IR 05000441/1990001

From kanterella
(Redirected from ML20055G388)
Jump to navigation Jump to search
Insp Rept 50-441/90-01 on 900625-28.No Violations Noted. Major Areas Inspected:Preservation Activities Affecting Structures,Components & Matl During Extended Const Delay
ML20055G388
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 07/17/1990
From: Gardner R, Neisler J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20055G384 List:
References
50-441-90-01, 50-441-90-1, NUDOCS 9007230120
Download: ML20055G388 (4)


Text

_ _ _ _ _ _ _ _ _ _ - _ - _ - _ _ _ _ _ _ _ _ _ - _ _ -

.,f

'

4-c.,.

U.S. NUCLEAR REGULATORY COMMISSION REGION 111 l

' Report N /90001(DRS)

Docket No. 50-441 Construction Permit N CPPR-149 i

'

Licensee: The Cleveland Electric 111uminating Company 10 Center Road Perry, OH 44081-Facil_ity Name: Perry Site Inspection At: Perry, Ohio inspection Conducted: June 25-28, 1990

!

, ,

inspector - M A 7 /7 ,I[

.E_N sler Date !

~ Approved By: . ,

IC H. Gar ~dner, Chief 7!/7[O Date 1 Plent Systems Section  ;

Inspection Summary

. Inspection on June 25-28, 1990 (Report No. 50-441/90001(DRS)) l

, Areas' Inspected: Routine announced inspection of Unit 2 preservation {

. activities affecting structures, components and' material during extended- <

construction dela "i Results: No violations'or deviations were. identified. Weaknesses were-identified in' quality verification of repetitive task maintenance and the protection of outside storage conditions of electrical cabl _

'

o s

%

_ _ . . . . . . . . . .

.

m - -

[J y -

.. ,

,

,.

~ '

y m

'

DETAIM v

- Persons' Contacted

The Cleveland Electric Illuminating Company (CEI)

a *E. G. Sterle, Manager, CSS .

'.

_

.

  • G. T. Cad, Lead Contract Administrator, CSS
  • D. W. Conran, Compliance Engineering, LCS
  • R. A DiCola, Operations Engineer, LCS K. :Kutolows_ki, Planner, Repetitive Task, Unit _2 J. Lausberg, Supervisor, QAS
  • M, Manley, Contract Administrator
  • L. Hinter, Supervisor, Quality Verification K. Monroe,-Coordinator, Repetitive Tasks, Unit 2 W. Morris, Quality Engineer R. Solt, Supe _rvisor, Quality Engineering
  • D. Takacs, Manager, Quality Control-J. Zarea, Electricil Engineer U. S. Nuclear Regulato y-Commission-(NRC)  ;

G; 0'Dwyer, Residenttinspector

-

. 1

  • Denotes ~those-persons attending the exit interview conducted on June 28,'41990.

,, . Inspection of Unit.2 Preservation' Activities

.The' inspector reviewed the licensee's current procedures for maintaining stored-in-place plant structures, systems, and material in the outside storage (laydown) areas and components'and materials stored within the warehouse complex. These procedures delineate the. requirements,.

- responsibilities and activities necessary to preserve the plant structures,-

systems,~ components and-materials until the resumption of Unit 2 construction activities. .The procedures appeared adequate to assure the

,

preservatio_n of plant components, t

The licensee'has included the Unit 2 systems and components in the facility wide repetitive-task program, a computerized preventive l maintenance syste Placing the; Unit 2 activities in the repetitive task i system has resulted in improved scheduling of maintenance and preservation l

,

activities involving Unit 2 components and materials, j i

- External Storage Areas The inspector. observed the condition of materials and components ;

i stored in the outside storage' areas, pipe laydown at Parmly Road, -!

the cable-yard near the training center, and tanks and miscellaneous !

material stored in the outdoor areas in the warehouse complex. In

,

i n

l

$

is - .

g .

'

{$ &

=c o 1, i

general, the material and components were'in good condition. Some corrosion.was observed on a few pipe spool pieces and on some safety-related HVAC ducts at the parmly Road laydown area. The licensee' initiated work orders to remove the corrosion and touch ,

up the~ coating on the pipe and duc Several reels of Class 1E cable in the cable yard near the training l center were not protected from the environment. The inspector 1 observed deterioration of cable jackets on the outer layers of j

exposed cable on the unprotected cable reels. The. licensee's maintenance personnel had identified the unprotected cables on the I cable reel maintenance log on May 9, 1990, and is reviewing their options for providing improved protection for the cable reels. In addition to the exposed cable, some of the wooden' reels have- 1 deteriorated and require replacement. The licensee has spare empty reels for re-reeling the cable and initiated work orders to replace 3 the rotted wood reels with sound wood reel :

a The level of quality verification of maintenance and preservation activities ~in the outside storage areas was minimal. Discussions with quality control and quality assurance personnel indicate that

.during 1990, there had been no quality control inspections in the external storage areas and one surveillance that only included areas i in the warehouse complex. At the exit interview,-licensee representatives agreed to review the adequacy of quality control'

l involvement in-the Unit 2 activitie l Warehouse Storage Areas R The inspector toured the licensee's warehouses used for the storag and preservation of Unit 2 partsLand components. The parts and

'

components stored.in the warehouses appeared to be adequately nmaintained and protected to assure their preservation. Heaters wer energized in the large electrical components, desiccants were being replaced at manufacturer's recommended = intervals and nitrogen purges E were being maintained at the required pressures on tanks stored in

-f the warehouse area, In-plant Storage I:

The licensee has uoved the majority of the safety-related structural

'

l steel from the laydown areas to sheltered storage in the Unit 2 heater bays. In the power block, the inspector-examined installed

'

or stored-in-place. components in the drywells, pump rooms, refueling floor, auxiliary building, control building and switch gear room '

Each component inspected had been included in.the Unit 2 maintenance repetitive task program with maintenance performed on schedul '

Equipment was protected from damage by adjacent activity except .in '

the Unit 2 control room where some openings in panels _were not covered and personnel working in the area had tossed paper and trash inside the panels. Other plant areas were adequately clean with all

'

l construction materials and parts properly stored.

L No violations or deviations were identified during this inspectio ;

p

,.

v7'

-

'

,; ,

,

g Oj }< t ,

<

.f4 m m y, ,

,

- i s o_..t- ,

- '

s .,.

-

,:. : . ' Qj ,

n , . . . .

t <

..

p4 "[' 3i: . EEit' Interview'

-

-

,, ,:{ _

7 ,

>r -

.

.

';

%

'

, The inspector met with licensee representatives (denoted in' Paragraph 1):

V"

.

.~at the conclusion. of the inspection and summarizeJ- the scope.and: finding ~

F '

- of.:!the inspection. The. inspector discussed thel hkelyLinformational content'of the inspection report with regard to documents or processes

~ j

reviewed by-the' inspectors during the inspection.
The'. licensee did no '

<'

,

'

, identify any such documents or processes. as, proprietar .. q v,, i n a

]s .

~ , ,

.t

-

-

, .

> L

'

,

E~ 4 -

'

W  !\

r . :i

.

a

I

',

4

-

p;

'

> -'

1 .t, t

,t

..h (.

r

! ,

> \

  • .!'- .: ;:b-

-

,

.

, q ,y  ?  ! I F i 4

. ,

Y ,

'

)

s t '

g

-

' '

y., )

'

'

l;_  !