MONTHYEARML20247Q7371989-07-28028 July 1989 Order Authorizing Dismantling of Facility & Disposition of Component Parts ML20211Q3021986-07-14014 July 1986 Order Authorizing Dismantling of Facility & Disposition of Components in Accordance W/Phase I of Dismantling Plan & NRC Rules & Regulations,Per 851029 Application ML20205G6071985-11-0808 November 1985 Order Terminating Proceeding Since Committee to Bridge the Gap Withdrew Petition for Leave to Intervene.No Other Petitions Remain.Served on 851112 ML20205G6551985-11-0808 November 1985 Memorandum & Order Approving Parties 851010 Stipulation to Dismantle & Dispose of All Reactor Components & Equipment Except for Biological Shield & Components Described in Stipulation.Served on 851112 ML20133Q2781985-10-30030 October 1985 Response to ASLB 851016 Memorandum & Order Re Settlement Agreement & Proposed Order on Matters in Dispute Concerning Proposed License Renewal & Dismantlement Proceedings. Paragraph 6 of Proposed Order Should Be Revised ML20133Q2941985-10-30030 October 1985 Affidavit of Dj Kasun Re Question 3 in ASLB 851016 Memorandum & Order Concerning Effect of Release of UCLA Security Plan to Public on Security of Other Nonpower Reactors W/Similar Plans.Certificate of Svc Encl ML20133J0691985-10-16016 October 1985 Memorandum & Order Requesting Parties to Respond by 851030 to Listed Questions Re 851010 Settlement Agreement & Proposed Order Terminating Proceeding.Served on 851017 ML20108A9601984-11-13013 November 1984 Answer Opposing Committee to Bridge the Gap 841024 Petition for Hearing & Leave to Intervene.Petition Fails to Satisfy Requirements & No Good Cause Exists for Deferment of Ruling on Petition.Certificate of Svc Encl ML20094A4741984-10-24024 October 1984 Petition of Committee to Bridge the Gap for Leave to Intervene & Request for Hearing Re Proposed Issuance of Orders Authorizing Disposition of Component Parts & Termination of License R-71.Certificate of Svc Encl ML20097A1271984-09-0707 September 1984 Response to ASLB 840806 Order Part B.Prompt Shipment of SNM, Removal of Metallic Core Components & Prompt Dissolution of Protective Order Required by Order,Regulations & Public Policy.Declaration of Svc Encl ML20097A0181984-09-0707 September 1984 Reply to Committee to Bridge the Gap 840801 Response Re Request to Withdraw Application.Aslb Should Approve Withdrawal of Application & Terminate Adjudicatory Proceedings.Certificate of Svc Encl ML20096G8791984-09-0707 September 1984 Response to ASLB 840806 Order Re Other Parties Responses to UCLA Motion for Withdrawal of Renewal Application. Clarification of Ambiguities in Proposals Progressing.W/Svc List ML20094C1371984-08-0101 August 1984 Response Opposing Staff Proposed Conditions for UCLA Withdrawal of License Renewal Application.Aslb Should Follow Required Practice Consistent W/Nrc Case Law.Certificate of Svc Encl ML20093H9281984-07-20020 July 1984 Reply Opposing Committee to Bridge the Gap (Cbg) 840703 Response to Univ Request to Withdraw Application.Cbg Not Established as Participant in License Termination Proceeding.Certificate of Svc Encl ML20093G1541984-07-20020 July 1984 Withdrawal of 840622 Emergency Petition for off-shipment of Reactor Fuel Prior to Arrival of Olympic Athletes.Petition Moot.Declaration of Svc Encl ML20090C7851984-07-11011 July 1984 Response Opposing Committee to Bridge the Gap 840622 Petition for Commission Order to Remove SNM Prior to Olympics.Motion Lacks Factual Basis & Does Not Conform to Procedure.Certificate of Svc Encl ML20092P2431984-07-0303 July 1984 Response Supporting Univ 840614 Request to Withdraw Application for License Renewal.Proposed ASLB Order Accepting Withdrawal Request Encl.W/Certificate of Svc ML20151J9891984-06-25025 June 1984 Memorandum Explaining Reason Underlying 840622 Telegraphic Memorandum & Order Suspending All Further Proceeding. Licensee Has Shown No Desire to Retain Fuel Longer than Necessary.Served on 840626 ML20092G2821984-06-22022 June 1984 Emergency Petition for off-shipment of SNM from Site Before Olympics,Due to Withdrawal of Renewal Application & Security Risk Associated W/Olympics.Declaration of Svc Encl ML20140C6651984-06-18018 June 1984 Order Canceling Contention Xx Evidentiary Hearings Due to Licensee 840614 Request to Withdraw License Renewal Application & to Decommission Reactor.Served on 840619 ML20197H3831984-06-14014 June 1984 Request to Withdraw License Renewal Application on Condition That Application Be Made to Decommission ML20197H4051984-06-14014 June 1984 Motion to Suspend Proceedings Pending ASLB Action on Request to Withdraw Application.Hearing on Security Contention Should Be Canceled Immediately to Avoid Unnecessary Expense.Certificate of Svc Encl ML20197G7651984-06-11011 June 1984 Motion to Compel Further Written Response of B Ramberg or for Alternative Relief & Costs.Committee to Bridge the Gap Has Not Revealed Documents Per Interrogatory Requests. W/Certificate of Svc.Related Correspondence ML20091Q6071984-06-11011 June 1984 Objection to ASLB 840606 Notice of Evidentiary Hearing Specifying That Portions of Contention Xx Evidentiary Hearing Will Be Closed to Public.Only Portions Dealing W/Protected Info Should Be Closed.Certificate of Svc Encl ML20091M8351984-06-0707 June 1984 Motion to Compel Committee to Bridge the Gap to Provide Further Written Answers to Questions 6 & 7 of Univ 840525 Interrogatories Re Security Contentions.Certificate of Svc Encl.Related Correspondence ML20091G8411984-05-30030 May 1984 Notice of T Taylor & D Hafemeister Depositions on 840604 & 05,respectively.Certificate of Svc Encl.Related Correspondence ML20091B3371984-05-25025 May 1984 Interrogatories Re Security Contention.Certificate of Svc Encl.Related Correspondence ML20090J6721984-05-0909 May 1984 Response to Applicant Request for Reversal of ASLB 840413 Finding of Matl False Statements.Requests Hearing in Which Questions Unanswered by Two UCLA Responses Can Be Thoroughly Explored.Declaration of Svc Encl ML20084H1991984-05-0404 May 1984 Notice of Disposition of Plotkin & Gt Cornwall on 840510 Re Physical Security & Request for Production of Documents. Certificate of Svc Encl.Related Correspondence ML20084F7061984-05-0101 May 1984 Estimate of Level of Threat Facing UCLA Reactor in Response to ASLB 840420 pre-hearing Conference Order.Facility Attractive Theft & Sabotage Target.Certificate of Svc Encl ML20084F1971984-05-0101 May 1984 Declaration of Wh Cormier in Response to ASLB 840413 Memorandum & Order Re Questions About Apparent Misrepresentations Made by Univ & NRC ML20084F1641984-05-0101 May 1984 Response to ASLB 840413 Order Directing Univ to Indicate Whether Any Representatives Had Reviewed Cormier 830825 Statements.No Representative of Regents Reviewed Statements Before or After Submittal ML20084F1881984-04-27027 April 1984 Declaration of Nc Ostrander Re Review of Cormier 830825 Statements.No Member of Staff Requested to Review Documents Before or After Submittal ML20084E7271984-04-27027 April 1984 Notice of Appearance in Proceeding.Certificate of Svc Encl ML20084D0711984-04-25025 April 1984 Motion for Reconsideration & Clarification of Portions of ASLB 840420 Prehearing Conference Order Re Contention Xx. Certificate of Svc Encl ML20084C4001984-04-24024 April 1984 Reply Opposing Applicant Motion for Reconsideration of ASLB 840322 Order & Further Suppl to Rebuttal.Source Term Issue Under Investigation Should Not Be Litigated in Individual License Proceeding ML20084C4151984-04-23023 April 1984 Response to Committee to Bridge the Gap (Cbg) 840406 Motions for Reconsideration of ASLB 840322 Memorandum & Order Ruling on Cbg Objections to Rebuttal Testimony.Motions Should Be Denied.Certificate of Svc Encl ML20088A0551984-04-0606 April 1984 Motion to Reconsider Portions of ASLB 840322 Memorandum & Order,Overruling Objections to Untimely Filed Rebuttal Testimony.Aslb Has Placed Interest in Complete Record Above Statutory Interests of Proceedings.W/Certificate of Svc ML20088A1611984-04-0606 April 1984 Motion for Reconsideration of Certain Portions of ASLB 840322 Order.Only Penalty for Violation of ASLB Orders Is Further Delay & Continued License Possession,Precisely What Licensee Desires.Declaration of Svc Encl ML20088A2011984-04-0606 April 1984 Response to Applicant 840330 Rept Re Reactor Shutdown, Repair & Testing Schedule.Certificate of Svc Encl ML20088A6911984-04-0606 April 1984 Petition Per Reconsideration of ASLB Order Ruling on Committee to Bridge the Gap Objections to Rebuttal Testimony.Certificate of Svc Encl ML20087D7111984-03-0909 March 1984 Response to ASLB 840224 Order Indicating Concerns on Security Plan & Security Insp Repts Re Sabotage Matters Raised by Contention Xx & Directing Univ & Staff to Respond by 840309.Certificate of Svc Encl ML20235Z3661984-03-0606 March 1984 Affidavit of MD Schuster in Response to Question Raised by Aslp in UCLA Proceeding in Aslp 840224 Order Re Physical Security Insp Repts to UCLA & Every Licensee Inspected ML20080N2431984-02-16016 February 1984 Motion Denying Committee to Bridge the Gap 740109 Motion for Reactor Curtailment.No Factual or Legal Basis Exists to Support Extreme Remedy Sought.W/Certificate of Svc ML20080B7491984-02-0101 February 1984 Response Objecting to Applicant/Nrc Proposed Witnesses & Proposed Mod to Protected Order.Witnesses Do Not Qualify as Experts.Declaration of Svc Encl ML20080B6871984-01-31031 January 1984 Response Objecting to Release of Certain Protected Info. Proposed Sanitized Portions of Security Plan Should Be Released Only to Qualified Witnesses.Certificate of Svc Encl ML20079H8501984-01-20020 January 1984 Reply Opposing Applicant 840117 Request for 24-day Extension to Respond to Committee to Bridge the Gap 840109 Motion for Curtailment.Reasonable Extension Not Opposed.Certificate of Svc Encl ML20079H4011984-01-17017 January 1984 Application for Extension of Time Until 840216 to Respond to Committee to Bridge the Gap 840109 Motion for Curtailment III (Irreparable Injury Associated W/Any Further Delay). Extension Will Not Delay Matters.W/Certificate of Svc ML20079H3751984-01-17017 January 1984 Response to Committee to Bridge the Gap Memorandum Clarifying Contention Xx,Paragraphs 1,2 & 3.Committee Should Be Made to Respond to NRC Motion Re 10CFR73.67. Certificate of Svc Encl ML20079J1881984-01-16016 January 1984 Review of UCLA Analysis of Facility Shutdown Mechanism. Postulated Power Excursion Will Not self-terminate as Assumed by Expulsion of Water Out Top of Fuel Box Region Through Surrounding Brick Walls 1989-07-28
[Table view] Category:PLEADINGS
MONTHYEARML20133Q2781985-10-30030 October 1985 Response to ASLB 851016 Memorandum & Order Re Settlement Agreement & Proposed Order on Matters in Dispute Concerning Proposed License Renewal & Dismantlement Proceedings. Paragraph 6 of Proposed Order Should Be Revised ML20097A0181984-09-0707 September 1984 Reply to Committee to Bridge the Gap 840801 Response Re Request to Withdraw Application.Aslb Should Approve Withdrawal of Application & Terminate Adjudicatory Proceedings.Certificate of Svc Encl ML20094C1371984-08-0101 August 1984 Response Opposing Staff Proposed Conditions for UCLA Withdrawal of License Renewal Application.Aslb Should Follow Required Practice Consistent W/Nrc Case Law.Certificate of Svc Encl ML20093H9281984-07-20020 July 1984 Reply Opposing Committee to Bridge the Gap (Cbg) 840703 Response to Univ Request to Withdraw Application.Cbg Not Established as Participant in License Termination Proceeding.Certificate of Svc Encl ML20090C7851984-07-11011 July 1984 Response Opposing Committee to Bridge the Gap 840622 Petition for Commission Order to Remove SNM Prior to Olympics.Motion Lacks Factual Basis & Does Not Conform to Procedure.Certificate of Svc Encl ML20092P2431984-07-0303 July 1984 Response Supporting Univ 840614 Request to Withdraw Application for License Renewal.Proposed ASLB Order Accepting Withdrawal Request Encl.W/Certificate of Svc ML20092G2821984-06-22022 June 1984 Emergency Petition for off-shipment of SNM from Site Before Olympics,Due to Withdrawal of Renewal Application & Security Risk Associated W/Olympics.Declaration of Svc Encl ML20197H4051984-06-14014 June 1984 Motion to Suspend Proceedings Pending ASLB Action on Request to Withdraw Application.Hearing on Security Contention Should Be Canceled Immediately to Avoid Unnecessary Expense.Certificate of Svc Encl ML20197G7651984-06-11011 June 1984 Motion to Compel Further Written Response of B Ramberg or for Alternative Relief & Costs.Committee to Bridge the Gap Has Not Revealed Documents Per Interrogatory Requests. W/Certificate of Svc.Related Correspondence ML20090J6721984-05-0909 May 1984 Response to Applicant Request for Reversal of ASLB 840413 Finding of Matl False Statements.Requests Hearing in Which Questions Unanswered by Two UCLA Responses Can Be Thoroughly Explored.Declaration of Svc Encl ML20087D7111984-03-0909 March 1984 Response to ASLB 840224 Order Indicating Concerns on Security Plan & Security Insp Repts Re Sabotage Matters Raised by Contention Xx & Directing Univ & Staff to Respond by 840309.Certificate of Svc Encl ML20080N2431984-02-16016 February 1984 Motion Denying Committee to Bridge the Gap 740109 Motion for Reactor Curtailment.No Factual or Legal Basis Exists to Support Extreme Remedy Sought.W/Certificate of Svc ML20080B7491984-02-0101 February 1984 Response Objecting to Applicant/Nrc Proposed Witnesses & Proposed Mod to Protected Order.Witnesses Do Not Qualify as Experts.Declaration of Svc Encl ML20080B6871984-01-31031 January 1984 Response Objecting to Release of Certain Protected Info. Proposed Sanitized Portions of Security Plan Should Be Released Only to Qualified Witnesses.Certificate of Svc Encl ML20079H8501984-01-20020 January 1984 Reply Opposing Applicant 840117 Request for 24-day Extension to Respond to Committee to Bridge the Gap 840109 Motion for Curtailment.Reasonable Extension Not Opposed.Certificate of Svc Encl ML20079H4011984-01-17017 January 1984 Application for Extension of Time Until 840216 to Respond to Committee to Bridge the Gap 840109 Motion for Curtailment III (Irreparable Injury Associated W/Any Further Delay). Extension Will Not Delay Matters.W/Certificate of Svc ML20079H3751984-01-17017 January 1984 Response to Committee to Bridge the Gap Memorandum Clarifying Contention Xx,Paragraphs 1,2 & 3.Committee Should Be Made to Respond to NRC Motion Re 10CFR73.67. Certificate of Svc Encl ML20079H9711984-01-16016 January 1984 Reply to NRC & Applicant 831230 Pleadings Re Contention Ii.Ucla Ceased Using Reactor in Fashion for Which License Granted & Therefore,Should Not Be Permitted to Receive License.Declaration of Svc Encl ML20079E4461984-01-11011 January 1984 Response to Committee to Bridge the Gap 831227 Second Motion to Curtail Activities.Motion Deficient in Form,Based on Factual Misrepresentations & Lacks Merit & Therefore Should Be Denied.Certificate of Svc Encl ML20083H3291984-01-0909 January 1984 Motion for Curtailment of Reactor Operation Pending Final Determination of Safety Concern.Irreparable Injury Associated W/Any Further Delay of Proceeding.Declaration of Svc Encl ML20083J4331983-12-30030 December 1983 Response to ASLB 831130 Memorandum & Order Requesting Further Views on Whether Use of Reactor Disposative of Contention Ii.Renewal of Class 104 License Respectfully Requested.Certificate of Svc Encl ML20083J3831983-12-30030 December 1983 Response Opposing Citizens to Bridge the Gap Motion for Curtailment of Activities.Motion Premature & Based on Misrepresentation of Factual Record.Certificate of Svc Encl ML20083J3541983-12-30030 December 1983 Response to ASLB 831130 Memorandum & Order Directing Parties to Address Question Re Whether Sale of Irradiation Svcs by UCLA to U West Constitutes Research Activities.Sale Constitutes Commercial Activity.W/Declaration Svc ML20083F5921983-12-27027 December 1983 Corrected Version of 831214 Motion for Curtailment of Activities Re Sabotage Protection Plan ML20083F5861983-12-27027 December 1983 Motion Requesting Evidentiary Hearings Be Scheduled No Later than 840215 Re Issue of Adequacy of Reactor Security So That Issue Can Be Resolved Well in Advance of 1984 Olympic Games. Declaration of Svc Encl ML20083A6201983-12-14014 December 1983 Motion for Curtailment of Activities Due to Lack of Plan for Adequate Protection Against Sabotage (Contention Xx). Facility No Longer Has Authority to Possess or Utilize SNM W/O Plan.Declaration of Svc Encl ML20082M3011983-12-0202 December 1983 Response Requesting That ASLB Overrule Committee to Bridge the Gap 831117 Objections to Rebuttal Testimony.Committee, Not Univ,Delaying Proceeding.Certificate of Svc Encl ML20082D6671983-11-16016 November 1983 Motion to Strike Proposed Rebuttal Testimony by Util & Nrc. Only Small Portion of Proposed Testimony Qualifies as Genuine,Legitimate Rebuttal.Declaration of Svc Encl ML20078B8551983-09-21021 September 1983 Answer to NRC Petition for Reconsideration of ASLB Rulings on Contention 11 Re Commercial Use of Reactor.Aslb Should Uphold Rule That Bars Commercial Use of Reactors Covered by Class 104 Licenses.Declaration of Svc Encl ML20077Q3111983-09-13013 September 1983 Consolidated Response Opposing UCLA & NRC 830829 Motion to Strike & Objections to Committee to Bridge the Gap Testimony & Exhibits.Objections Lack Merit.Certificate of Svc Encl ML20077Q3181983-09-12012 September 1983 Response Opposing NRC 830815 Motion for Reconsideration of ASLB 830511 Denial of NRC Motion for Summary Disposition of Contention Xx Re Radiological Sabotage.Pu/Be Sources Not Exempt from SNM Count.Certificate of Svc Encl ML20024F2681983-09-0606 September 1983 Exceptions to Alternate ASLB Member Ja Laurenson Recommended Decision Re Contention Ii.Reactor Primary Use Is No Longer Research & Educ.Licensee Cannot Be Entrusted W/Class 104 License.W/Declaration of Svc ML20077S6391983-09-0606 September 1983 Response Supporting NRC 830502 Petition for Reconsideration of ASLB 830422 Order Denying Licensee & NRC Motions for Summary Disposition of Contention Ii.Aslb Misinterpreted 10CFR50.22.Certificate of Svc Encl ML20077S4201983-09-0606 September 1983 Response Opposing Alternate ASLB Member 830712 Recommended Decision That Class 104 License Be Granted Upon Condition That Less than 50% of Use of Reactor Be Dedicated to Commercial Purposes.Certificate of Svc Encl ML20080D2021983-08-26026 August 1983 Motion to Strike H Pearlman Testimony Re 15 C Graphite Temp Due to Wigner Release.New Conclusion Inserted Into Evidence W/O Supporting Basis.Declaration of Svc Encl ML20080D3121983-08-25025 August 1983 Response Supporting NRC 830815 Petition for Reconsideration of ASLB 830511 Memorandum & Order.Aslb Should Reverse Ruling Denying NRC Motion for Summary Disposition of Contention Xx. Certificate of Svc Encl ML20076G8951983-08-20020 August 1983 Motion Opposing Admission of Portions of Committee to Bridge the Gap Testimony.Testimony Is Beyond Scope of Matters ASLB Directed to Be Considered or Otherwise Inadmissible.Certificate of Svc Encl.Related Correspondence ML20024C3621983-07-0606 July 1983 Reply Opposing Util 830630 Motion to Reopen Contention II Proceedings.Motion Untimely,W/O Proper Foundation & Unnecessary.Proferred Matter Irrelevant.Declaration of Svc Encl ML20072K7851983-06-30030 June 1983 Motion to Reopen Special Proceedings on Contention Ii,To Take Official Notice of Commission Licensing Records Re Ga Technologies,Inc License Class ML20024A0751983-06-0909 June 1983 Response Opposing Ucla 830602 Motion,Requesting Leave to Introduce Testimony on Seismic Matters at Safety Hearings, Deferred by ASLB in 830513 Memorandum & Order Re Contention Xvii.Declaration of Svc Encl ML20071P3151983-06-0202 June 1983 Requests for Clarification of ASLB 830513 Order Scope of Upcoming Hearing.Ucla Must Be Allowed to Present Testimony on Seismic Questions to Answer Issue of Worst Case Accident. Certificate of Svc Encl ML20023C0001983-05-0404 May 1983 Motion for Reconsideration of ASLB 830422 Memorandum & Order to Clarify Scope of Contention II Proceedings.Certificate of Svc Encl.Accounting Based on Actual Use of Reactor Demonstrates That Costs Attributed to Noncommercial Use ML20073R2241983-04-29029 April 1983 Response to Committee to Bridge the Gap (Cbg) 830414 Motion to Strike Portions of UCLA Response to Cbg Request for Expedited Ruling on Contention Xiii.Certificate of Svc Encl ML20073R1571983-04-29029 April 1983 Response to Committee to Bridge the Gap 830414 Motion Opposing Scheduling Earlier Date for Filing of Written Testimony.Ucla Wishes to Reserve Right to Modify Witness List If New Date Set for Hearing.Certificate of Svc Encl ML20073G0131983-04-15015 April 1983 Final Supplemental Response in Opposition to Applicant 830316 & NRC 830323 Responses to Issue of Quantity of SNM Currently Possessed by Applicant.No Reliance Can Be Placed on Applicant & NRC Estimates ML20073J1521983-04-14014 April 1983 Motion to Strike Portions of NRC & Util 830404 Responses to Committee to Bridge the Gap 830315 Request for Expedited Ruling on Contention Xiii.Responses Not Responsive to Motion Before ASLB & Are Motions in Incorrect Format ML20073J0721983-04-14014 April 1983 Motion for Reconsideration of Certain Hearing Scheduling Matters in ASLB 830407 Order.Deadline of 830715 to Prefile Testimony Should Be Reset to 830515.Declaration of Svc Encl ML20073G8231983-04-12012 April 1983 Reply Opposing Committee to Bridge the Gap 830404 Response to ASLB 830322 Memorandum & Order,Taking Exception to ASLB Stated Concerns on Potential Sabotage as Part of Accident Analysis.Certificate of Svc Encl ML20072T5771983-04-0101 April 1983 Response to Committee to Bridge the Gap & City of Santa Monica 830315 Filings Re Scheduling.Opposes Change to 830615 Filing Date for Testimony.Dates Should Not Be Set for Hearings on Contentions I,Ii,Vi or Xv.W/Certificate of Svc ML20072R5751983-03-30030 March 1983 Response in Opposition to Committee to Bridge the Gap 830315 Request for Partial Summary Disposition of Contention Xvii Re Site Seismicity.Univ Will Stipulate to Facts Appended to Gap Request.Certificate of Svc Encl 1985-10-30
[Table view] |
Text
,,
COMMITTEE TO BRIDGE THE GAP June 22, 0984Ein' 1637 Butler Avenue, Suite 203 W:
Los Angeles, California 90025 ,
(213) 478-0829 *g g UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION }ryi;-
- u. ..,
BEFORE THE COMMISSION ' W -
In the Matter of )
) Docket No. 50-142 THE REGENTS OF THE UNIVERSITY )
0F CALIFORNIA ) (Proposed Renewal of
) Facility License)
(UCLA Research Reactor) )
)
EMERGENCY PETITION FOR OFF-SHIPMENT OF SPECIAL NUCLEAR MATERIAL FROM UCLA REACTOR FACILITY BEFORE THE JULY OLYMPICS On June 14, 1984, the University of California withdrew its anolication for renewal of its license for its reactor facility on its Los Anaeles camnus, announcing its intention to permanently close and decommission the reactor facility.N The withdrawn application had been for a combined reactor operating license and license to possess Special Nuclear Material (SNM) associated therewith U Also on June 14, the University requested suspension of evidentiary hearings, scheduled to begin the following weekk hearings which were to assess the adequacy of security at the facility, particularly in light of the proximity of the reactor to the Olympic Village and Olympic competition sites a few hundred yards away. The reactor has been widely identified as a potential
.targetforterroristattackduringtheupcomingOlympics.S y June 14, 1984, letter from UCLA Chancellor Young to Chairman Palladino 2/ UCLA Application for License Renewal, page 5 3/ See, e.g., Newsweek of 6/27/83, New York Times of 7/30/83, Playboy of May 1983 8406250097 840622 PDR ADOCK 05000142 C pyn ,
~
4 L
2 At issue in the forthcoming security hearirgs which UCLA requested be suspended was in part, the adequacy of protection against acts of sabotage, protection against which the University had stated was not included in its security plan: " University wishes to note that its physical securicy olan, '
which is not designed to provide protection against sabotage ..." The Atomic Safety and Licensing Board ruled that some measures to protect against sabotage were required, consistent with the Columbia University case and 10 CFR 73.40(a), and that the scheduled evidentiary hearings would determine what additional protection measures were necessary at UCLA to provide adequate protection against sabotage.5_/ The Board, taking official notice of the rise in terrorist incidents and the unique dangers associated with the uncominq Olympics, i committed itself to completing the security hearing and ruling on what additional measuras might be necessary for the Olympics prior to the start of the Olympics.
In addition to requesting susoension of the security proceedinas '
due to withdrawal of the application, UCLA wrote to the NRC, indicating its intention to expeditiously remove the nuclear material at the reactor site and
.requestingNRCassistanceinexpeditingsaidremoval.b ,
On June 15, in a conference call with the Atomic Safety and Licensing .
Board Chairman and the parties, all partir:s stipulated to the suspension of the proceedings on the condition that the nuclear material on site--the additional security precautions for which were to have been resolved in the forthcoming hearings being suspended--be expeditiously removed offsite. This stipulation was memorialized in the Board's June 18 Memorandum and Order (attached):
...it was stipulated to suspend further proceedings, to ship the irradiated fuel presently on site at UCLA offsite as soon as possible, if possible prior to the Olympic games, and that all parties would use their best efforts to make the necessary arrangements and obtain the necessary government approvals to accomplish this goal .
A written stipulation to this effect was to be signed by all parties, and on that basis and with those provisos, the Board suspended the proceedings.
4/ UCLA Response in Support of Staff Motion for Reconsideration on Contention XX, Xugust 13, 1983. This statement was involved in a finding by the Board that counsel for~ Applicant had made a material false statement; Applicant continues to insist the statement is true.
5/ Orders of May 11 and October 25, 1983 F] Letter, June 14, 1984, UCLA's Wegst to NRC's Denton
L Thus, evidentiary hearings which were to determine what additional security measures might be necessary to protect the UCLA reactor facility ag:. nst acts of sabotage, particularly during the 1984 Olympics, were susoended on the condition that "all parties would use their best efforts" to assure that the reactor fuel was shipped offsite, if at all possible, prior to the raoidly approaching Olympics. However, UCLA has not complied; only a few days remain in which ,
to start the off-shipment process; urgent and immediate action oy the Comissior, is necessary to ensure the fuel is off-site before the Olympics.
In response to the June 15 stipulation by parties and the June 18 Order by the Board, the NRC's Safeguards staff has carried out its part.
It .has determined that a shipping cask is apparently available from Brookhaven, and another one possibly available from GE at Vallecitos. It passed that information on immediately to UCLA, i.elling UCLA to make the arranoements for the casks.
The Staff also determined that the various approvals (routing, etc.) could be expedited so that the SNM could be off-shipped orior to the arrival of the Olympic athletes at the UCLA Olympic Vill' age, which is to occur sometime around July 14. The Comission's Safeguards staff indicated it merely awaited formal request from UCLA to comence its part of the process, and then could move quite expeditiously.
UCLA, however, despite the Board Order and its previous stipulation, now refuses to provide the NRC Staff with such an expedited request for off-shipment prior to the Olympics, saying instead they will take six months to carry out the off-shipment. Furthermore, on June 19, Counsel for Applicant refused to sign the written stipulation, the terms of which he had previously agreed to, demanding in particular the elimination of the previously-agreed-to comitment to remove the fuel prior to the Olympics if possible.
On June 20, Counsel for Applicant refused repeatedly to return calls to CBG to resolve the impasse, although he did return calls to the Board's clerk.
CBG requested the Board set up a conference call to hear CBG motions on the matter and enforce compliance with the stipulation and the Board Order; UCLA's counsel declined to participate in such a conference call, and no such conference call was thus held.
e-v ,
On June 21, Counsel for Applicant did soeak by phone with CBG, informing CBG UCLA had no intention of shipping the fuel offsite before the Olympics and had not yet even contacted the cask owners suggested by the NRC Safeguards Staff days earlier. No good reason whatsoever was provided ,
for refusing to get the material offsite before the Olympics, nor for refusing to sign the stipulation.
in short, hearings that were to put additional security measures in place at the UCLA reactor to protect against terrorist attack during the Olymoics were suspended, at UCLA's request, on condition that UCLA would use its "best efforts" to expedite the off-shipment, and that the fuel would be offsite before the Olympics, if at all possible. UCLA, after having agreed to that, now refuses to sign the written stipulation and to comply with the Board Order, instead intending to take a far more leisurely approach and not have the fuel offsite until many months after the Olympics.
CBG has exhausted its remedies, and the time is so short and the international ramifications of an untoward incident at the Olympics so grave that emergency action by the Commission is needed, within the next few days if there is any chance to get that fuel out of risk in time. The parties have sticulated and the Board has ordered, but UCLA fails to comply. Attempts to have the Board Order enforced have proven futile, as UCLA has refused to even participate in a conference call to resolve the problem. Waiting for written motions and written responses, appecls and enforcement actions for failing to comply with sticulations and Orders would be futile given the time frame involved--if the fuel is to be off-site before the Olympic athletes arrive at UCLA Olymoic Village, the shipping arrangements must be commenced within the next few days. ,
UCLA's Technical Specifications mandate that fuel can be handled within three weeks of shutdown; the reactor has already been shutdown far longer than that due to a control blade failure. The core is opened and all the fuel therein removed in one day during routine fuel unloading practices.E The NRC Staff is committed to expediting approvals and the liae, has tentatively identified shipping casks, and awaits merely a request for schedule approval from UCLA, a request UCLA refuses to make.
y see Application, Page 111/8-4
e The only barrier preventing completion of off-shipment prior to the Olympics, with the attendant reduction in risks of terrorism at that very important international event, is UCLA's refusal to comoly with the stipulated agreement and Board Order to ship the nuclear material offsite as soon as nossible.
Because of the potential international ramifications of an untoward terrorist incident at the Olympics involving irradiated nuclear fuel at a reactor adjacent to Olympic Village, CBG respectfully petitions the Commission for an immediate order directing the JNM be removed p;ior to the arrival of the Olympic athletes at the UCLA Olympic Village. Having withdrawn its application for license renewal, current license authority to possess nuclear material lapses, existing as it did only by virtue of the facility license which exoired in 1980 and extended only under color of the timely renewal application provisions of 10 CFR Part 2.
Having withdrawn its renewal application, UCLA no longer has license authority to possess the nuclear material, nor any need for the material given closure-of its reactor. Given the unique ' circumstances surrounding the risks of terrorist action at the fast-approaching Olympics, CBG respectfully requests the Commission order immediate removal of the SNM, enforcing the Board's Order in this regard.
There is no time to go through normal procedures here--if a decision is not made and the preparations commenced by Tuesday or Wednesday of next week, it may well be too late, given the time necessary for transporting the cask to the site.
The Commission need not reach any factual or legal issue regarding orotection of a licensed research reactor against sabotage threats. UCLA is no ~lonaer.a licensed facility, its license having lapsed with the withdrawal of the renewal application and the expiration of the former license. (CBG requests the Commission immediately accept the withdrawal, contingent upon such conditions the Board may s'ee fit to attach.) The only issue is the speed with which the SNM for which UCLA has no longer either need nor license is to be off-shipped--before or after '
the Olympics. CBG submits that a serious international incident can be avoided if the Commission expeditiously assures the removal of that material in advance of the Olympics, as stipulated by the parties and directed by the Board.
~
< l
k
, CBG respectfully requests the Comrission issue such an Order (a proposed version is attached), and that, due to the fast approach of the Olymoics and the very few days left in which to initiate the off-shiorent arrangements, the Commission, if it must await the responses of the parties before acting, hear oral argument on the matter on June 25 or 26 in Washington and issue its ;
decision immediately. Any delay beyond that may make resolution of a serious international concern that is time-urgent beyond reach.
Re .ec fully su -itted, Daniel Hirsch President COMMITTEE TO BRIDGE THE GAP dated at Washington, D.C.
this 22nd day of June,1984
. ADDENDA: After completion of this Emergency Petition, CBG was informed by phone by the Board's law clerk that the UCLA licensing board had vacated its June 18th Order requiring shipment of the fuel before the Olympics if possi51e, due to UCLA's refusal to sign the stipulation agreed to on the 15th.
Thit '.MERGENCY PETITION TO THE COMMISSION can thus be considered an Emergency Appe of the Board's failure to enforce the June 18th Order and June 15th stipulation. There is no time to aopeal the matter to the Appeal Board, and the unique situation regarding the Olymoics and a licensee who suddenly withdraws an irenewal application under which SNM possession had been permitted after expiration of previous license mandate Commission immediate action because of the unique policy and international ramifications.
3;
& Attachment A Prooosed Commission Order UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION COMMISSIONERS:
Nunzio J. Palladino, Chairman Victor Gilinsky Thomas M. Roberts James K. Asselstine Frederick M. Bernthal In the Matter of )
)
THE. REGENTS OF THE UNIVERSITY ) Docket No. 50-142 0F CALIFORNIA )
)
(UCLA Research Reactor) ) (Proposed Renewal of
) Facility License)
ORDER On June 14, 1984, the University of California withdrew its apolication for renewal of its license for its research reactor facility. The withdrawal occurred one week before hearings were to begin before the Atomic Safety and Licensing Board as to adequacy of security at the facility, particularly ir. light of the July-August 1984 Olymoics to be held in part at UCLA. The University announced its intention to permanently close the reactor facility and decommission it.
UCLA's possession of Special Nuclear Material (SNM) was by virtue of its reactor license which expired in 1980. SNM possession and reactor operation have continued since that time because of UCLA's apolication for
- license renewal--pursuant to the timely renewal anplication provisions of 10 CFR Part 2--an application now withdrawn.
2 The Commission accepts the withdrawal of the application, subject to such conditions as the Atomic Safety and Licensing Board may see fit to require.
The Commission directs UCLA--and directs the NRC Staff to assist in ensuring that this directive is carried out--to remove the SNM from the UCLA site orior to the arrival of the Olympic athletes at the UCLA Olympic Village.
M m.
UNITED STATES OF AMERICA
_y ' NUCLEAR REGULATORY COMMISSION % 319 A9 48 <
ATOMIC SAFETY AND LICENSING BOARD
- 5.5. f.# . -!J Before Administrative Judges: ""
518[r.
John H Frye, III, Chairman :
Glenn 0. Bright Emeth A. Luebke SERVED JUH 191384 l
) Docket No. 50-142 OL ~ -
In the Matter of (Proposed Renewal of
) Facility License)
THE REGENTS OF THE UNIVERSITY )
0F CALIFORNIA 1 June 16, 1981 (UCLAResearchReactor) )
MEMORANDIF. AND ORDER
?. Bo=.rd and parties
.On June 14, 1984, counsel for UCLA advised the i d that UCLA had determined to withdraw its license renewal applicat on On the same date, counsel to. seek permission to decomission the reactor.
served UCLA's written request to withdraw the license t applicati motion to suspend proceedings pending action on its withdrawal req Evidentiary proceedings are scheduled to commence 25.
on C3G in Bethesda, Maryland, on June 21, and continue in Los Angele In a conference telephone call of Fr'iday, June 15, in which U ,
Sta'ff., CBG, and the Board Chairman participated, it was stipul suspend further proceedings, to ship the irradiated h fuel prese on,jite at UCLA offsite as soon as possible, if possible pri Olyiipic Games, and that all parties would use their t best effor make' the necessary arrangements and obtain the necessary gove This stipulatior. is being reduced approvals to accomplish this goal.
d to writing and will be executed by the parties and the Boar .
b
' J fa \
offik Win >ff WJ u
iy /f f
, Y In light of the short time remaining prior to the scheduled consnencement of the Contention XX evidentiary hearings, the Board is issuing its Order cancelling those hearings today in advance of receipt of the written stipulation.
It is so ORDERED.
FOR THE ATOMIC SAFETY AND ;
LICENSING BOARD A
John Ftyek III, Chainnan
.. STRATiVE JUDGE Bethesda, Maryland June 18, 1984 l
e
Declaration of Service I declare that copies of CBG Emergency Petition for Off-Shipment of Special Nuclear Material from UCLA Reactor Facility Before the July Olympics have been served on the following this 22nd day of June,1984:
by hand delivery to NRC mail system:
Chairman Palladino Commissioners Gilinsky, Roberts, Asselstine, Bernthal Secretary Chilk Docketing and Service Section Judges Frye, Bright, & Luebke Counsel for Staff Woodhead by express mail:
William H. Cormier Office of Administrative Vice Chancellor UCLA Los Angeles, CA 90024 Christine Helwick/Glenn Woods Office of General Counsel
- University Hall Berkeley, CA
( '
'l Daniel Hirsch
.