ML20090M615

From kanterella
Jump to navigation Jump to search
Cycle 2 Scram Reactivity Considerations,Analysis & Mods
ML20090M615
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 10/31/1973
From:
GENERAL ELECTRIC CO.
To:
Shared Package
ML20090M612 List:
References
NUDOCS 9105070374
Download: ML20090M615 (32)


Text

.

- Monticello - Cycle 2 -

Scram Reactivity Considerations, Analysis and Modifications October 1973 BWR PROJECTS ENGINEERING General Electric Company San Jose. California 9105070374 731010 PDR ADOCK 05000263 P PDR

i t

i

{

Contents l 1

1 INTRODUCTIO!4 2

11 SUMi%RY 2 i; 111 DISCUSSION I

A. Background 2 l l

B. Reanalysis Basis 5 C. Transients Analyzed 7 j

i D. Results of Analysis 8 i Case 1 Outage to 2680, RV's 9

] Case 2 2680 to E0C2, RV's 10 Case 3 B00 to Outage. SV's 11 '

i Case 4 Outage to E002. SV's 12 l i i 12  :

i IV SUPJMRY OF RESULTS V TECHNICAL SPECIFICATION CHANGES 13 f

l List of Figures 14 l

i i

i 1

l l

I ,

i a h

l

I M0fiTICgttl- CYCLE 2 SCRAM, RQC,T,lVITY, C0f SIDERAT10fi$. AllALYSIS_ AQMODIFICAT10lS, l

! INTRODUCTION Over the past several months, considerabic attention has ben given to the l potential effects of the previously reported changes to the f4onticello scram reactivity insertion rate as applied to abnormal operational transient analyses.

j An additional factor, the inability of the Target Rock Safety / Relief valves to mect tha original de:ign opereting specification (delay time) of 0.200 seconds l

i from attainment of setpoint pressure to valve opening has also been evaluated.

1 The effects apply to the satisfaction of the GE recommended 25 psi margin between the peak pressure resulting from the worst case single failure caused abnormal operational transient (turbine trip with failure of the bypass i valves) and the setpoint of the lowest set spring safety valve, i.e., the relief valve sizing transient.

The safety valve sizing event (main steam isolation valve closure with l indirect scram) is used to determine satisfaction of ASME pressure vessel

! code requirements and, while affected by the variables discussed here, does not result in limiting conditions. This event is, however, analyzed here for comparison and completeness.

j Efforts have been made (and reported) to determine the magnitude of these

! effects and the time (cycle 2 core exposure) at which they introduce possible operational restrictions, a

~

Because several variables are involved, many evaluations were made to obtain a solution (or solutions) that was both optimum and conservative from the analytical, operational and practical standpoints, including such factors as shutdown schedules, modification possibilities, plant availability requirements, analytical capability, license limitations and regulatory considerations.

The end result has been the development of a specific short term solution based on plant modifications and operating restrictions for the present cycle and a long term solution for future cycles; the former is reported here.

1

Il SUM'MRY Based on analyses performed at several core exposure values throughout cycle 2 and adoption of the proposed modifications to the relief and safety valves, operation for the entire cycle has been defined. For the interval up to 1640 MWD /T, full power operation was obtained; between 1640 and the early October 1973 outage, a control rod pattern limitation coupled with a power

' restriction was applied; from the outage (following the RV and SV modifications) to 2680 MWD /T, full power operation is permissible; between 2680 MWD /T and the end of cycle 2 (3635 MWD /T) reactor power must be restricted to 91%.

The sensitivity of the transient effects to changes in the analytical input parameters and analysis under varied assumptions have shown that the operating envelope described adequately ensures operation of the plant within the intended constraints and, given adequate consideration to the conservatisms involved, within desired margins.

III DISCUSSION A. Bachgraund, As reported in the past (Feb 73), development and improvement of analytical methods at Gtneral Electric revealed changes to the scram reactivity inser-tion curve applied to Monticello. Recognition of additional scram reactivity curve degradation was made early last year with subsequent development of the Monticello end of cycle (EOC) curve, designated curve "C." Because the analysis in effect at that time was based on the " Generic 72," (i.e.,

"B") curve, an evaluation was made to estimate the Cycle 2 exposure at I which the "B" curve ceased to adequately described the scram reactivity insertion rate, the effect of the assumption of "C" curve inputs at that time, and what actions might be taken to compensate for any adverse effects.

4 Attainment of "B" curve conditions was conservatively estimated to occur at 2250 MWD /T in Cycle 2. Beyond that exposure, reactor operation would be restricted, (assuming no changes to the plant) based on the E0C2 "C" curve, 1

I

A later refinentnt to the 2250 MWD /T exposure determination derived from then mere current projected plant operation confirmed the conservative nature of the original estimate, the new figure being 24001%'D/T. As actual operating history accumulated, a more precise figure was calculated in August,1973, establishing 2680 P. tid /T as the exposure at which the curve equivalent to the Generic '72 B curve was attained. At the same time, the EOC? C curve was recalculated and found to be slightly less effective than previously noted. The 2680 ff!D/T and E0C2 C2 curve (designated C2 to differentiate from the earlier C curve) are analytical benchmarks in this report.

A review of earlier generic data and analyses revealed, in early 1973, the possibility of Target Rock Safety / Relief valves being unable to satisfy the design operating specification (delay time) of 0.200 seconds from attainment of setroint pressure to valve operation. For conservatism, an outer bound delay time of 0.800 seconds was applied to plant analyses where Target Rock valves were installed.

Using this outer bound value, analyses showed that the GE recomended 25 psi nargin to the safety valves in the turbine trip without bypass transient could not be maintained to as late a time in the cycle as was previously reported.*

The margin is reduced because the transient pressure relief starts some 600 milliseconds later.

One factor that controls the magnitude of the transient is the starting reactor power; as an interim measure, analyses were performed to determine what oower level could be sustained under the new conditions and at what point in time, based on core exposure, the power restraint should be applied to compensate for the increase in the analyzed peak of the pressure transient.

The "B" curve originally defined the scram reactivity insertion curve that yielded a transient margin of > 25 psi with the RV delay time of 0.200 seconds, i Because the actual reactivity curve degrades to the B curve with exposure, the margin correspondingly degrades to s 25 psi when the B curve is reached. For exposures less than that at which the "B" curve occurs, (2680 MWD /T) the margin is > 25 psi. The exposure point and shape of the "B" curve does not change; ,

the margin at that point, however, does. i

I

  • i The initial estimations indicated the margin would rcmain above 25 psi until s 2000 MWD /T in Cycle 2. (At the time of this evaluation, the B f curve exposure was assumed to be 2400 MWD /T.)

j 1

1  !

At 2000 MWD /T the reactor power levt.) reduction would have to begin, J

holding a fixed control rod inventory, until power " coasted down" to 90%.

This would adequately compensate for the longer RV delay time. The new,

]

i lower power level could tha. be maintained up to 2400 MUD /T, the cut off point for operation under reviewed analyses based on the B curve. (Between i 2000 and 2400 MWD /T, the power level could follow a locus of points with (

the lowest power point occurring 6t 2400 MWD /T. liowever, because these intermediate noints have not been reviewed, the end point restriction is applied to the entire interval.)

i Beyond 2400 MWD /T, the more limiting "C" reactivity curve (all rods out, end-of-cycle) would have to be applied.

1 The latest evaluations based on refined input information, revised the 2000 MWD /T figure to 1640 MUD /T and the 2400 MWD /T figure to 2680 MUD /T.

i

! During the course of determining the exposure values above, analyses and I esaluations were concurrently made to define what analytical, hardware

- and Tech Spec changes could be applied to mitigate the change to the analyzed plant conditions.

Two changes were cornitted for alleviation of the overall effects: i

1) Increasing the setpoints of the safety valves to four at 1240 psig from 2 each at 1210 psig and 1220 psig, and 2) modifying the relief valves to ensure a delay time less than 0.400 seconds, a value selected on the basis of actual tests of modified valves where measured delay
times for all tests were less than 0.350 seconds. These tests, conducted by General Electric, were performed at a steam test facility utilizing sophisticated equipment and methods in support of a program to improve the response of all Target Rock valves.

4

Some of the other possible changes considered are listed below:

1. Lowering RV setpoints 10 psi
2. Reducing control rod scram times l
3. Applying an operationally oriented ratter than a design value multiplier to the scram reactivity curve and void coefficient inputs to the analysis.*
4. Operating Power restrictions Some of these factors were applied to the analyses performed in support  !

of the proposed changes.

Although these extra analyses are not completely applicable to the existing and proposed plant conditions, they have been useful in establishing the sensitivity of the transient results to variations in assumptions and modification possibilities. Additionally, more accurate relationships among the input assumptions can be derived.

The net effect of the many analyses and evaluations is to increase confidence in the analytical methods and to identify those parameters having a signi-ficant effect on transient outcomes.

B. Reanalysis Bases ,

The transient resnalytis of Monticello, Cycle 2 is based on the latest available data at three specified core exposures for which scram, void and '

Doppler reactivity characteristics are defined. The specified exposures are:

a) 1640 MWD /T, which corresponds to the projected exposure to which the plant can operate at full power without violating defined pressure margins, b) 2680 MWD /T, which is the exposure at which the scram reactivity profile is equivalent to the Generic 1972 (B) scram curve.

  • Because of a better understainding of the actual scram curve and void coefficient, the multipliers originally applied (design conservatism factors, DCF) for uncertainty could be somewhat reduced.

1 5-

c) 3635 P.WD/T which is the exposure corresponding to the planned EOC2.

The scram reactivity curves employed in the reanalysis are shown in figure 1.

The scram curves for 1640 MWD /T and EOC2 represent calculated reactivity profiles for the plant at the specified exposures with consideration of current exposure data. The scram curve at 2680 MWD /T represents a previously defined curve but is equivalent to a calculated reactivity profile at that ,

exposure, four operating conditions were considered in this analysis based on a scheduled outage during the cycle to modify the Target Rock relief valves l l and to change the safety valve setpoints. The outaae is assumed to occur

' at some time between the core exposure of 1640 MWD /T and 2680 MWD /T.

The modification of the relief valves will reduce the time delay from 800 milliseconds to 400 milliseconds. The safety valve setp a will be raised to 1240 psig. The four operating conditions conside orrespond to conditions prevailing during four cycle intervals:

1 A. 800 to 1640 MWD /T

B. 1640 MWD /T to Outage C. Outage to 2680 MWD /T l '

! D. 2680 MWD /T to EOC2 (3635 MWD /T)

The conditions assumed for these intervals are tabulated as follows:

TABLE 1 (BOC-1640) (1640-outage) (outage 2680) (2680-EOC) 4 Operating Cycle Cycle Cycle Cycle Coriditions Interval A Interval B Interval C Interval O Power 100% 90% 100% 97%/91%

SVSetPt(nominal) 1210 psig 1210 psig 1240 psig 1240 psig RVSetPt(nominal) 1070-1080 1070-1080 1070-1080 psig + 1; psig + 1% psig + 1% t 1080 psig + 1%

RV Timt Delay 800 ms ,

800 ms 400 ms 400 ms CRD 67 PL 67 PL 67 PL 67 PL ,

l Scram Curve 1640 MWD /T 2680 MWD /T 2680 MWD /T EOC2 "B" Curve "B" Curve "C2" Curve

The scram reactivity profile for Monticello is degraded from C0C to the EOC on the basis that the scram reactivity function is characterized by the amount of reactivity inserted in a specified period of time. The ,

decreasing functicn results in pressure responses to operational transients which are increasingly more severe. Consequently, the scram curves considered l for each cycle interval, except interval B, correspon' to the end of that [

period to ensure a conservative margin for the entire interval, flo scram curve is defined for the end of interval B so the next defined curve is used. .

i Analysis of a plant in the design phase using a mathematical model employing ,

design data must consider uncertainties associated with the mndel, des!gn data, and design characterist tes and features. Consequently, design conser-vatism factors (DCF) should logically be larger than the conservative factors used after the plant is operating where as-built inputs may be a pplied . Theconceptofoperatingconservatismfactors(OCF)wasapplied  :

in the Monticello reanalyses to gain a better understanding betwcen the ,

design, pre-operational analyses and the more realistic current plant condition analyses.

C. Transients Analyzed ,

The change of the scram reactivity curve from BOC to EOC and the time delay of the relief valves affects primarily the transients employed as j

the bases for sizing the relief and safety valves. The design basis for sizing the relief valves is to avoid lifting the safety valves. The l

transient which defines this basis is the most severe abnormal operational  ;

l j transient, turbine trip with the bypass valves failed. The design basis for safety valve sizing is to avoid violating the vessel pressure code l

}

limit of 110% of design vessel pressure, or 1375 psig. The event used to define this is the closure of all main steamline isolation valves (MSIV) ,

! with flux scram, assuming direct scram has failed.

l The relief valve sizing transient, turbine trip without bypass, is more limiting than the safety valve sizing event. Consequently, power reduction levels are defined on the relief valve sizing basis. Safety valve sizing t 7

. . . - - - _. - . - - _ , . _. _- - - ,_- - l

l . .o .

1 events are evaluated in all cases at full power but only for cycle interval i

B to cover from DOC to the outage and for cycle interval D to cover from the outage to EOC 2. This full power analysis over the entire cycle ensures

{

conservatism and eliminates the need for analysis at the various power plateaus in the four exposure intervals, t '

Fourteen analyses (Table 2) have been performed, eight using the design f conservatism factors and six using operating conservatism factors which l

  • establishes the sensitivity of the analyses to both design (DCF) and operating conservatism factors (OCF). Those six analyses for the exposure i perioduptotheoutage(3withDCFand3withOCF)wereassumedtohave i

RV setpoints at a nominal 1070, 1075, and 1080 psig + 1%, a conservative I application of "as set" RV's. (RV's are set 1% below specifications to ensure setting rtethods account for possible detpoint changes related to f

! environmentalconditionsandotherfactors.) For the eight analyses for l

the period following the outage, five were perfomed using DCF and three with OCF. Of these eight, two were run using RV setpoints of all at

1080 psig + 1%.

1 l

D. Results of Analyses The pertinent results of the current analysis of the Monticello plant based 4

on the latest data available, including exposure data, is tabulated in Table 2. The relief valve sizing transient for cycle interval B is eval-

^

uated at 90% power because that power level had been defined by a previous

! analysis. Cycle interval 0 is evaluated for relief valve sizing at power levels corresponding to defined pressure margins with both the operating conservatismfactors(OCF)andthedesignconservatismfactors(DCF).

l The tabulated data specifies the peak steamline pressure (PSL)forthe relief valve sizing transient of turbine trip without bypass with the margin to the lowest safety valve setpoint noted in parentheses. Peak pressure  !

at the bottom of the vessel (P y) is tabulated for the MSIY closure events with the margin to the 1375 psig code limit noted in parentheses. Appropriate

! figure numbers for the transient plots are shown in brackets [ 3

1 I

i TABLC 2 l MONilCELLO CYCLE 2 DATA I

i power TT w/o BP F151V i Cycle Conservatism level (%) . Trip Scram . Flux Scram Interval factors T.T liSIV Psl (psig)[ Fig] Pv (psig)[ Fig) i A) 00C to OCF 100 1179 (31) '73 i 1640 ftWD/T DCF 100 1193 (17) '8]

1 l B) 1640 liWD/T to OCF 90 100 1167 (43) ;9] 1266 (109) 10]

l outage DCF 90 100 1182 (28) 11] 1276 (99) :5]

l C) Outage to OCF 100 1185 ll12; j 2680l'WD/T DCF 100 1208 13 j DCF 100 1211 *

(3).

, D) 2680 M.4D/T to OCF 97 100 1213 (27 14) 1289 (86) ~15]

1 C002 (3635 IMD/T) DCF 91 100 1212 (28 l16] 1301 (74) l6]

DCF 91 1215 (25 * '4].

  • 4 RV's 01080 psig + 1'i; all others with RV's @ 1070,1075 and 1080 psig + 1%

i As shown in table 2, the application of OCF versus DCF yicids an analyzed peak pressure j difference of s15 psi; the post outage analyses reveal similar relationships including a 6% power equivalence for the OCF/DCF conditions as well as a 3 psi margin change for a consolidation of all the RV setpoints at 1080 psig + 1%.

TF analyses discussed below are those necessary for operation from the outage I to the end of cycle, after the RV and SV changes have been made. Figures 3 i through 6 are the transient plots for these analyses. Figures 7 through 16 are the transient plots for the remaining ten analyses and are provided for com-parison with those parameters not noted in this report. -

1 i

F10ure 1 shows the scram reactivity curves applied to the various analyses.

! Relief Valve Sizing (TT w/o Byp)

Case 1 - Outage to 2680 MWD /T. Figure 3.

j Assumptions: NB rated power and flow, design conservatisms (FSAR), SV's set 4 0 1240, RV's set 4 0 1080, 67 PL scram time, 2680 MWD /T reactivity curve.

RV delay time 0.400 seconds.

i A scrw signal is initiated at the same time a turbine trip occurs by position switcN s on the turbine stop valves. This transient causes a r.1pid pressure increase in the reactor pressure vessel. Primary system relief valves are provided to remove suf ficient energy from the reactor to prevent safety valves f rom lif ting. The peak pressure in the steam lir.e at the safety valve location is 1211 psig, which provides an adequate margin of 29 psi to the first safety valve set point. Thus, the adequacy of the four relief valves was confirmed for these conditions. Four relief / safety valves are required to operate to prevent this pressure transient from exceeding the safety valve set point. The rapid pressure rise due to rapid closure (0.10 sec.) of the turbine stop valve without bypass operation causes core voids to collapse and neutron flux reaches 202% of design in 0.89 seconds (figure 3) before the scram shuts down the reactor. Peak surface heat flux is no greater than 105% at 1.5 seconds (figure 3) thus adequate thermal margins are raaintained.

Case 2 - 268011WD/T to EOC2 (3635 MWD /T). Figure 4.

Assumptions: Same as Case 1 except EOC reactivity curve ("C2", 3635 MWD /T) and 91% NB rated power Sequence of events as in Case 1; pressure peaks at 1215 psig, providing a 25 psi margin, lieutron flux peaks at 257% in .92 seconds, heat flux at 104% in 1.6 seconds.

All margins satisfied.

Safety Valve Sizing (MSIV Closure)

The ASl1E Nuclear Boiler and Pressure Vessel Code requires that each vessel designed to meet Section 111 be protected from the consequence of pressure and temperdture in excess of design conditions. The ASA Code for Pressure Piping also requires overpressure protection. The set points of the safety valves comply with the ASME pressure vessel code taking into account static heads and dynamic losses.

I

i Case 3 - B0C to outage. Tigure 5.

)

Assumptions: flB rated power and flow, design conservatisms (f5AR),

SV's set 2 0 1210, 2 0 1220, RV's set in 3 groups at 1070,1075, and 1080 psig + 1%, 67 PL Scram time, 2680 MWD /T reactivity curve, RV delay 0.8 seconds, indirect (high flux) scram. , ,

)

Both a turbine trip without bypass and closure of all main steam line isolation l Analyses for these two events valves produce severe overpressure transients.

j have shown that the 3 second closure of the isolation valves is slightly more j

j severe for the final plant configuration when direct reactor scram is neglected. ,

This results because the longer steam lines, alluwing more volume for steam j

compression, more than compensates for the faster acting turbine stop valves in '

1

' the former transient, when compared with MSLIV closure. The latter event is therefore provided here as the basis for determining the adequacy of the safety valves. ,

{

Pressure increases follow this reactor isolation until limited by the opening j of the safety vslves. The peak allowabic pressure is 1375 psig (according to ASME Section Ill, equal to 110 percent of the vessel design pressure of 1250 psig). The Target Rock set points are $ 1080 psig and the spring safety valve Thus the i set points are at 1210 psig (2 valves) and 1220 psig (2 valves).

ASME code specifications that the lowest safety valve be set at or below vessel l

design pressure, and the highest safety valve be set to open at or below 105 l The four spring valves to-i percent of vessel design pressure are satisifed.

I gether have nameplate capacity greater than 35 percent of turbine design flow.

Figure 5 shows the resulting transient assuming the capacity of the 4 relief /

safety valves (47% of main steam generation rate) and the 4 safety valves (36.9% of main steam generation rate). An abrupt pressure and power rise occur as soon as the isolation becomes effective, lieutron flux reaches scram at ap-proximately 2.10 seconds initiating reactor shutdown; it peaks at a value of 592%.

The assumed safety valve capacity (Target Rock plus spring safety ca-

' pacities) keeps the peak vessel pressure 99 psi below the peak allowable ASME

' overpressure of 1375 psig. Therefore, the relief valves plus the spring safety valves provide adequate protection against excessive overpressurization of the nuclear system process barrier with a large margin. .

_ _ _ _ _ _- __ _ . ~ . - .

Case 4 - Outage to E002 (3635 MWD /T). Figure 6.

Assumptions: fiD rated power and flow, design conservatisms (FSAR),SV'sset 4 0 1240, RV's set in 3 groups at 1070, 1075, and 1080 psig + 1%. 67 PL scram time E0C reactivity curve ("C2", 3635 MWD /1),

RV delay 0.4 seconds, indirect (high flux) scram.

Sequence is as in Case 3; pressure peaks at 1301, 74 psi below AStiE limit. fleutron flux peaks at 6 31 %. All margins satisfied.

Other cases analyzed are summarized in Tables 1 and 2. Transient plots for all cases are provided in figures 3 through 16.

IV SUMtiARY OF RESULTS Figure 2 is the power profile for Monticello for Cycle 2.

For the exposure periods and power levels described, the desired margins in the RV sizing transients and SV sizing events have been maintained or exceeded with one exception; in the interval up to 1640 MWD /T the margin could, on the basis of the very conservat've design assumpti: v , be as low as 17 psi, 9 psi below the GE recommeded 25 psi, With the application of operating'conservatisms 6nd the sensitivity relationships found in the other analyses, the margin here would be maintained.

While the plant safety is in no way jeopardized by the inability to meet the recommended 25 spi margin, the desire to retain it remains. For this reason, operation will be restricted on this basis.

For that interval in which the margin was analytically inadequate, the judicial application of more realistic, yet still very conservative, assumptions shows that, in fact, the margin was not threatened.

The conclusion may therefore be drawn that Monticello operation throughout cycle has been and will continue to be safe and within the contraints desired.

V ILCHNICAL SPEClflCATIONS CHANGES l_l E M LOCAT101 ChANGL hlASON J

  • Bases Statenent for Pg. 24 last para. Change to read as follows: This change 2.2 Pg. 25 top of pg, "The n)naal operating pres- provides the sure of the reactor coolant bases for the system is approximately valve configu-1025 psig. The turbine ration used trip from power with f ailure in this of the bypass system analysis, represerts the mott severe primary system pressure increase resulting from en abnormal operational transient. The peak pressure in this transient is 1215 psig, in addition, the safety valves are sized on the basis of a closure of all Main Steam Isolation Valves (MSIV Closure) where scram is assumed to be in-direct (high flux) rather than from the MSIV position switches. In this transient, assuming rated power, the pressure at the bottom of the ussel is no greater than 1301 psig. Reactor pressure is continuously monitored in the control room during operation on a 1500 psig full-scale pressure recorder.
  • Basis Statement for Pg. 26 Para 2 Change 1283 psig to 1301 psig This change 2.4 Line 9 reflects the results of this analysis.

Basis Statement for Page 26. Para 3 Delete entire last sentence This change 2.4 last sentence climinates a contradiction with the Specification that RV's be set 41080 psig A + 1%

  • This or a similar change was proposed in a e on the!

the submittal to the AEC dated September 13, 1973. basis of ASMEl This change, were different, supersede all previous codes and need changes. Other pending changes are considered not be listed e f fe cti ve, here.

List of Fioures Figure 1 - Scram Reactivity Curves rigure 2 - Cycle 2 Operating liap igure 3 - Case 1 - OutaCe to 2680 MdD/T, RV Sizing q

)

Figure 4 - Case 2 - 2680 tiWD/T to EOC2, RV Sizing '

Figure 5 - Case 3 - BOC to outage, SV cdequacy Figure 6 - Case 4 - outage to E0C2, SV adequacy figure 7 - BOC to 1640 ItlD/T, OCF, TT w/o Byp,100%

Fi gure 8 - BOC to 1640 MWD /T, DCF,1T w/o Byp,100%

Figure 9 - 1640 MUD /T to outage, OCF, TT w/o Byp, 90%

Figure 10 - 1640 IMD/T to outage OCF, MSIV,100%

Figure 11 - 1640 tiWD/T to outage DCF, TT w/o Byp, 90% ,

Figure 12 -

Outage to 2680 ftAD/T, OCF, TT w/o Byp,100%

figure 13 - Outage to 2680 f tWD/T, DCF, TT w/o Byp,100%

Figure 14 - 2680 MWD /T to EOC2, OCF, TT w/o Byp, 97%

Figure 15 - 2680 ftWD/T to EOC2, OCF, MSIV, 100%

Figure 16 - 2680 MWD /T to EOC2, DCF, TT w/o Byp, 91%

s .

iy

_[. . . . . . - _ L. ._ J _. . ..

4.

..}.__..L._ -.:. '

I i .

i

_.L. __......_i _. a _. - . 1._. 1 s .l._.-_

._.a.

._ . . - ._. _J_ -- I ~~~ - - -- --- - ~~ --- -- '

.i .. +j .

l ,i _.. .i.._ !_ . .l _ . __ r.. .,I__. ' .c...

I i

_. L .._ .. . .. -. .. ... ,

, 4..

.l. .q. ..{. 4- j. e. i .; _

l

. l _. . _i_.

1

-f

_.4_. . ... ._. _ _ _ . . _ .

_q . ..

.7. . .i. .. l. . ____[ {_ _

._ .] _. .j. .i 1 . ._1.. . _. . .

_ L. .._ q__._.- ... .. . _

.. 3 . . . _. , . . .]. J.. .4_.

. ._L. _j _.. _ J... .

. . . .j..

j. - _ . . . _

..q.- $

_ .l .. J

_.j _ m.,i.

.I.._i.

_J _ . . _ . _ . _ . _ .!.. ._! _ ___1_ . . . . - J._ .. J._ .j... _ . . _ _ _ _ ..

l ,

.a. __'  ! j I t q.

  1. p i _j ,-

1i_

l-l _ _. _ -

i  !

_4 i ,

l t

i

!,  !,i , i, I l

>/, a# i '/ l

.i. 1_ . 4 s_ .+

[f ,.e<)li

~ _._.-. . . . _ . . , . - _ . - - .- _ - . . _ - - . .

-.t_.

l G..y. *.

l l l j \

l.

/ / .[._' _ _ _ .

1. '

t i l l  : I j t

-[ _ . g ...

{ . ! _. ... _. .

I

. g _. _ .i .

j. Y i/_. 7 i

.. ] __ . _ 7, . .

..j

= i ,

n .

i l

j6 l . l- l T+

'.' 1. .

, I I

f< , n L_ L--J --

'.-g!.f.),.2_I.__'. i6 I

._c_. .

_. . . . __ _ . L- _ .

J /_..-. _ __

}.- ,

__ ' } __. ._

i l

j. . .. , __ l_. ,

.I je e I

i- t ./__.l_._. l

._a _ _ _ _ . . , -

_..p _. _ _j_ _.

_.u _l

__.[. . p _.._L. ..

/A. ._ _ _ _ _ . . ...q .p _ ._ ..__ y,

.c, .

_ .a_ ._., g. 7,. .f. _. _ . . _ _ _ . . . _ . o-q ._ .q _4 __ . .. /. . _4_ ' .

7 _ , .

.q._ _L_,..

J-

._,. 34. ,,. ._.p/ ,

s ;

_ _ p_ .

i.

_4_

.L.. ', 4p g/., , . . . _ _/. . .

y ..

j. .~1_ .,

t __l . . g

_. ._ _ ___ __2. ..f __

/q[ .

j

. .<1 . .J , y

.j:

17 ,q / ,e. . /, .g

.- tu

1___ i. ._i .
i. i

,u jr ..jej Ly

. >s__/. ,p.<,' : i i

i. j.

r ,.y y, j

.1 -j;. pli w _ , cg y .

f. q P- . g ,g y . .. j) ..p !_ 'F.../3_ . c .__ _ j-. _

/ -

,. i -

i_ . . . . ..

.l ..

~~ '

.. l (,

f

._ .a_. .. .- ~ d. . .

c -

-- . / l L_ _

. _.,I . . . . . . .-l . i

@ar .j m

. f.,p/,' ..y.

L

[-[ -,

f, N ,

Y. .n

  • %N._ /t_

-. .l .. j .

p-

,; . j 7 ,.. .

.i

~

/ it.. _ _.' [ -- N.CC,.L .d.Q,- +

i- '9 i

i_ p%%l y- l/- \.I-

[ 1

.a. .-._ ._

l

- l -y {- --

-I~

'. l _t.

l *

.v. .] 7

.J

/. /._ '

,.t

. . t. i ._. - QC I'J - 4: i

_p 4 , r o _ _ _ w _.;_

_w, p!

i _ .u.

_ /.

' . _.L __ ! .

~ /j_ _f ja .p?

_p

... .2 _

_q ._.-

_. q _ ._.

_ . J ._

.1 _t g__

- i

. _ j___..

/ /_

. . . ~ _ __9 _

_ . _ s s . J .<_..__

_t ..

J _. ._1_

.__E._ -..

_ _ . ) . .- ._.s..

_f $. ._. ' . . _.

.l . .

]A[/

E b, ~f - , ,  ! .. - -_

l

_ ._ .[_ . _! ._ __ ,j._:__..s_ J. . ..

- - I ._

.l r*

l .

~.c 3,- _ ..

.,t .,

f. . , . ' _ .L c

4 - -

. d.. _ . _ . L._. ;_. .] .2

.j

_ _ . . _ . _ . . .__. . . _ , t a, 2 '

, s

- ' . ., s . . v

. . _.i _. _i _._. .-

... ._ '. n-

. i_ ,

, k~ t' I. j- l j ' . i - *~

'. N,

"! j' Figure 1 - Scram Reactivity -

L -

.

  • i. h

- .a , . nM c-x w. ,

g I I.L i a 1. o. 4 -

~

e

'Y4Q'. C 2680-) .

Cycle Interval A 9 Cycle Interval C r 3635) .!

i

- 100% .;

100 ,

I Fixed Rod Inventory Fixed Rod Inventory Coast Down (Approrbnate) te) - ] i

{ Coast Down - (Approxima

  • 95

.~ r/cle Interval D All-Rods-Out Coast I Outa9 91% - " ~ ' -

90% '%s y N

Cycle Interval B A i u -

85 i

e i

o i

j E

, o 0 ,

l . .

=  :

MONTICELLO

  • CYCLE 2 OPERATING l'AP 3

j  :

Figure 2

. . . 1._ : .. [

f .

, i i i 1000 2000 3000 4000 r 10/73 CORE AVERAGE EXPOSURE (t"dD/T)

An.-f, -.4 4l.a.a 4 m, te u _ -oc_=5_u____--a__r-+_, m&- 4-a..__aa.ha..e_.# -

.,.m. _ _ . _ . - ~4._.. .-m,Mwa

s. 4 - m _e =4s.**.b m ae & A_aa__m.k_ -_ ..*AJ 4>_._m ,_..-w, m ,

Tt I E ,

i 12 <.

3 f t o

4 g ea kb g g -a f .

g -

i E. N

(

. G

! 'Y o h

-- . a a

-~.. ,n ,

.l g = e j W 5 a '

d W , 'S

" N

__. ,Y  ;- g ,

. g

\  !

/ _

i .

m h

H

k.  :

- d s . . . .:

i

"[ .

samoa g 4

-i r ,

=

., i

. . I 3

hh , - .

\a a ng N*g

" 3l, h f f I st ll ~.. .

-~.. .

a

,a $rq, s :s ,

D i w w J J t

Sl O Y

i in

.A .A i

- - g

/C./ r I

J i  %  : (

i N ,

% . . . . . ."j

,j (031UU 30 IN3393dl

, t o

i ,

l t

1 visstl

, i sw uw*ws ewsatt>:xes:t i-5:1 i l

l , (. 'eratctngps ritm Tee 3T iSE F5'l

3 IhY SL8 FACE +(ptT ruct = c'J4!1e
s vaf7PvS.>*s s erwter l
  • rtmerts a E D MX A.T c!:: NC in ,

rts tu

!? w:w s um IE a (C*[F fLW -

f

<. 2 m .,

' in

/

Km i

- > -- ~

  • l.

o ta  %

w c-.

/ [

c 1 c y .

i L sf b

' 5 y s so,  !

! - si i[

ha e  :

1 n i s N

S f i

S

w 1 b -1 4

~t

      • =*d

"- se f-

2. A s. e. '!
b.  !

i t

S.....r.... 2. u. s. ' e. s TIME (SEC1 ,L TIME (SEC) 5

! 1 ogi sagt;vid.T ,

2 sage argtryg .i 1

'

  • Ifv! Lit f-1KIRT 3 cystse seat:DITT ,

2 SFYTT vatvE d (D t =:;g neiti;vgry 4

S fe R E*MD tf 11'OC51 l j s CSE IttET 51$ 8 Z s k *;

3 PELIEF 48LVE plt > LU I

t

~

5 4

  1. """~ s

.k i

A S.

  • j tal. \

E l

$ f i

% Na d E

- c2 i s 4. ,

i

, so. . ,/ j - . .

e

/ -

1  :

. O

,s  : , j

,= ,2

s. e.  ;

2 . sam .e_ _ty...r.... 2 *.

a ..B.i. ..

a. s. CCRE FLOW (~il i
b. 2. s.

TIME ISEC)

Figure 4 - Case 2 - 2680 FiWD/T to EOC2, RV Sizing ,

t e

! MONT RLD170 H/0 PRT ^- - ,*

i TT H/0 BP.DCF.67R-8/73-C2.tiRV-47% CIP.O.14 DLY.917. PWR W/2 PUMP TRIP f

4 4 A el g 1 2 ,

v

? .' -

I I y

[ T Tf

  • 1

.__ 1 g g as  ;!

g g$b

,5 $

.y


, ba - !

.Eh If s

[h x ..

sJ sm

-~,.

n!

.. a/ ,_

9Ee

-~-. . ,g a i g g .

~

/ d w w E I xV'g3 E

] o

/ . y B

e

, g

~-- a J a t

[  !

I $

)[:.

1 I

$ $ $ E E I I O I I h

suulloa' g:

rg -

g H 39h 3 hh g - l, 1jj!

6 - -

m_r

, !B' s g 3 - S pg m e a

Lp)

,0

,0

[ [ m EE P (  ?

/ i '

y /

} -

- s 1 ,

'd , .a  ; y/ a ,

,i f- i 7(#~ .

lan a..

ane i , sina t .,

(0316W 30 IN33W3cl)

! I2 i at m ak an

5. o< c ,.:st ,-sn 5 c o nw I 2 - r st en w
3 TMIT *M5 9 SF Mil i

3 4 SM rCI **F~ Rt3 '!, 4 C,'*E IG SA!

y c;,e a 19'M SF 4FF D ifB FLS4 2so.l '

g

= vtewA3 i-2"

' %l 3f!T 5"! *= R == tti l

i '

N y N

w A L: ~

85"-

S "- n. '

E ' s N

e 2

a m

! r \ ,f ~

so.t . V fy s%- -

'C-M  : )'

- , A . . .

E i

M

- 22 _se

]

. . . . . . a .2.. .. s. ..

m2 e.

. ..i.... s. .. TIME (SEC)

,d. 2. ..

TIME ISEC) wr remd a m Mmu

tmtird-se sum 2 wtn wr as, m E E W WI.'"

! EA'iOV rT#i'E75' 5-25 >sw m:m m

,,E ,/

z e JeY , '

, s [-- W' ~N N g l tn l .

g

! d a

' ' 5 0 _s.

so. .

[ s -

1 w N _2 M  :

4 t Xa >

s tz -

~f- s. e.

~<

~+ -nh. 2.

c ~..=.* 2.

a. s. CCRE FLCW t%)

t.

TIME (SEC)

Figum 6 - Case 4 - Outage to EOC2, SV Adequacy MONT FLD158 W/C PRT W/2 PirP TRIP _ _, ,

M51V FSCBRM.CCF 67A-8 n3C2M. 36.9%SV.

5 521 - - - - _ _

  • * ,a g 'O e S

O

=- h

' ll - l'

. i

$$v e

Xp '

4=>

[r s

b_$56! W9 $

a_

-~~

_ as g I <

S

  • x e f w a -

a

~

d' #

O h.

E

a.  ;:

al g E

- a w e

o

\< -

f .s N. i \ 4 l

w ,,,i,...-

h 0 'S k Q N h SWUT100  ;

9l

. i{

-n@!i

,o

/

O4 3 ap 4 le ;di

, \

  • y

/ '

e eu l 9 tit

'. ) .

a 1

}

'E e u

$ f $ )

r s

! = <

u

\

f m

W ( f )l

)/

i i

_.- . n A-9,, . .-

N N h N h h '

(0310U 30 IN3'JU3dl

e e

msah l2t em nuxunta I Trw s23 s-mc.s ews n: west: ;,5

    • = rtet ftswi;w MS a,9 m t 3 ave SM5EE @f Flux g c;q 7,(Et spg ;g wtp FIEMTm RN N > ey ovE pyffrg4 gz3 gaiD" 3 k1SSEL SiE%T@e S 13914 stem PLSs tv 3

[ ~

e w ,, '

g gm-ym ,,,r -

r- -

'. s y '

/

  • i 5 s s
  • ,/./'

al I i 5g \3 5 N _s%

g 6 , j y _'- E 4

I na S ." J s a a

, 1 - .. . .. .... i m

. . ....... _,,h. 2. m. s. a.

,b. 2. s. s. e.

TIME (SEC)

TIME (SEC) l wt gecrnt 2 scw vwT v I2 swen ne noe tut tevtteo-edsre-scar s ar e werr.:n I s = a swo tr4urets e vc*c Mst.fiv:*T 4 CSE ICT FLSs t 2 I E IE 's FELIS V8tvE 6Od tb a L g

S _1

g /w a, 4, h

E w a o

s N o \

s s u=

y _3,t T

~

7  :

/

i

- , - s .

-ms

.so "....t.... 2.

, .x.e. l,l 3 2 1 m -a s. s. e.

n s. a. h.

b. 2. s. CORE FLOW 17.1 TIME :SEC; Figure 8 - 80C to 1640 IGD /T, DCF, TT w/o Byp,100%

g MCNT RLD L'8 W/0 PRT W/2 PleP TRIP ULM6Ug6 y 7BM . __ - . _ _ _ - - _ _ _ _ _ _ _ _ -

- . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , _ _ . . . . _ _ . . . . _ . _ _ _ _ _ _ . - - _ . - m_.m.. . . . . .m.___._.._-..mm._ _

1

+

e i k

1 *.TTEL M m;g (P3;)

I W N FLUM l

2 $!n LIT PM3 PTT 1*S!! ,,

2 PECM FUEL CDPTM Tfg 3 RFBP4E PTS 5t:3E (PSI.  ;

3 AVE Stfv ACE **RT FLUX 4 CFE 3ae.ET SLE 19M93 4 FNTEM FLt> > CM AT CJ F'WC CJ  !

IE ,

. WSSFL STEiM fLim 8 TJ6 M S'E3P FLSetis

[

1

.f

  1. x g  ! _.

g gg - '

cr E j V

~

b ' ' '

8, s N L ,s / -

n x.

y ( lg s s -

t 1 1 -- a 4 .g " . . .l....
2. 6. 4.

m4 l i

g"....I.... 6. 9. L L "

D. 2. L TIME ISEC)

TIME ISEC)

?

1 gT MactivM 2 *Jr>4W 48CTIV {

l23 m$FEf? witVE dSe itst tfvatMVP-sFIRT R YviFD Lf4LtitT53 3 IXF'tf9 48CT ITT 4 veI3 M M.T!vi 4 CST PLET FL3+ t E I IT' s MLIET vfLvE l'L36 113 .

t i t n o.

f, ,

6-zm-I N i d i N - o 5 5 '" -s.

so. _ ,

- 7  :

- 2 Y f

....i....

-,=a s.

2 2 m_.s _w 4. 6. 8. ,

....e.. . 2

6. e. L 2,

,h. 2. m. CORE FLOW (%)

TIME ISEC) i Figure 9 - 1640 PWD/T to Outage, OCF, TT w/o Byp, 90%

g .

MONT RLDJ* J W/0 PRT W/2 PU$1P TRIP - ,

TT W/O BP. OCF 67R-2A28.1877.RV  :. -

L*E _ _ . _ _ . . _ _ . . _ . . _ _ _ _ . . _ _ _ _ . - _ . . . . _ . . _ . . _ _

_ _ _ . - - - - - - _ . _ . . - . . . . . . . - . . . .-..-nn....~a.w.-._-..~.x_ _ . ... . _ .. _ .x - ..x _~. .. --

0 i

.  ! vt3Tl NES # tPS!?

1

  • ELM fu!X 2 $7= L t PsES 1 t* Sit .

2 etsu TEw 3 n: TIT MS MI'1 1P513 '

3 frvt anysatt ,ePT FList 4 CSf_ IstIT SA315TuAS)

' E FH384TER FW > @WI5 TT CD TU i

> VE$SEL $9 FLSI 6 T'Je:t s*fje FLDs tu ,

- . / r is 25 Ww .

8 25 m w E

NN

' l 2

=a w

r w N  %

. V N .__ '" .

1

b g [ a e a s b -

Q, ....t.... wg 1 I - = el a.

s. c.

k"....t.....2. 4.

TIME (SEC1

8. 8, 2,

TIME ISEC1 I *ET fEnCT!vfN 1 LEvtLt!O SEP-9t1MT 2 m se x ?!v 2 til RtK FLSs 2 5- j, 15 = euzu vu ruw tu i

f A o-

. s. ~ C -

t

" i te.

a, -!

g d

o \

5 s d _s. ,

\

E s, s .

T

\\Q N  %. - -

~

WA 1m4 . -10 ==t==*= e.

.. f1 / s. s. 6. 2. s. s.

og . . . a. s . 2" TIME (SEC1 CORE FLOW 1Z1 ,

Figure 10 - 1640 FWD /T to Outage, OCF, M5IV,100".  !

MGNT RLOl6tl W/0 PRT 36,9%SV, W/2 PUMP TRIP .

MSIV FSCB9M.CCF 679-2/728 . -

w "W ' - . _ _- - .. _ _ - . - __ .__ ___ _

- -a

i e  !

r i 1 vtssEL egs abr tP5f t

! st?fnes 7tt.tr l 2 Stw Lig 843 prW tr$13 L j

2 Ptset FLFL WFM TTir 3 Ti.selet PT5 M tests

< 3 cvt arvstl seaf n.ux 4 c q tatti ts'ttise

  1. FtImmffm Fli> > Cpf e,E r3;) N tu a 435EL STUim Fb s iuet e s? tea rt> tv s.

- \ -

g a

~ Isa.

/

7 2

~

. 1a0.

!f U NN - s s ,

4'

=

w so.

O s N~xt. _N e so.

R

/

p-i w s a a b

k -

j N A , i -- m-E

_,o..........

2. m

,s..... ....2.

s. n.

TIME (SEC3 l;

' TIME (SEC1 ,

i 1 et't 8EETTvtt [

1 Lfvftt WP-Sttstf 2 stgee 4DCTiv t 2 5ftYTY v4VE et s tu 3IRIP"tf* E80Y ITY ;i 3 N R TWjED tr4LtI4M33 # vcfD SE8t.11t!

t 4 CTE fitfi FL$ ( I I ,f N > #ELIET vfLVE FLD (U 1

4 a ,

e r

  • s _

3

a. -

3 100.

J

N s ' -

s m.

s

g. y 1

so.

~

f W ~

[

.\

_ s -

- / ="= 18 I

- 2 z

...r.. y 2 2 enims . 18 0.

8

2. m. s. a. .l e.

,b. 2. a. s. CORE FLOW t~il  ;

I TIME (SEC) l Fiaure 11 - 1640 t@D/T to Outage, DCF, TT w/o Byp, 90%

~

Ist i i MONT RLCfM W/G PRT W/2 PUMP TRIP l IT W/D BP, DCF 67R-2n28. t&74RY

.. _~ (,  ;

.o

. ' 't

L l

vt

.I J

t eft 5 s tiv s.riews rws 3TW:4 P'E5 4:2 t*S!

c:wah esit iesn 2 eu m'orstux etn arm ice 3R4'RM8U WAT FLUX 4 CST tat.fi SA ts*#Jts l E pfER FLOE > tef avt n;a y wr sta 1

gg > WESSEL STEM 8554 si n:* stm ustu

)

s i

N a ,. .. -

s .

    • / V p' -w N

/ -

g iP 'f cr 7 N/

N - s 5 A 5 so. , . e - s

" ~

l so.  ;

g q r a g w 't e 1 0 _

-f

...l.... m .

1 --e. . 4 _so

2. o a. e. '

....r.... e. b.

  • b. 2. a. s. tit'E (SEC1  ;

TIME (SECl .

4 i (T gett*v

-TP-StI8tf 2 scgin mE# city I LEVElt! S Or*LfM M8CT ITT *i+

2 WETY vsqlvt F.tne (23 3isRYMY3tDFitteOfSi 4 WOID MIE1!Vitf 4 CNE ISLET FLtdt15 .f IE 4 MLIU V8%.VE FLS6 LI) l 1

l ,i a

JL --

e 3 _

L s, 1%

K 1

N N

=

$ i

' Nt_ s d o <

s 4 i j

l

/_

V W

! ....l....

m a

t.

.. ..d... 2.

2 s.

2

s. s.

2 -. 4 _io

n. 2. s.

CORE FLOW (%)

s. .

TIME (SEC) >

Figure 12 - Outage to 2680 mfd /T, ^CF, TT w/o Byp,100%

15 0 MONT RLDL*J W/0 PRT W/2 PUMP TRIP ,

TT W/0 BP. OCF 67R-2/728, t&T4RV .

--__m -_ _ _ -_-___ .

(?Iffi?,i'#  ![' ,[ !If  ! fI, . , ;j .It f i i l!! ;l! lr ;I  ;; ii il.

4 - 1

. 0 0 ,

1 p -

y S ,

o d s /

?M:9

'5 P

tW 3

ts1 S

IPA tt s t

?".

W1 wv,.

9 js Ia Wy ' .

Y E

T T

I ;

mT 8 T

F w

2

8 Tv C Rs t8N ae Ticts D rSS :c s gts1 1

3 t MuTt T S

iENE T8 tE 8 ,

u PE i

MJ9M a8 T

11d;E 4

  • 4 ciN eE W t O /

ieE 5 D P w7 OiPITC W(nMC ti vs Ci t 1 1234 CW N i

I23L >f L1 u n 0 l C W 8 E O 6 S L 2 a

I F P

-t o I E't t R m T 4

I T ~ 't e g P:

a t L

y,-

1 t P u

O 2

- /

W 8 b .L 3

1

'L .

e

/ /

I t

i r

u g

L L

'"D C

' o 1

g 5 ~\

F n.

5 S iE M 1 8 ;8 V

m.

R :

. Z _

74 t

8

- f T 3 2

7 R 3 m

/-

J

/

yIC lf 3 )

1 T2 wN fL I & Pi.(PZ Et

(

8 1 R-P- A TF e 3L SL 2 06

- i 8

kS.E w F g

/

f(E"LS fD 3 - MELFP D*L E HF tet g

3 eLi i 6 V LDt Lf V C L

FtRME W 2Fh s 05EE 1vM%

f V

gc. D e

SF rMt t T lTT1 tT 7 t gtP i sac EI E i 4

D TF9y L DB Tr Jedf Cf sPAF I234 n Y W f

AJ F

LSsC I234 3 e

8E

%s 1 oj L

R0/

TW C

4

" C E

_ E S

S I

CT IT

(

E N O E

I T

M s

1 o

D T

8 5

.\ '2 N ,

.2

~

n

\

,, gt

-

  • g I ,

k fl L L h -

I S O E I

E t i

E JNwb t

A

' . i, 1I!;1* ,l I l i  ;'J j '. I J'  !  ;; l!' i:f1 Ii.. af!'

_ =

1 d e W o,

o

=

k>

1 l i

EfBB *

l[ E g

l

, y, h5 $l a g; -

e e

ah e

. hini-

_, ,n e

) e e

,g l e -

~i; W 1 B -

~

d q e

$ E ,

- { ii! - i i u J J a

    • N e*

/

/)

y  :

(

e

?

% i ,

i

...it

.f I

j . . , , ,g y g g g d d

g

^ SWUT100 k.

a 4

i gg I $al:: e  !" -$ i

" J , !B 3

) g!i g,i

[ sgl 4

! I!

E sl /

ni i Ls q- oe d d a g:

m e

4 w w 4 J J

\

e s e

88 1

Q

/

- [\/(,, .

f .

_.m . rs-M . - ,, .,,.

1031BW JO IN3303dl

(

______-_._..._.__..._-.._.__-..._-__._m. ....._..__m._.___,m _____m___.m m._..m_-- ,m..m. _ i . _ _ . _ . .

i E

4 I

f ,

i' i

. t l 1 visul sets ah t911 I

3 ,cfice nty l 2 5:= L!T PT3 P!1E tP5:3 3 M:wE PT.5 9!*iE (F1?S 3 2 PDIK FtfL ENT1I TDP 4 C3% !(IT S.319?ul81 3 ave SLwncE say;T Rux I 4 fTED*TER Flot l3 COT A.T r$Tf4C (II '

?, l Ytre!T SD FLSa tif I > VESSEL STE94 FLSe i

  • f i /

1 t u s ,,,. ._ -- -

s w 2 % NW s

T 1 N w

  • ta.

U a l f ,

s N e

( \

f de 15 i 7

\ E s B a E .

4 LJ - 1

- - _ _ .. a t

.....u.... L s. e.

m, i f

h. 2.
o. ....u.... 2. 4. 6. e. TIME (SEC1 D.

TIME ISEC) '

1 eET fvjectivfTI

  • EP-SINT 2 SJ4 ppt %KT!v
  • 1 LEVEtt 3 N M8CT ITT 2 STETY v&WE (2) 1!63  % WO!D M81CTIV! . l 3 w R *iD5E.3 E CfFC INLf,T FL iI9 L +

t_

IE 3 FELIEF vf TLfL54 (I) f '

l t /

4 C.

E Y f 3 -

u [

100.

\ 1..

sa-i s y

i: -5.

d 50.  :

!  : /  !

_ s f.

} 1 m -

i NNe' a oe M i __.

1 i

/ ,

, _m e.

1- .,,b.

2. s. s. e. t 1

.b........... 2. s.

TIME ISEC)

a. CORE Fl.CW 121 i

Figure 15 - 2680 MID/T to EOC2, OCF, MSIV, 100".

MCNT RLD156 W/0 PRT W/2 PUMP TRIP

~

MSIV FSCBRM.CCF 67R-8 n3C2M. 36.9%SV. - - - .

4- 7- -t s w= ->  ? ~

_ _ _ _ . _ _ . - _ _ . _ _ _ _ _ _ _ _ _ . . . . _ _ . . . _ . _ _ . . _ _ ~ . _ . - _ . _ . _ _ _ _ . _ . _ . . _ . _ . _ _ _ _ . . _ _ _ _ _ _ _ _ _ ...

3 CN FIM 1 viset ews adut tr$f t 2NNNN 2 Sm LIT **E3 FISE tests 3 ftyp q may3 se1R tr513 8#4 SMRI @IFtLDC * = r,uv s= em.

  • Fu=ta Ft* N rw gu 1so. 3 VE5SE'" Stim FLf34~

> Npg s tw:* sTtsee ruse tu

/E \

l

/ 77 L- = W 51m i e' ~ a / //  % ~

e ,

w -

.l e

[ '5 N '

  • % ~

s s i 5 50. rs

' s N 3- s so. (, _

- -- r.

i g -i E

~

S R R

-s

'....i.... r, us2 ,

o'....l.... [

_1 _____---^_2.

TIME (SEC) TIME (SEC1 1 (MTP-St!MT 2 % set avt e;o in

! artso 2 sr. .esctrer ptTIvrT1 '

3 gyptyg stjgy3g77 3 N M 1EM5FD iftfl(INCpfS$

4 M 188.11Fudi13 4 VSID MsCTID!ff I -

b fELIEF V51.VE FLfDi (D a

132.

A O.

'N i

\ E s w -

s i s

N s  %

do t

, 3_. _

or - - , ....i....  ; - _ , l

, 33

....: ... 2

b. 2. s. s. e.
  • b. 2. t s. v.

CCRE FLCW (%)

TIME (SEC)

Figure 16 - 2680 PolD/T to E002, DCF, TT w/o Byp, 91:

MONT RLD15tl W/0 PRT l TT W/0 BP. DCF 67A-8/73C2H,t&7%P.V, W/2 PUMP TRIP -

n _ __ _

.. - - - ~ _ _ _ _ _ _ _ . ,

,