- _ _. - _ _ - -. _ - - _ _ - _ _

j 11 rv su-

'ver-s August 23,1996 Memorandum To: Commissioner Dicus From:

Terence L. Chan

SUBJECT:

COURTESY VISIT BY PUBLIC SERVICE ELECTRIC AND GAS j

CO. (PSE&G) l You will be visiting with Messrs. E. James Ferland, Chairman of the Board, President and CEO, and Leon R. Eliason, Nucl. Business Unit and Chief Nuclear Officer of the l

Public Service Electric and Gas Co. cn Monday, August 26,1996, at 9:30 a.m..

PSE&G is the licensee for the Salem Nuclear Generating Station and the Hope Creek Generating Station. Salem is a two-unit Westinghouse PWR site; Hope Creek is a i

single unit General Electric BWR site.

I This will be a courtesy visit. Consequently they will likely discuss with you current activities at the plant, organizational changes, and problems and how they're being handled.

\\-

i---

A..

l Salem Salem has had a number of significant operability issues and has been shut down since mid-1995. Both plants are under Confirmatory Action Letters which means the

)

plants must satisfy certain specified conditions prior to restart. Commission action is j

not required in this case, as it is for Millstone. The latest SALP ratings for Salem, the j

i f

f E'od2ogg3961 tao f jfj u

O'NEILL96-351 PDR

)

r

'4

. )

period for which ended November 1994, was SALP 3 in Operations and Maintenance, SALP 2 in Engineering, and SALP 1 in Plant Support. Salem also does not have an enviable enforcement history, having been assessed a $600k civil penalty in October

)

1995 for numerous instances of inadequate corrective action, inadequate controls j

j related to plant modifications, and failure to comply with their Technical Specifications.

j Other items of Interest i

All four steam generators in Unit 1 are being replaced during this shutdown. The steam generators from the unfinished Seabrook Station Unit 2 are being used. Anticipated completion of the SG replacement project is January 1997, with startup of the unit in i

the second quarter of 1997.

)

Salem completed their Licensing Basis Conformance Project on August 9,1996. A number of deficiencies which required corrective action were identified. However, most were inconsistencies in design basis documentation. Only a limited number of 1

conective actions were cansidered needed for restart.

l PSE&G is considering merging with PECO Energy Co., the other major owner of Salem. Both companies own 42.59% of the Salem station. The new company would be stand-alone entity, separate from PSE&G and PECO. PECO operates the Limerick i

1&2 plants and the Peach Bottom 1&2 plants. in addition, the remaining minority owners of Salem, Atlantic Energy, Inc. and Delmarva Power and Light announce their merger on August 12,1996.

M h