ML20140A476

From kanterella
Jump to navigation Jump to search
Provides Addl Info to 970429 Part 21 Rept Re Potential safety-related Problem W/Asco HV 266000-007J Scram Solenoid Pilot Valves.Corrective Actions Also Listed
ML20140A476
Person / Time
Site: Monticello, Peach Bottom, Browns Ferry, Oyster Creek, Quad Cities, FitzPatrick  Constellation icon.png
Issue date: 05/27/1997
From: Rich Smith
AUTOMATIC SWITCH CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
REF-PT21-97 NUDOCS 9706040214
Download: ML20140A476 (4)


Text

..d e DEPEt DABLE ON AOL Smce 1888 FLORHAM PARK. NEW JERSEY 07932

  • NJ 1200 966-2000 / N Y 4212) 344 3765 FAX 966 2629 May 27,1997 U.S. Nuclear Regulatory Commission b Washington, DC 20555 ATTN: Document Control Desk

SUBJECT:

Potential Safety-Related Problem with ASCO HV 266000-007J Scram Solenoid Pilot Valves l

Dear Sir:

This will provide you with additional information related to my letter of April 29.1997, concerning the potential safety-related problem with ASCO HV 266000-007J scram soienoid pilot valves (SSPV's).

BACKGROUND:

During performance maintenance testing (PMT) of the SSPV's at Oyster Creek, it was discovered that there was air leakage from some of the SSPV's (Vil8 valves). The PMT was being performed after the SSPV's had their diaphragms changed to the new diaphragm material which addressed a slow scram insertion time issue. Upon further evaluation of the cause of the air leakage, it was discovered that the air leakage was from hardened core discs in the SSPV pilot heads.

I PROBLEM CAUSE: l A General Electric (GE) / Automatic Switch Company (ASCO) joint investigation identified the cause of the problem to be the use ofincorrect core disc elastomer material. Specifically, the core dise elastomer material should have been Fluorocarbon (Viton) btn was identified as a commercial grade Nitrile (BUNA-N). Material examination of 261 SSPV pilot heads returned from Oyster Creek identified that the incorrect Nitrile material was provided in 44 pilot heads while the correct Fluorocarbon material was provided in 217.

AFFECTED PLANTS:

On the basis of ASCO's investigation, we are now reasonably confident that the total suspect l population is 1000 SSPV's. GE/ASCO identified a total of six plants that received the suspect SSPV's with the following distribution:

Oyster Creek 300 Peach Bottom 10 Monticello 260 Brown's Ferry 5 Quad Cities 372 Fitzpatrick 53 POTENTIAL SAFETY IMPACT: (.

GE/ASCO identified two potential performance impacts that could result from the hardened Nitrile '

(BUNA-N) core discs: \ O

./

9706040214 970527 PDR ADOCK 05000171 ilillHIIlplirl Hr lily l11, Ulrllijplill 4 PDR llll11lllllllllllIl ll ll1l l11

p ,.

,, .t U.S. Nuclear Regulatory Commission May 27,1997 f l -,- .. i i

j. 1, Dise Fraamentation - No significant impact on Control Rod Drive (CRD) performance as a l direct result of the air leakage has been identified. However, a severely degraded disc could fragment and pieces could restrict the air flow path and delay the start of motion of the drive. ,

It could be postulated that a piece of the fragmented disc could completely block the air flow i t and prevent a scram of that drive. However, this is very unlikely because complete blockage l l of the air flow path by the brittle Nitrile (BUNA-N) fragments would be very difficult to accomplish / GE's licensing basis analyses already assumes that one control rod does not l insert. Failure of more than one CRD, due to all causes, would have to occur before a safety l concern would exist. Even in this highly unlikely event there is scram backup from the l Backup Scram Valves and the Anticipated Transient Without Scram Alternate Rod injection ~  :

Valves which will insert control rods at a slower rate. However, if the affected plants follow }

the recommendations provided by GE (summarized below), repiacement of the suspect pilot j valve assemblies (top halves of the SSPV's) should take place well before disc fragmentation  !

can occur.

l

2. Rod Driftmg - While very unlikely, one or more CRD's might exhibit rod drifting if air leakage becomes severe as a result of hardened discs On the basis of previous drifting rod  ;

insertion events at BWR's, potential rod drifting would have little impact on plant safety.

RECOMMENDED CORRECTIVE ACTION FOR AFFECTED PLANTS: l GE and ASCO conducted tests to characterize the aging profile for the commercial grade Nitrile.  !

(Bl1NA-N) discs. Chemical, physical, and accelerated thermal aging tests on the commercial  :

grade Nitrile material provided a performance capability comparison to nuclear grade Nitrile i

- (BUNA-N) that was used in predecessor ASCO supplied HV 90405 SSPV's for many years. The l base polymer of both materials is essentially the same and both materials have almost identical I levels of Butadiene and Acrylonitrile. On the basis of these tests, it was conservatively determined ,

that the incorrect core disc material would have a predicted acceptable service life of three to four  !

years.

GE provided a Justification for Continued Operation (JCO) to the affected plants which still have SSPV's from the suspect 1000 piece lot installed. It recommended that pretested pilot valve assemblies (top halves of SSPV's) be installed on all suspect valves before they reach the predicted  ;

three to four year end-of-life. The JCO also recommended augmented air leakage testing be  !

considered by the plants until the change-out can be completed. As the disc material hardens, air j leakage will substantially precede any significant SSPV performance degradation. Leakage can j only be identified for the Vil8 valves and not the VI17 valves on each Hydraulic Control Unit  ;

(HCU). The JCO advised that any leakage should be considered an indication that the suspect  ;

SSPV contains a Nitrile (BUNA-N) disc which may be approaching its end of life limit. It further  :

advised if leakage occurs consideration should be given to replacing all SSPV's in the suspect  ;

population.  !

l ASCO INVESTIGATION RESULTS:

! An investigation was conducted by ASCO to determine how and when the core assemblies were l manufactured using the incorrect commercial grade Nitrile (BUNA-N) discs. Two possible scenarios'were identified:

T l

de s U.S. Nuclear Regulatory Commission May 27,1997  ?

1, Records indicate that several orders for core assemblies containing commercial grade Nitrile (BUNA-N) discs were being manufactured in the core assembly area at ASCO's Aiken, South Carolina facility at the time the suspect lot of nuclear grade core assemblies were being manufactured. These commercial grade core assemblies would have been produced on the same equipment used to assemble the nuclear grade core assemblies, making contaraination 3 of the nuclear assemblies a possibility.

l t

2. It was found that during the time of manufacture of the core assemblies for the suspect 1000 l SSPV lot, the incorrect commercial grade BUNA-N discs were stocked in a location directly adjacent to the nuclear grade Fluorocarbon (Viton) discs at ASCO's Aiken, South Carolina

.icility. A stockroom pulling error could have occurred as a result of this adjacent location.

With either scenario, the likelihood of repeat occurrences on other nuclear lots is minimal. In the I case of the possible stockroom pulling error, the nuclear stocking area was relocated prior to ,

withdrawals for assembly of the next nuclear grade core assembly lot. Additionally, inspection of {

184 SSPV's from the next 1000 piece manufacturing lot of nuclear grade core assemblies showed j all to contain the proper Fluorocarbon (Viton) material.

l There are a number of inspection steps in the SSPV manufacturing process to ensure correct I materials are used in SSPV's. These include:

I

1. Lot / batch recording and tracking of elastomer components including the subject core disc from reccipt of the material, through the manufacture of sub-assemblies, to the final ,

manufacture of the SSPV.

2. First piece sample inspection for correct materials (by color code for the disc) at the manufacturing step where the disc is inserted into the core.
3. Sample final inspection of the core esemblies at completion of the manufacturing run.
4. 100% inspection of the core assemblies (for critical dimensions and assembly color code) prior to final manufacture of the SSPV's.

Unfortunately, none of the controls, all of which were in place at the time of manufacture of the suspect 1000 piece SSPV lot, would have detected the postulated stockroom pulling error.

ASCO CORRE('TIVE ACTION:

In order to preclude any recurrence of the above described problem and similar problems with ASCO's SSPV's, the following corrective actions have been taken:

1. All elastomer components are now 100% checked (by color code and durometer) prior to the start of sub-assembly manufacture.
2. Q.C. audits are now perfomied at completion of sub-assembly processes to ensure that all excess material is removed from the a*ea at the completion of eachjob.

l 3. An accounting process has been added as part of all nuclear elastomer stock picks.

l

4. Only stockroom supervisors and lead people are now allowed to pick components from the
nuclear stockroom.

i

n e

e U.S. Nuclear Regulatory Commission May 27,1997

5. Destructive testing sample size has been increased from a maximum of two pieces to five pieces during receiving inspection (from the vendor) prior to release of nuclear elastomer materials to stock.

It has always been ASCO's goal to maintain full compliance with all applicable NRC rules and regulations and to provide the best possible products to the nuclear industry. We believe the above actions are iri accordance with this goal and are more than adequate to address this and similar problems. Please feel free to contact me at 201-966-2100 for additicnal information.

Sincerely, AUTO TIC SWITCI COMPANY a

L-:

y Randy P. mith President l

RPS/ja CC: General Electric i GPU Nuclear - Oyster Creek i

David Skeen - U.S. NRC '

1 l

l l

l l

l l

l