ML20134H956

From kanterella
Jump to navigation Jump to search
Technical Specification Bases 3.9
ML20134H956
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 05/12/2020
From: Siva Lingam
NRC/NRR/DORL/LPL4
To:
Lingam S
References
Download: ML20134H956 (40)


Text

Refueling Equipment Interlocks B 3.9.1 BASES ACTIONS A.1, A.2.1, and A.2.2 (continued) control rods to be withdrawn in accordance with LCO 3.10.6 while complying with these actions. This verification that all required control rods are fully inserted is in addition to the periodic verifications required by SR 3.9.3.1 and SR 3.10.6.2. Like Required Action A.1, Required Actions A.2.1 and A.2.2 ensure that unacceptable operations are blocked (e.g., loading fuel into a cell with the control rod withdrawn.)

The alternative option (Required Actions A.2.1 and A.2.2) also allows fuel movement to continue rather than halting refueling activities to perform SR 3.9.1.1 should it become due before completion of fuel movement activities.

This option should not be used to eliminate the first performance of the SR before starting in-vessel fuel movements. The objective of the option is to provide flexibility under limited circumstances, not to disable the refueling interlocks indefinitely and is only allowed for a period not to exceed 31 days, after which time performance of the SR 3.9.1.1 would be required.

SURVEILLANCE SR 3.9.1.1 REQUIREMENTS Performance of a CHANNEL FUNCTIONAL TEST demonstrates each required refueling equipment interlock will function properly when a simulated or actual signal indicative of a required condition is injected into the logic. The CHANNEL FUNCTIONAL TEST may be performed by any series of sequential, overlapping, or total channel steps so that the entire channel is tested.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

Should this SR become due before completion of fuel movement activities, fuel movement may continue rather than halting refueling activities to perform the SR provided that Required Actions A.2.1 and A.2.2 are met. As discussed above, this option should not be used to (continued)

GRAND GULF B 3.9-4 LBDCR 18127

Refuel Position One-Rod-Out Interlock B 3.9.2 BASES (continued)

SURVEILLANCE SR 3.9.2.1 REQUIREMENTS Proper functioning of the refuel position one-rod-out interlock requires the reactor mode switch to be in refuel. During control rod withdrawal in MODE 5, improper positioning of the reactor mode switch could, in some instances, allow improper bypassing of required interlocks. Therefore, this Surveillance imposes an additional level of assurance that the refuel position one-rod-out interlock will be OPERABLE when required. By "locking" the reactor mode switch in the proper position (i.e., removing the reactor mode switch key from the console while the reactor mode switch is positioned in refuel), an additional administrative control is in place to preclude operator errors from resulting in unanalyzed operation.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.9.2.2 Performance of a CHANNEL FUNCTIONAL TEST on each channel demonstrates the associated refuel position one-rod-out interlock will function properly when a simulated or actual signal indicative of a required condition is injected into the logic. The CHANNEL FUNCTIONAL TEST may be performed by any series of sequential, overlapping, or total channel steps so that the entire channel is tested.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. To perform the required testing, the applicable condition must be entered (i.e., a control rod must be withdrawn from its full-in position). Therefore, this SR has been modified by a Note that states the CHANNEL FUNCTIONAL TEST is not required to be performed until 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after any control rod is withdrawn.

(continued)

GRAND GULF B 3.9-7 LBDCR 18127

Control Rod Position Indication B 3.9.3 BASES APPLICABLE Control rod position satisfies Criterion 3 of the NRC Policy SAFETY ANALYSES Statement.

(continued)

LCO All control rods must be fully inserted during applicable refueling conditions to minimize the probability of an inadvertent criticality during refueling.

APPLICABILITY During MODE 5, loading fuel into core cells with control rods withdrawn may result in inadvertent criticality. Therefore, the control rods must be inserted before loading fuel into a core cell. All control rods must be inserted before loading fuel to ensure that a fuel loading error does not result in loading fuel into a core cell with the control rod withdrawn.

In MODES 1, 2, 3, and 4, the reactor pressure vessel head is on, and no fuel loading activities are possible. Therefore, this Specification is not applicable in these MODES.

ACTIONS A.1 With all control rods not fully inserted during the applicable conditions, an inadvertent criticality could occur that is not analyzed in the UFSAR. All fuel loading operations must be immediately suspended. Suspension of these activities shall not preclude completion of movement of a component to a safe position.

SURVEILLANCE SR 3.9.3.1 REQUIREMENTS During refueling, to ensure that the reactor remains subcritical, all control rods must be fully inserted prior to and during fuel loading.

Periodic checks of the control rod position ensure this condition is maintained.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program (continued)

GRAND GULF B 3.9-10 LBDCR 18127

Control Rod OPERABILITY Refueling B 3.9.5 BASES SURVEILLANCE SR 3.9.5.1 and SR 3.9.5.2 (continued)

REQUIREMENTS The Surveillance Frequencies are controlled under the Surveillance Frequency Control Program.

SR 3.9.5.1 is modified by a Note that allows 7 days after withdrawal of the control rod to perform the Surveillance. This acknowledges that the control rod must first be withdrawn before performance of the Surveillance and therefore avoids potential conflicts with SR 3.0.3 and SR 3.0.4.

REFERENCES 1. 10 CFR 50, Appendix A, GDC 26.

2. UFSAR, Section 15.4.1.1.

GRAND GULF B 3.9-18 LBDCR 18127

RPV Water Level Irradiated Fuel B 3.9.6 BASES SURVEILLANCE SR 3.9.6.1 (continued)

REQUIREMENTS level limits the consequences of damaged fuel rods, which are postulated to result from a fuel handling accident in containment (Ref. 2).

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program REFERENCES 1. Appendix B to Regulatory Guide 1.183, July 2000.

2. UFSAR, Section 15.7.4.
3. NUREG-0800, Section 15.0.1.
4. NUREG-0831, Supplement 6, Section 16.4.2.
5. 10 CFR 50.67, Accident Source Term.

GRAND GULF B 3.9-21 LBDCR 18127

RPV Water Level New Fuel or Control Rods B 3.9.7 BASES SURVEILLANCE SR 3.9.7.1 (continued)

REQUIREMENTS met. Water at the required level limits the consequences of damaged fuel rods, which are postulated to result from a fuel handling accident in containment (Ref. 2).

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program REFERENCES 1. Appendix B to Regulatory Guide 1.183, July 2000.

2. UFSAR, Section 15.7.4.
3. NUREG-0800, Section 15.0.1.
4. NUREG-0831, Supplement 6, Section 16.4.2.
5. 10 CFR 50.67, Accident Source Term.

GRAND GULF B 3.9-24 LBDCR 18127

RHR High Water Level B 3.9.8 BASES APPLICABLE Although the RHR System does not meet a specific criterion SAFETY ANALYSES of the NRC Policy Statement, it was identified in the NRC (continued) Policy Statement as an important contributor to risk reduction. Therefore, the RHR System is retained as a Specification. The ADHRS is included in the Specification to provide requirements for decay heat removal capability during an outage while the RHR System is out of service.

LCO Only one RHR shutdown cooling subsystem is required to be OPERABLE in MODE 5 with irradiated fuel in the RPV and the water level 22 ft 8 inches above the RPV flange. Only one subsystem is required because the volume of water above the RPV flange provides backup decay heat removal capability.

The current requirements for decay heat removal are: In MODE 5 with no interface between vessel bulk coolant and spent fuel pool, the requirement is 155°F.

In MODE 5 with vessel bulk coolant interfacing with the spent fuel pool, the requirement is 140°F.

An OPERABLE RHR shutdown cooling subsystem consists of an RHR pump, two heat exchangers, valves, piping, instruments, and controls to ensure an OPERABLE flow path. The required RHR shutdown cooling subsystem must have a OPERABLE diesel generator capable of supplying electrical power. Management of gas voids is important to RHR Shutdown Cooling System OPERABILITY.

Additionally, each RHR shutdown cooling subsystem is considered OPERABLE if it can be manually aligned (remote or local) in the shutdown cooling mode for removal of decay heat. Operation (either continuous or intermittent) of one decay heat removal subsystem (either RHR or ADHRS) can maintain and reduce the reactor coolant temperature as required. However, to ensure adequate core flow to allow for accurate average reactor coolant temperature monitoring, nearly continuous operation is required. A Note is provided to allow a 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> exception for the operating subsystem to not be in operation every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

APPLICABILITY One RHR shutdown cooling subsystem must be OPERABLE in MODE 5, with irradiated fuel in the RPV and the water level 22 ft 8 inches above the top of the RPV flange, to provide decay heat removal. RHR System requirements in other MODES (continued)

GRAND GULF B 3.9-26 LBDCR 14044

RHR High Water Level B 3.9.8 BASES ACTIONS B.1, B.2, B.3, and B.4 (continued) ensuring secondary containment is OPERABLE, one standby gas treatment subsystem is OPERABLE, and secondary containment isolation capability (i.e.,

at least one isolation valve and associated instrumentation in each associated penetration not isolated that is assumed to be isolated to mitigate radioactivity releases are OPERABLE or other acceptable administrative controls to assure isolation capability). This may be performed as an administrative check, by examining logs or other information, to determine whether the components are out of service for maintenance or other reasons. It is not necessary to perform the Surveillances needed to demonstrate the OPERABILITY of the components. If, however, any required component is inoperable, then it must be restored to OPERABLE status. In this case, a surveillance may need to be performed to restore the component to OPERABLE status. Actions must continue until all required components are OPERABLE.

C.1 and C.2 If no decay heat removal subsystem (RHR shutdown cooling subsystem or ADHRS) is in operation, an alternate method of coolant circulation is required to be established within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. The Completion Time is modified such that 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> is applicable separately for each occurrence involving a loss of coolant circulation.

During the period when the reactor coolant is being circulated by an alternate method (other than by the required RHR shutdown cooling subsystem or ADHRS), the reactor coolant temperature must be periodically monitored to ensure proper functioning of the alternate method. The once per hour Completion Time is deemed appropriate.

SURVEILLANCE SR 3.9.8.1 REQUIREMENTS This Surveillance demonstrates that the RHR shutdown cooling subsystem or ADHRS is in operation and circulating reactor coolant. The required flow rate is determined by the flow rate necessary to provide sufficient decay heat removal capability. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

(continued)

GRAND GULF B 3.9-28 LBDCR 18127

RHR High Water Level B 3.9.8 BASES SURVEILLANCE SR 3.9.8.2 REQUIREMENTS RHR Shutdown Cooling System piping and components have the potential to develop voids and pockets of entrained gases. Preventing and managing gas intrusion and accumulation is necessary for proper operation of the required RHR shutdown cooling subsystem(s) and may also prevent water hammer, pump cavitation, and pumping of noncondensible gas into the reactor vessel.

Selection of RHR Shutdown Cooling System locations susceptible to gas accumulation is based on a review of system design information, including piping and instrumentation drawings, isometric drawings, plan and elevation drawings, and calculations. The design review is supplemented by system walk downs to validate the system high points and to confirm the location and orientation of important components that can become sources of gas or could otherwise cause gas to be trapped or difficult to remove during system maintenance or restoration. Susceptible locations depend on plant and system configuration, such as stand-by versus operating conditions.

The RHR Shutdown Cooling System is OPERABLE when it is sufficiently filled with water. Acceptance criteria are established for the volume of accumulated gas at susceptible locations. If accumulated gas is discovered that exceeds the acceptance criteria for the susceptible location (or the volume of accumulated gas at one or more susceptible locations exceeds an acceptance criteria for gas volume at the suction or discharge of a pump), the Surveillance is not met. If it is determined by subsequent evaluation that the RHR Shutdown Cooling System is not rendered inoperable by the accumulated gas (i.e., the system is sufficiently filled with water), the Surveillance may be declared met. Accumulated gas should be eliminated or brought within the acceptance criteria limits.

RHR Shutdown Cooling System locations susceptible to gas accumulation are monitored and, if gas is found, the gas volume is compared to the acceptance criteria for the location. Susceptible locations in the same system flow path which are subject to the same gas intrusion mechanisms may be verified by monitoring a representative subset of susceptible locations. Monitoring may not be practical for locations that are inaccessible due to radiological or environmental conditions, the plant configuration, or personnel safety. For these locations alternative methods (e.g., operating parameters, remote monitoring) may be used to monitor the susceptible location. Monitoring is not required for susceptible locations where the maximum (continued)

GRAND GULF B 3.9-28a LBDCR 14044

RHR High Water Level B 3.9.8 BASES SUREVEILLANCE SR 3.9.8.2 REQUIREMENTS (continued) potential accumulated gas void volume has been evaluated and determined to not challenge system OPERABILTY. The accuracy of the method used for monitoring the susceptible locations and trending of the results should be sufficient to assure system OPERABILITY during the Surveillance interval.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. The Surveillance Frequency may vary by location susceptible to gas accumulation.

REFERENCES AECM-90/0135, MAEC-90/0236, ER-GG-2007-0028 GRAND GULF B 3.9-28b LBDCR 18127

RHR Low Water Level B 3.9.9 BASES APPLICABLE Specification. The ADHRS is included in the Specification SAFETY ANALYSES to provide requirements for decay heat removal capability (continued) during an outage while the RHR System is out of service.

LCO In MODE 5 with irradiated fuel in the reactor pressure vessel (RPV) and the water level < 22 ft 8 inches above the RPV flange both RHR shutdown cooling subsystems must be OPERABLE, or the ADHRS may be substituted for one of the RHR subsystems.

The current requirements for decay heat removal are: In MODE 5 with no interface between vessel bulk coolant and spent fuel pool, the requirement is 155°F.

In MODE 5 with vessel bulk coolant interfacing with the spent fuel pool, the requirement is 140°F.

An OPERABLE RHR shutdown cooling subsystem consists of an RHR pump, two heat exchangers, valves, piping, instruments, and controls to ensure an OPERABLE flow path. An OPERABLE ADHRS consists of two pumps, two heat exchangers, valves, piping, instruments and controls to ensure an OPERABLE flow path. At least one of the required RHR shutdown cooling subsystems must have a OPERABLE diesel generator capable of supplying electrical power. Management of gas voids is important to RHR Shutdown Cooling System OPERABILITY.

Additionally, each RHR shutdown cooling subsystem is considered OPERABLE if it can be manually aligned (remote or local) in the shutdown cooling mode for removal of decay heat. Operation (either continuous or intermittent) of one decay heat removal subsystem (either RHR or ADHRS) can maintain and reduce the reactor coolant temperature as required. However, to ensure adequate core flow to allow for accurate average reactor coolant temperature monitoring, nearly continuous operation is required. A Note is provided to allow a 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> exception for the operating subsystem to not be in operation every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

APPLICABILITY Two decay heat removal subsystems are required to be OPERABLE in MODE 5, with irradiated fuel in the RPV and the water level < 22 ft 8 inches above the top of the RPV flange, to provide decay heat removal.

RHR System requirements in other MODES are covered by LCOs in Section 3.4, Reactor Coolant System (RCS); Section 3.5, (continued)

GRAND GULF B 3.9-30 LBDCR 14044

RHR Low Water Level B 3.9.9 BASES (continued)

SURVEILLANCE SR 3.9.9.1 REQUIREMENTS This Surveillance demonstrates that one RHR shutdown cooling subsystem or ADHRS is in operation and circulating reactor coolant. The required flow rate is determined by the flow rate necessary to provide sufficient decay heat removal capability. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program SR 3.9.9.2 RHR Shutdown Cooling System piping and components have the potential to develop voids and pockets of entrained gases. Preventing and managing gas intrusion and accumulation is necessary for proper operation of the RHR shutdown cooling subsystems and may also prevent water hammer, pump cavitation, and pumping of noncondensible gas into the reactor vessel.

Selection of RHR Shutdown Cooling System locations susceptible to gas accumulation is based on a review of system design information, including piping and instrumentation drawings, isometric drawings, plan and elevation drawings, and calculations. The design review is supplemented by system walk downs to validate the system high points and to confirm the location and orientation of important components that can become sources of gas or could otherwise cause gas to be trapped or difficult to remove during system maintenance or restoration. Susceptible locations depend on plant and system configuration, such as stand-by versus operating conditions.

The RHR Shutdown Cooling System is OPERABLE when it is sufficiently filled with water. Acceptance criteria are established for the volume of accumulated gas at susceptible locations. If accumulated gas is discovered that exceeds the acceptance criteria for the susceptible location (or the volume of accumulated gas at one or more susceptible locations exceeds an acceptance criteria for gas volume at the suction or discharge of a pump), the Surveillance is not met. If it is determined by subsequent evaluation that the RHR Shutdown Cooling System is not rendered inoperable by the accumulated gas (i.e., the system is sufficiently filled with water), the Surveillance may be declared met. Accumulated gas should be eliminated or brought within the acceptance criteria limits.

(continued)

GRAND GULF B 3.9-33 LBDCR 18127

RHR Low Water Level B 3.9.9 BASES SURVEILLANCE SR 3.9.9.2 (continued)

REQUIREMENTS RHR Shutdown Cooling System locations susceptible to gas accumulation are monitored and, if gas is found, the gas volume is compared to the acceptance criteria for the location. Susceptible locations in the same system flow path which are subject to the same gas intrusion mechanisms may be verified by monitoring a representative subset of susceptible locations. Monitoring may not be practical for locations that are inaccessible due to radiological or environmental conditions, the plant configuration, or personnel safety. For these locations alternative methods (e.g., operating parameters, remote monitoring) may be used to monitor the susceptible location. Monitoring is not required for susceptible locations where the maximum potential accumulated gas void volume has been evaluated and determined to not challenge system OPERABILITY.

The accuracy of the method used for monitoring the susceptible locations and trending of the results should be sufficient to assure system OPERABILITY during the Surveillance interval.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. The Surveillance Frequency may vary by location susceptible to gas accumulation.

REFERENCES AECM-90/0135, MAEC-90/0236, ER-GG-2007-0028.

GRAND GULF B 3.9-34 LBDCR 18127