Forwards Info Which Was Transmitted by Facsimile on 990409 to C Manges of Pse&G,To Facilitate Conference Call in Order to Clarify Licensees Submittal ,which Provided Addl Info Re Relief Request for First 10-year ISI for Plant
ML20205N710
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 04/09/1999
From: Richard Ennis
NRC (Affiliation Not Assigned)
To:
NRC (Affiliation Not Assigned)
References
TAC-MA1231, NUDOCS 9904190090
Download: ML20205N710 (3)


Text

t April 9,1mq FROM: Richard B. Ennis, Project Manager, Section 2 Project Directorate l /s/

Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

HOPE CREEK GENEHATING STATION, CLARIFICATION REGARDING PSE&G FIRST TEN YEAR ISI INTERVAL RELIEF REQUESTS (TAC NO. MA1231)

The attached information was transmitted by facsimile on April 9,1999, to Mr. C. Manges of Public Service Electric & Gas Company (the licensee). This information was transmitted to facilitate a conference call in order to clarify the licensees submittal dated December 15,1998, which provided additionalinformation regarding relief requests for the first 10 year Inservice Inspection (ISI) interval for the Hope Creek Generating Station. This memorandum and the attachment do not convey a formal request for information or represent an NRC staff position.

Decket No. 50-354

Attachment:

Items to Be Discussed with PSE&G Concerning its December 15,1998 Submittal, First Ten Year ISI Interval Relief Requests DISTRIBUTION Docket File PUBLIC JClifford PPatnaik OFFICE PDl-2/PM NAME REnnis DATE 3 / i /99 OFFICIAL RECORD COPY lf DOCUMENT NAME: MEMA1231.WPD [,Q j 9904190090 990409 PDR ADOCK 05000354

' 's G PDR hf )

r.

p WE t UNITED STATES

{o j s

NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-4001 April 9,1999 MEMORANDUM TO: Docket File FROM: Richard B. Ennis, Project Manager, Section 2 1 Project Directorate i Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

HOPE CREEK GENERATING STATION, CLARIFICATION REGARDING PSE&G FIRST TEN YEAR ISI INTERVAL RELIEF REQUESTS (TAC NO. MA1231)

The attached information was transmitted by facsimile on April 9,1999, to Mr. C. Manges of Public Service Electric & Gas Company (the licensee). This information was transmitted to facilitate a conference call in order to clarify the licensees submittal dated December 15,1998, which provided hdditionalinformation regarding relief requests for the first 10 year Inservice Inspection (ISI) inte tval for the Hope Creek Generating Station. This memorandum and the attachment do not convey a formal request for information or represent an NRC staff position.

Docket No. 50 354

Attachment:

Items to Be Discussed with PSE&G Conceming its December 15,1998 Submittal, First Ten Year ISI Interval Relief Requests i

i l

l

\

Items to Be Discussed With PSE&G Conceming its December 15,1998 Submittal First Ten Year ISI interval Relief Requests Relief Reauest RR-B1: Weld 6. Line 1-FD-10DBA-001 Reference - PSE&G submittal dated 12/15/98, Attachment 3, Page 19 Provide information regarding volumetric examination coverage for this weld and/or results of previous examinations performed which provide reasonable assurance of structuralintegrity.

Relief Reauest RR-B1: Welds 3 and 7. Line 1-BH-2CCA-011: Weld 1. Line 1-BH-1.50CCA-011 Reference - PSE&G submittal dated 12/15/98, Attachment 3, Pages 20 and 21

'Nhat is the approximate distance of each weld from the wall? Provide the results of any previous examination for each weld.

Relief Reauest RR-B1: Welds 12B.12C. and 12D. Line 1-BH 1.50CCA-011 Reference - PSE&G submittal dated 12/15/98, Attachment 3, Pages 21 and 22 For evaluation of structural integrity, are these welds subject to any tests, e.g., system leakage test, etc.?

Relief Reauest RR-C1: Intearal attachment (lua) welds (ltems C3.20)

Reference - PSE&G submittal dated 12/15/98, Attachment 4, Pages 2,3,4, and 5 The drawings provided do not show the obstructions. Provide information to support limited surface examination.

Relief Reauest RR-C1: Pumo Casina Welds (Items C6.10)

Reference - PSE&G submittal dated 12/15/98, Attachment 4, Pages 5,6,7, and 8 ISI Weld identification Figures B-2 and B-3 appear to show that the location, orientation, and interferences are identical for the welds associated with the core spray pumps and RHR pumps respectively. Clarify why the surf ace examination coverages are different for welds in the same location for the core spray pump versus the RHR pump welds. For example, only 18% coverage is possible on weld RHP-W2, while 73% coverage is possibly on weld CSP-W2.

)

Relief Reauest RR-D1: H002-lA and 1KJ034H004 Reference - PSE&G submittal dated 12/15/98, Attachrnent ', Page 1 The drawings do not appear to clearly show that the required inspections are impractical.

Provide information to clarify the limitations to examination.