time forward, all subsequent Category I engineering and
design change requests (E&DCRs) were required to be reviewed by E0
personnel prior to implementation. The plant was also walked-down
r , 20 -
. ,
.
100% to verify visually EQ attributes to ensure that they were in
,
accordance with engineering design requirements,
e
'
5. NNECO believes that continuing training regarding the 'use of test :
data will ensure that appropriate parameters are included in future
<< testing and test results evaluation.
6. The four connectors used for containment valve position indication
will be replaced with new connectors with heat shrink tubing during
the next refueling outage.
F. OTHER ISSUES THAT SHOULD BE CONSIDERED
1. The deficiencies were of minimal or no safety significance.
2. Once the deficiency was discovered, NNECO took prompt actions by
analyzing operational considerations and proposing corrective
actions.
-
.
-
- 21 -
.
. .
,
. '
ISSUE NO. 4
GENERALATOMICS(GA)HRRM
.
.
A. STATEMENT OF THE ISSVE
NRC Inspection Report Issue 50-423/88 04 02 concerns GA HRRMs installed
in containment prior to the licensing of Millstone Unit No. 3. The
Inspection Repcrt states that "there are indications that the GA HRRMs
were qualified when installed and prior to licensing of the Millstone
Unit No. 3 facility." However, ir light of information from the vendor
(dated November 6, 1986) indicating IR problems with the HRRM cable
assembly, the inspection Report states that "it appears that the licensee
was still in the process of evaluating the qualification . . . at the
time of this inspection. The licensee apparently has not followed the
guidelines of the NRC Generic Letter 86-15. The licensee has assumed
that the GA HRRM is operable until the vender information is confirmed."
8. NNECO'S POSITION REGARDING THE EXISTENCE OF A VIOLATION
NNECO's position is that this item does not presently represent a viola-
tion of 10 CFR 50.49. NNECO had adequate documentation in the GA HRRM
file to qualify the components at the time of their installation. NNECO
subsequently analyzed additional vendor information and concluded that
the equipment is still qualified. To the extent that there are still any
open issues regarding these analyses, this item should be more properly
classified as an unresolved item rather than as a potential violatten.
,
- 22 -
. Should the Staff maintain that a violation exists, NNECO believes that
the deficiency has no safety significance for Millstone Unit No. 3.
,
'
C. FACTORS SUPPORTING NNECO'S POSITION
As previously stated, the two GA HRRMs were considered qualified at the
time they were installed. The inspector reviewed NUSCO engineering
assurance audit Finding No. 3-10, contained in Memorandum No., 1103866
(dated July 24,1987), which incorrectly suggested that the GA HRRMs were
being qualified while in use. However, this finding wo addressed in
NUSCO memo GSP 87 387, B.A. Tuthill to B. S. Kaufman (October 29,1987).
NNEC0 has taken and continues to take the position that the GA HRRMs
installed at Millstone Unit No. 3 were qualified. This conclusion was
restated in NNEC0's letter to the NRC, B12671 E. J. Mroczka to
U.S. Nuclear Regulatory Commission, dated September 30, 1987.
The current issue addresses IR uncertainties addressed in post startup
information supplied by the vendor, Sorrento Electronics (Sorrento).
Specifically, the cable used in connecting the detector output to the
containment penetrations (RockbestosRSS6104) exhibited undesirable
characteristics at LOCA temperatures. At these temperatures, the elec-
trical IR decreases, increasing cable leakage currents which in turn
would reduce indicated radiation levels. The issue was first raised in
Northeast Utilities letter GSP 86 570 to Sorrento, J. S. Nicosia/
W. J. Hayes to Zvi Rendel (dated October 14, 1986). In that letter,
NNECO identified IR concerns and sought justification for the factor of 2
accuracy of the HRRM system. Sorrento responded on November 6, 1986,
i
_ _ _ _ _ _ _ _
,- ,
- 23 -
'
.
- This information adequately addressed the issue for Hillstone Unit No. 3
and confirmed qualification of the GA system.
,
Subsequently, in February 1987, Sorrento issued a Part 21 notification of
cable IR deficiencies. Following notification of this potential problem,
NNECO implemented a Sorrento calculational methodology to evaluate the
-
Rockbestos coaxial cables used in the GA HRRMs for Millstone Unit No. 3.
(A detailed chronology of NNECO's efforts in this regard is attached.)
Using that methodology, the calculated overall loop accuracy equated to a
maximum error of <1 R/hr. Thus, the factor' of accuracy for this equip-
ment specified in Regulatory Guide 1.97 is met.
With respect to the issues raised in the July 6,1988 inspection report
(i.e., compliance with 10 CFR 50.49), NNECO considers that the HRRMs are
qualified. To the extent that there are open questions regarding this
conclusion, this item should be regarded as an unresolved issue rather
than a potential violation.
NNECO has followed procedures analogous to those outlined in the Generic
Letter 8615 for addressing the potential EQ deficiency. Specifically,
as indicated by the chronology of events, NNECO has in a timely fashion
addressed the new information and concluded that the equipment is in fact
qualified. Pending this determination, NNECO prepared and maintained a
JC0 only as a conservative approach to be utilized if continued qualifi-
cation could not be shown. However, this JC0 was never implemented.
In this situation, NNECO properly undertook an evaluation to assess the
impact on qualification status and to assess reportability. NNECO
-
.
24
.
maintains that it was not required in this instance, upon receipt of
vendor information, to assume that the HRRMs were not qualified (given
that they were already considered qualified). NRC regulations in 10 CFR
Section 50.72 and 50.73 inherently recognize the time allowed for this
evaluation and do not call for interim reports to the NRC of "potentially
reportable" conditions. NNECO ultimately completed its reportability
evaluation and concluded that this event was not reportable under 10 CFR
50.72 or 50.73.
D. SAFETY SIGNIFICANCE
NNECO has concluded that this item has no safety significance. The GA
HRRMs are located inside containment. They are used to detect post-
accident radiation levels between 1 R/hr and 10 million R/hr. Any
unsatisfactory IR at elevated temperatures could lead to a reduction in
the indicated radiation levels at low ranges under certain conditions.
However, NNEC0 has concluded for the following reasons that the HRRMs
remain operable and would not mislead the reactor operator.
1. The principal function of these monitors is to assist in making
emergency assessment determinations, in this regard, NNECO has
performed a conservative evaluation of the HRRM readings under ,
maximum postulated containment temperatures, taking into account
cable and penetration current leakages. The Hillstone Unit No. 3
HRRMs meet Regulatory Guide 1.97 guidelines, even with maximum
potential biases due to reduced cable insulation resistance follow-
ing a LOCA or MSLB.
.
s
o
,
- 25 -
. 2. At the time when assessment of plant conditions would be made in
accordance with established (plant-specific emergency action levels)
guidance, either containment temperatures are not predicted to be
elevated (and, thus, these biases do not exist) or indications
independent of the HRRMs (i.e., elevated temperature, reactor
coolant system level, and leak rate indications) provide appropriate
information to permit valid assessment of plant conditions. Most
importantly, determinations concerning public protective measures
based even in part on containment radiation levels occur at such
high containment radiation levels that the potential biases would be
undetectable.
3. In addition, alternative means are available to determine fuel
conditions and containment curie inventories. The primary alterna-
tive method involves radiation monitors located outside the contain-
ment sensing through penetrations. Also, post-accident sampling
system samples, process monitors outside containment, and thermal
hydraulic parameters provide information that permits assessment of
fuel conditions and/or curie inventory.
4. Finally, although they provide no automatic control function, the
monitors are used at Millstone Unit No. 3 in making certain dect-
sions under the emergency operating procedures. For Millstone Unit
No. 3 there is a decision point at 1 x 105 R/hr for assessing envi-
ronmentally qualified electrical equipment instrument accuracy.
NNECO has concluded that the HRRM biases in the ranges of those
<
t
,
\
'
oj .
- 26 -
decision points are negligible and, thus, the HRRMs fulfill these
functions.
.
In addition, recent enforcement history in a similar case indicates that
this issue has low safety significance. In similar circumstances, the
NRC has classified a violation regarding GA HRRM qualification deficien-
cies as a Severity Level IV. In an enforcement action involving
Tennessee Valley Authority's Sequoyah Units I and 2 (June 17,1987), the
Staff found that the licensee had not adequately established qualifica-
tion for GA Technologies RD 23 radiation detectors and the associated
Brand Rex coaxial cable. This was one of eight qualification deficien-
cies collectively categorized as a Severity Level IV violation. NNECO
concludes that the circumstances in the present case are certainly no
more significant, and probably less significant given that there is less
equipment involved.
E. OTHER CONSIDERATIONS
Inspection Report 50 423/88 04 also includes two unresolved items that
relate to the HRRMs. NNECO believes that these items can be resolved.
1. . Item No. 88 04 03. This item concerns the potential for an error of
about 1.7 rad /hr. over the entire range for the GA HRRMs. The NRC
inspector observed tnat this error "could lead to the detector going
off-scale at the low end and the green ' operate' light going off.
This could result in subsequent high radiation readings which could
confuse the operator even though the readings were accurate."
i
I
-
, . _ _ _ . _ -
.
%
'
.[ .
27 -
NNECO committed to revising the operations procedure number OP 3362,
"Radiation Monitor System Display and Control System," to address
this concern. The revision was completed May 10,198'8 . In addi-
tion, NNECO comitted to incorporate this HRRM alarm response into
the Control Room Operator Requalification Training Program and to
notify control room operators of the potential problems. These
training activities have been accomplished. Therefore, this unre-
solved item should be closed.
2. Item No. 88 04-01. This item concerns NNECO's procedure NEO 2.25,
"Identification and Implementation of NRC Reporting Requirements."
and the need to "proceduralize the licensee's JC0 process." The
Staff was concerned that NEO 2.25 did not contain an express provi-
sion requiring preparation of a JC0 when a "potential EQ deficiency"
is identified. At the exit meeting NNECO stated that it would
consider adding directions in the procedure NEO 2.25 to address the
need for JCOs for EQ deficiencies.
NNECO does have controls in place to assure adequate evaluation and
timely corrective action of identified nonconformances to include
equipment governed by technical specifications that has been deter-
mined to be inoperable for any reason.
NNECO notes that, well prior to the NRC inspection, a program to
strengthen procedural controls regarding EQ was begun. As part of
this program, a 1987 internal audit suggested that NNECO's proce-
dures be clarified regarding preparation of JCOs in the event of
'
.
.' -
28 -
..
9 ,,
, identified EQ problems. In response to this internal audit, NNEC0
has concluded that the need to prepare JCO's are not issue specific
and could relate to concerns other than EQ. Therefore,*this concern
can best be addressed generically in existing Nio 2.25 on
reportability.
NNECO has prepared a draft revision of NE0 2.25 to clarify that a
JC0 will be prepared in appropriate cases. Note, however, that
NNECO does not contemplate preparing a JC0 for equipment simply if
there is information suggesting a possible qualification deficiency.
Rather, where NNECO no longer has reasonable assurance of qua'ifica-
tion cf the equipment, appropriate action, such as preparation of a
JCO, will be initiated. The revised NE0 2.25 is currently under-
~'
going internal NNECO review, and is expected to be issued shortly.
>
,
f
$
i
.
I
f
.
'
,- ', - 29 -
..
.
.
UNRESOLVED ISSME
t
.
, A. ETAT OF THE ISSUE I
Ne ' ion Report unresolved issue 50-423/88-04-04 addrasses the
.
re..c 4 the EQ file for Target Rock solenoid operated valves (S0Vs). )
1
The inspectors were specifically unable to determine if IE Notice l
(IEN) 84-68, "Improperly Rated Field Wiring to Solenoid Valves,' had been
addressed for the Target Rock S0Vs at Millstone Unit No. 3. In addition,
the Staff requested formal documentation of calculations considering the
impact on aging calculations of self-heating.
B. NE C0's RESOLUTION
NNECO has previously completed an investigation to determine the applica-
bility of IEN 84-68 for Millstone Unit No. 3. The results of the
investigation were documented in a letter, NES-38528, dated May 15, 1985.
In part, it stated:
Solenoid valves manufactured by Target Rock are not impacted.
Target Rock has performed a test showing that the internal tempera-
ture rise is less than the rating of the field wiring (Reference
Target Rock Test Report TRP 4207).
t Field wiring at Hillstone Unit No. 3 has been determined to be qualified
fcr forty years when applied within its temperature rating. Therefore,
l
-
i
,
"
l
-
.
-
-
- 30 e
..
, the field wiring which terminates on normally energized Target Rock
solenoids is qualified for forty years at Millstone Unit No. 3.
r
.
NNEC0 will add NES-38528 to EQ File Number 654 to complete the documenta-
tion and resolve this issue. In addition, formal documentation of aging
calculations considering self heating are also being added to the EQ file
to close this issue.
.
b i's --
_ . _ _ _ _ . . _ _ _ . - _ - _ . _ _ _ _ _ _ - - - - - - - - - - - - . _ _ - - - - - _ - - -
.
'
-
- - 31
',.
[ 11)]IMARY
T
.
In summary, from the foregoing, NNEC0 maintains that the Staff inspection
findings associated with Litton-Veam connectors and Raychem installed over
~
braided jacketing constitute violations of NRC requirements. However, these
violations have minimal safety sigificance, and accordingly, do not individu-
ally or collectively warrant escallated enforcement action.
NNEC0 maintains that all EQ equipment at Millstone Unit No. 3 is presently
qualified for the current application, with the exception of four Litton-Veam
connectors associated with two valves. NNEC0 has placed appropriate controls
on those connectors until they can be replaced. NNECO acknowledges that
certain other Litton-Veam connectors are not qualified for a forty year life,
and accordingly, NNECO will replace that equipment at the next refueling
outage. However, that equipment is presently qualified and operable.
NNEC0 notes that while its efforts to implement an effective EQ program at
Millstone Unit No. 3 have generally been successful and demonstrate dedication
to EQ excellence, there are still some areas needing improvement. NNEC0 has
learned that in EQ, as with all important safety programs, success means a
continued effort throughout the life of the plant.
!
,_- -
s -
6 ,
o-
e
'
MILLSTONE UNIT NO. 3
CONTAINMENT AREA
HIGH-RANGE RADIATION MONITORS (HRRMs)
CHRONOLOGY OF EVENTS
-
01/24/86 -
NNECO Special Report MP-8655, W. D. Romberg to
Dr. Thomas Murley--Subject: Containment Area High-Range Radia-
tion Monitors.
04/28/86 -
GA HRRM installation and calibration completed; monitors declared
operational.
10/14/86 -
NUSCO Memo GSP-86-570, J. S. Nicosia/W. J. Haynes to Zvi Rendel
(Sorrento Electronics)--Subject: Request for Resolution of
General Atomic HRRM Qualification Ambiguities. (Note: Identi-
fies cable IR value discrepancy based on Rockbestos
Report QR-6802.)
11/06/86 -
Sorrento Electronics (SE) letter to W. J. Haynes--Subject:
Justification of Environmental Qualification of GA Technologies
HRRM for MNPS Unit 3. (Response to GSP-86-570; includes cable IR
justification and overall accuracy evaluation.)
02/27/87 - SE letter, T. A. Moshenrose to C. H. Clement--Subject: Defective
-
Coaxial Cable. (Note: Initial 10CFR21 notification.)
03/04/87 -
MP3 received Sorrento letter dated February 2, 1987. (Note:
Reasonable assurance of continued qualification provided by SE
letter of November 6,1986.)
03/06/87 -
Millstone Station Controlled Routing 6611 opened to evaluate ,
'
impact on MP1, 2, and 3.
03/10/87 -
MP3 Engineering received CR 6611. Contacted Tom Moshenrose,
Sorrento Electronics for additional information. Began i
collecting drawings, calculations, quality assurance test '
reports, etc.
03/12/87 - SE letter to C. H. Clement--Subject: Update on HRRM Cable
Problem. (Includes technical note with limited cable IR informa- ,
tion; states that "SE has not found a solution.")
03/24/87 -
SE letter to C. H. Clement from T. A. Moshenrose--Subject: Heat
Transfer Methodology for HRRM Cable Acceptability Determination. {
(Includes first model for analysis of cable response.)
03/24/87 -
Opened MP3 Commitment 3 87-0031 to track HRRH cable analysis and
response. [,
i
!
l 04/06/87 -
MP3 received SE letter dated March 24, 1981. Started Calcula- !
tion 3-ENG-094.
!
'
- _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _
.1
(. *
-2-
I
e
04/09/87 - SE letter to :. H. Clement from T. A. Moshenrose--Subject:
Revised Heat 'ransfer Methodology. (Includes revised heat
transfer modei.)
04/16/87 - MP3 received SE letter dated April 9,1987. Revised
Calculation 3-ENG-094, Rev.1, to incorporate better model.
04/23/87 - Completed review and approval of MP3 Engineering
Calculation 3-ENG-094, Rev. 1--HRRM Cable Operability Determina-
tion. (Note: Assurance of cable qualification conff aed.)
05/18/87 - Letter MP-3-928, C. H. Clement to S. Scace. Closed MP3 response
to CR 6611.
05/19/87- - NUSCO QA Engineering Assurance Audit (A-30123) of EQ Program.
07/20/87
05/21/87 -
MP3 Commitment 3-87-0031 closed.
05/22/87 -
Received SE letter dated May 18, 1987, requesting copies of
calculations for Millstone units.
05/28/87 -
C. H. Clement i.etter HP 3-940 to SE forwarded Calcula-
tion 3-ENG-094, Rev. 1.
06/29/87 - NUSCO Memo GSP-87-198, B. A. Tuthill/W J. Haynes to
M. F. Samek--Subject: Request Loop Accuracy Calculation for MP3
GA HRRMs.
07/24/87 - NUSCO QA Memo 1103866, V. Papadopoli to J. R. Ferraro--Subject:
Report c1 EEQ Program Audit (A-30123). (Note: Finding 3.10
addresses MP3 HRRMs and is source of potential violation.)
9/30/87 -
NNEC0 letter (B12671) to NRC, stating that the two GA HRRMs
satisfied the provisions of Regulatory Guuide 1.97, Rev. 2 and
the requirements of 10 CFR 50.49.
10/29/87 -
NUSCO Memo GSP-87-387, B. A. Tuthill to B. S. Kaufman--Subject:
Response to EEQ Program Audit (A-30123) Findings.
01/13/88 -
NUSCO Memo GIC-88-052, D. Robinson to B. A. Tuthill--Subject:
MP3 General Atomic HRRM Total Probable Error Calculation (Calc.
l No. PA-79-236-851-GE, Rev. 1).
01/14/88 - NUSCO Memo QSD 88-5008, B. S. Kaufman to B. A. Tuthill--Subject:
Status of Engineering Assurance Audit A-30123, EEQ Program.
(Note: Accepted response to Finding 3.10.)
02/02/88 - NUSCO Memo GSP-88-035, P. M. Blanch to
l
R. A. Crandall/E 1. Holloy--Subject: HP1, 2, & 3, and CY HRRM
Uncertainty,
i
i
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ d
y 9
-3- .
I
- g ?' , *
'
,
o. j
j 02/09/88 -
hb?,CO Radiological Assessment Branch and Generation Electrical I
, Engineering review / approval of reportability evaluation for l
REF. No. 87-21, Containment High Radiation Monitors. (Note: l
This evaluation covers MP1 and 2 and CY in addition to MP3.) <
03/14/88- - NRC Inspection No. 50-423/88-04, MP3 EQ Audit.
03/18/88 .
i
f
l
i
!
\
l
. . - _ _ _ _ _ _ _ . - . .