Comments on Revised Emergency Procedure EP-18.W Lynick Inspected Retention Pond Berm on 900501 & Concluded That Seepage Through Dam &/Or Along Foundation/Embarkment Contact Likely Whenever Pond Levels Rise Above NormalML20043C608 |
Person / Time |
---|
Site: |
05000054 |
---|
Issue date: |
05/18/1990 |
---|
From: |
Zobel S NEW YORK, STATE OF |
---|
To: |
Mcgovern J CINTICHEM, INC. |
---|
References |
---|
NUDOCS 9006050383 |
Download: ML20043C608 (2) |
|
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20155H9301998-11-0404 November 1998 Forwards Listed Canceled Financial Assurance Documents Re Decommissioning of Cintichem Facility in Tuxedo,Ny.Without Encls ML20154H6341998-10-0505 October 1998 Responds to Requesting That Order on Consent for Case D200059005 Be Terminated.Released from All Requirements Set in Order,Effective 981005 ML20237C4981998-08-19019 August 1998 Informs That Commission Has Issued Encl Order Terminating FOL R-81 for Cintichem 5 Megawatt Open Pool Nuclear Research Reactor IAW 901019 Application.Copies of Amend 16 to Idemnity Agreement B-14 Encl for Signature.Se & EA Encl ML20237C5491998-08-19019 August 1998 Informs That NRC Completed Review of Info Submitted by Cintichem,Inc to Support Decommissioning of Tuxedo,Ny Facility.No Further Remediation or Actions W/Respect to NRC Regulated Matl Required,Based on Conclusions ML20197C7691998-07-28028 July 1998 Responds to Requesting Amend to Order on Consent Case D200059005.Amend 10 Which Requires That Sampling of 001 Outfall & Retention Pond Continue Encl ML20236L7321998-06-0808 June 1998 Informs of Completed Review of Final Status Survey Rept for Decommissioning of Bldg 4.Facility May Be Released from Radiological Control.License Termination,Encl ML20236S0211998-06-0202 June 1998 Forwards Confirmatory Surveys of Bldgs & Areas of Cintichem Facility Located in Tuxedo,Ny.Radionuclide Concentration in Bedrock Soil Samples & Orise Resrad Calculation,Encl ML20248D6681998-05-27027 May 1998 Requests That Process for Terminating Licenses R-81 & SNM-639 Be Resumed Due to All Radioactive Matl Having Been Removed as Final Condition for Termination Subject Licenses ML20216C5311998-04-15015 April 1998 Forwards Results of NRC TLD Direct Radiation Monitoring Around Cintichem Facility for Fourth Quarter of 1997.Final Rept Due to Termination of Program ML20217Q6411998-02-10010 February 1998 Responds to Requesting Mod to Ref Order on Consent.Amend 9 to Order,Authorizing Most Changes Requested Enclosed ML20202A8051998-02-0202 February 1998 Forwards Amend 10 to License SNM-639,in Resonse to 971204 Request to Amend Decommissioning Plan for Tuxedo,Ny Facility to Reduce off-site Environ Monitoring Program ML20202E1841998-01-28028 January 1998 Forwards Revised Tables Including Sr-90 Analytical Results. Five Individual Samples from Adjacent Locations Consolidated Into One Sample for Sr-90 Analysis ML20202E1941998-01-28028 January 1998 Forwards Amended Table Which Includes Sr-90 Data Re Final Survey of Soils at 001 Outfall.Conclusion That Survey Results Meet Soils Acceptance Criteria Has Not Changed ML20202E4781998-01-19019 January 1998 Forwards Cintichem Final Status Survey Plan & Rept,Per Section 7 of Licensee Radiopharmaceutical Facilities Decommissioning Plan.W/O Encl ML20199C2511998-01-0202 January 1998 Responds to Concerning Status of mixed-waste at Cintichem Site.Attached Table Presents Overview of Radioactively Contaminated Waste That Remains to Be Disposed of from Decommissioning Project ML20198C8521997-12-23023 December 1997 Forwards Result of NRC TLD Direct Radiation Monitoring Around Cintichem Facility, for Third Quarter of 1997 ML20199B6091997-10-22022 October 1997 Forwards Characterization Rept for Union Carbide Spoils Area Tuxedo,Ny.Area Meets Criteria for Unrestricted Use ML20217G2501997-10-0808 October 1997 Forwards Response to 970819 RAI Re Survey Repts of Hot Laboratory Support Bldgs & Outdoor Areas Inside & Outside of RCA ML20199B6151997-10-0303 October 1997 Responds to 971002 Request for Mod to Order on Consent Case D200059005.Amend to Order on Consent Authorizing Changes Encl ML20199B6601997-10-0202 October 1997 Requests That Order on Consent D200059005 Be Amended to Allow for Delay in Analysis of Water Samples from S-12 for Gamma Emitting Radionuclides,As Currently Done W/Analysis for Sr-90 ML20211C5501997-09-22022 September 1997 Forwards Bedrock Dose Assessment Rept, Which Completes Final Survey Process.W/One Oversize Drawing ML20210R8271997-08-22022 August 1997 Forwards Results of NRC TLD Direct Radiation Monitoring for Second Quarter of 1997 ML20210Q6631997-08-19019 August 1997 Requests That Listed Info Be Submitted in Order to Complete Preliminary Review of Sections 11-18 of Cintichem Final Plant & Rept Submitted by 970606,27,0703,25 & 30 Ltrs ML20210L8541997-08-0505 August 1997 Informs That Responsibility for Non-Power Reactor Insp Program Has Been Transferred from Regional Ofc to Nrr.All Activities Re Non-Power Reactors Including Licensing,Insp & Operator Licensing Will Be Responsibility of NRR ML20149G7981997-07-0303 July 1997 Forwards Chapters 15 & 16 of Final Survey Repts for Cintichem Outdoor Areas Outside Former RCA, Which Describes Cintichem'S Approach to Conducting Final Survey for Areas of Property ML20149G9111997-06-27027 June 1997 Forwards Chapters 13 & 14 Final Survey Repts for Cintichem Outdoor Areas Inside of Former Rca. Chapter 14 Presents Results of Survey ML20140H0591997-04-24024 April 1997 Informs of Completion of All Remediation Work & Final Surveys Per Cintichem Decommissioning Plan.Will Submit Last Sections of Final Survey Rept for Review & Approval in May ML20137W1391997-04-0303 April 1997 Discusses Radiological Characterization Plan for Union Carbide Spoils Area ML20135D1601997-02-21021 February 1997 Forwards Results of TLD Direct Radiation Environ Monitoring Around Facility for Fourth Quarter of 1996 ML20133A4641996-12-20020 December 1996 Forwards Results of NRC TLD Direct Radiation Monitoring Around Cintichem Facility ML20133N0281996-12-19019 December 1996 Informs of Agreement to Extension of Deadlines for Weekly & Monthly Repts in Response to 961206 Request Re Reporting Requirements in Order of Consent Case D200059005 ML20132B6591996-12-0606 December 1996 Informs That License SNM-639 Will Remain in Effect Until Completion of Decommissioning Operations ML20134K7041996-11-14014 November 1996 Advises That SNM-639 License Expires on 961215,per Amend 7 Issued 950118.Request License Remain Effective Through June 1997,allowing Sufficient Time for Completing Work Outlined ML20134F7571996-10-29029 October 1996 Submits Response to Re Radiological Status of Bedrock at Tuxedo,Ny Facility ML20134F7611996-09-25025 September 1996 Provides Comments Re Ground Water Issues Raised at Cintichem Inc Decommissioning Project ML20078N4221995-02-0202 February 1995 Submits Comments Re Cintichem,Inc Decommissioning Proposed Bedrock Criteria ML20078K4791995-02-0101 February 1995 Confirms Discussions Had Yesterday & Morning Re Strontium-90 Analyses of Water Discharged Through 001 Outfall at Cintichem Site ML20059K1891994-01-14014 January 1994 Forwards Insp Repts 50-054/93-03 & 70-0687/93-03 on 931116- 18.No Violations Noted ML20058C9821993-11-22022 November 1993 Provides Results of NRC TLD Direct Radiation Monitoring Around Cintichem Facility for Third Quarter of 1993 ML20057C7521993-09-24024 September 1993 Expresses Appreciation for J Mcgovern Addressing Town Board & Public Re Decommissioning of Cintichem ML20057B7701993-09-14014 September 1993 Forwards FRN Discussing 930726 Final Rule on Decommissioning Recordkeeping & Documentation.W/O Encl ML20056H4001993-09-0101 September 1993 Responds to Re Towns Request for Status Rept on Licensees Decommissioning Project.Advises That Town Board Meeting Will Commence on 930922 & Outline of Planned Presentation Will Be Issued ML20057A5751993-08-31031 August 1993 Forwards Results of TLD Direct Radiation Monitoring at Facility for Second Quarter 1993 ML20056H1131993-08-27027 August 1993 Provides Clarification Re 930715 Exemption Request from Requirements of Revised 10CFR20 ML20056H4061993-05-25025 May 1993 Suggests That Meeting Date Be Set Up for Sept to Hold Discussions on Closing of Cintichem Reactor Facilities ML20128L3931993-02-11011 February 1993 Forwards Potential Effects of Cintichem-Proposed Residual Soil Criteria on Water Quality of Indian Kill Reservoir ML20128F2901993-02-0303 February 1993 Provides Clarification Re Use of Proposed Subsurface Soil Criteria ML20128B8781993-01-28028 January 1993 Confirms Meeting Arrangement W/Cintichem on 930201 in Tuxedo,Ny to Discuss Unrestricted Release Criteria for Soil at Ny Facility ML20127C1521993-01-0707 January 1993 Requests Assistance in Obtaining Info Re Residual Radiation Exposure Criteria for Decontamination & Decommissioning of Licensed Sites.Author Employed by DOE to Provide Assistance ML20127J5791993-01-0404 January 1993 Forwards Listed Proprietary Procedures for Soil from Teledyne,Per .Procedures Withheld 1998-08-19
[Table view] Category:EXTERNAL CORRESPONDENCE
MONTHYEARML20154H6341998-10-0505 October 1998 Responds to Requesting That Order on Consent for Case D200059005 Be Terminated.Released from All Requirements Set in Order,Effective 981005 ML20197C7691998-07-28028 July 1998 Responds to Requesting Amend to Order on Consent Case D200059005.Amend 10 Which Requires That Sampling of 001 Outfall & Retention Pond Continue Encl ML20236L7321998-06-0808 June 1998 Informs of Completed Review of Final Status Survey Rept for Decommissioning of Bldg 4.Facility May Be Released from Radiological Control.License Termination,Encl ML20217Q6411998-02-10010 February 1998 Responds to Requesting Mod to Ref Order on Consent.Amend 9 to Order,Authorizing Most Changes Requested Enclosed ML20202E1941998-01-28028 January 1998 Forwards Amended Table Which Includes Sr-90 Data Re Final Survey of Soils at 001 Outfall.Conclusion That Survey Results Meet Soils Acceptance Criteria Has Not Changed ML20202E4781998-01-19019 January 1998 Forwards Cintichem Final Status Survey Plan & Rept,Per Section 7 of Licensee Radiopharmaceutical Facilities Decommissioning Plan.W/O Encl ML20199C2511998-01-0202 January 1998 Responds to Concerning Status of mixed-waste at Cintichem Site.Attached Table Presents Overview of Radioactively Contaminated Waste That Remains to Be Disposed of from Decommissioning Project ML20199B6151997-10-0303 October 1997 Responds to 971002 Request for Mod to Order on Consent Case D200059005.Amend to Order on Consent Authorizing Changes Encl ML20199B6601997-10-0202 October 1997 Requests That Order on Consent D200059005 Be Amended to Allow for Delay in Analysis of Water Samples from S-12 for Gamma Emitting Radionuclides,As Currently Done W/Analysis for Sr-90 ML20140H0591997-04-24024 April 1997 Informs of Completion of All Remediation Work & Final Surveys Per Cintichem Decommissioning Plan.Will Submit Last Sections of Final Survey Rept for Review & Approval in May ML20137W1391997-04-0303 April 1997 Discusses Radiological Characterization Plan for Union Carbide Spoils Area ML20133N0281996-12-19019 December 1996 Informs of Agreement to Extension of Deadlines for Weekly & Monthly Repts in Response to 961206 Request Re Reporting Requirements in Order of Consent Case D200059005 ML20078K4791995-02-0101 February 1995 Confirms Discussions Had Yesterday & Morning Re Strontium-90 Analyses of Water Discharged Through 001 Outfall at Cintichem Site ML20057C7521993-09-24024 September 1993 Expresses Appreciation for J Mcgovern Addressing Town Board & Public Re Decommissioning of Cintichem ML20056H4001993-09-0101 September 1993 Responds to Re Towns Request for Status Rept on Licensees Decommissioning Project.Advises That Town Board Meeting Will Commence on 930922 & Outline of Planned Presentation Will Be Issued ML20056H4061993-05-25025 May 1993 Suggests That Meeting Date Be Set Up for Sept to Hold Discussions on Closing of Cintichem Reactor Facilities ML20128F2901993-02-0303 February 1993 Provides Clarification Re Use of Proposed Subsurface Soil Criteria ML20043C6081990-05-18018 May 1990 Comments on Revised Emergency Procedure EP-18.W Lynick Inspected Retention Pond Berm on 900501 & Concluded That Seepage Through Dam &/Or Along Foundation/Embarkment Contact Likely Whenever Pond Levels Rise Above Normal ML20043C6371990-05-17017 May 1990 Advises That Listed Issues Re Emergency Procedures EP-18 & EP-19 for Diverting S-7 Water to Site Need to Be Addressed 1998-07-28
[Table view] Category:EXTERNAL LETTERS ROUTED TO NRC
MONTHYEARML20043C6081990-05-18018 May 1990 Comments on Revised Emergency Procedure EP-18.W Lynick Inspected Retention Pond Berm on 900501 & Concluded That Seepage Through Dam &/Or Along Foundation/Embarkment Contact Likely Whenever Pond Levels Rise Above Normal ML20043C6371990-05-17017 May 1990 Advises That Listed Issues Re Emergency Procedures EP-18 & EP-19 for Diverting S-7 Water to Site Need to Be Addressed 1990-05-18
[Table view] |
Text
__ . . _ _ _ _ _ .
~
eh fo-@/
. New York State Department of Environmental Conservation 50 Wolf Road, Albany, New Wrk 12233 May 18, 1990 Thomas C. Jorling Commissioner Mr. James McGovern cintichem, Inc.
P.O. Box B16
Dear Mr,
McGovern:
Your revised emergency procedure, EP-18, for heavy rain alerts has been reviewed by the Department. The following comments are offered:
The Department's letter of May 17, 1990, suggested a modification to EP-18 wherein the retention pond would be kept at a depth of 20" or less'. Your original procedure stated the pond would be kept at 20". The revised EP-18, received May 18, 1990, has eliminated this statement. Additionally, in step 5., which initiates the S-7 diversion, the retention pond maximum depth has l been changed from 35" to 45" without any explanation.
Mr. W. Lynick, Buread of Dam Safety, inspected the retention i pond berm on May 1, 1990, and concluded that:
Seepage through the dam and/or along the foundation / embankment contact is likely whenever pond levels rise above normal.
The constructed embankment when suojected to high pond i
levels may exhibit slope instability and/or piping of the earthfill. .Either of these two conditions could lead to failure of the dam.
l Before this emergency procedure can be put into effect, please explain:
- 1. Why a 45" pond depth was selected for initiating the S-7 diversion.
- 2. At what depth will the retention pond normally be kept?
- 3. The telefaxed copy of pictures of the diversion structure was not clear enough to easily discern the structure's details. Please provide a detailed sketch of the structure or better copies of the photographs.
9006050383 900518 FDR ADOCK 050000'.4 1 i P PDC f
\
]/ >o
IL , 't
.-_,.'6 If you have any questions, please contact me at:
NYS Department of Environmental Conservation Bureau of Radiation, Room 510 I 50 Wolf Road Albany,_NY 12233-7255 or (518) 457-2225.
Sincerely !
l L !
1 !
L !
Steven Z il Environmental Radiation Specialist i